Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 4.80 |
P161757
Closed
Kristoffer Welsien , Sylvestre Bea
United Republic of Tanzania
November 2, 2016
(as of board presentation)
September 7, 2017
September 9, 2019
US$ 4.80 million
Ministry of Water and Irrigation,TIB Development Bank Limited
2018
US$ 4.80 million
N/A
September 6, 2024
August 31, 2022
BANK APPROVED
Financier | Commitments |
---|---|
Global Partnership on Output-based Aid | 4.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.80 |
Total Project Cost** | 4.80 |
Name | Review | Date |
---|---|---|
Overall | Satisfactory | 2021-12-17 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-12-17 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-12-17 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-24-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of other water service providers that the project is supporting | Value | 0.00 | 110.00 | 110.00 |
Date | October 29, 2018 | February 28, 2022 | August 31, 2022 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 500000.00 | 472436.00 |
Date | October 29, 2018 | February 28, 2022 | August 31, 2022 | |
Comment |
Voume(mass) of COD pollution load reduction achieved under the project | Value | 0.00 | 1000.00 | 1087.00 |
Date | October 29, 2018 | February 28, 2022 | August 31, 2022 | |
Comment |
Female beneficiaries | Value | 0.00 | 51.00 | 51.00 |
Date | October 29, 2018 | February 28, 2022 | August 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of CBWSOs sensitized and trained | Value | 0.00 | 110.00 | 110.00 |
Date | October 29, 2018 | February 28, 2022 | December 1, 2021 | |
Comment |