Skip to Main Navigation

ID-Geothermal Energy Upstream Development

Key Details

Project Details

  • P161644

  • Active

  • Muchsin Qadir , Maria Ayuso Olmedo

  • PT Sarana Multi Infrastruktur (Persero)

  • Indonesia

  • December 10, 2015

  • (as of board presentation)

    February 9, 2017

  • August 4, 2017

  • US$ 6.25 million

  • PT Sarana Multi Infrastruktur (Persero),PT Geo Dipa Energi

  • East Asia and Pacific

  • 2017

  • US$ 6.25 million

  • A

  • Not Applicable

  • December 31, 2025

  • TBD

  • BANK APPROVED

  • P155047

  • October 7, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 6.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 6.25
Total Project Cost** 6.25

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2023-10-05
Counterpart Funding Satisfactory 2023-10-05
Project Management Moderately Unsatisfactory 2023-10-05
Monitoring and Evaluation Satisfactory 2023-10-05
Progress towards achievement of PDO Moderately Unsatisfactory 2023-10-05
Financial Management Moderately Satisfactory 2023-10-05
Overall Implementation Progress (IP) Moderately Unsatisfactory 2023-10-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.