Accelerating Solar Water Pumping via Innovative Financing

Development Objective

The Project Development Objective is to support sustainable access to water in selected rural communities of Tanzania.

Key Details

Project Details

  • P161757

  • Closed

  • Kristoffer Welsien , Sylvestre Bea

  • United Republic of Tanzania

  • Tanzania

  • November 2, 2016

  • (as of board presentation)

    September 7, 2017

  • September 9, 2019

  • US$ 4.80 million

  • Ministry of Water and Irrigation,TIB Development Bank Limited

  • Eastern and Southern Africa

  • 2018

  • US$ 4.80 million

  • N/A

  • September 6, 2024

  • August 31, 2022

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Partnership on Output-based Aid 4.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 4.80
Total Project Cost** 4.80

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Satisfactory 2021-12-17
Progress towards achievement of PDO Moderately Satisfactory 2021-12-17
Overall Implementation Progress (IP) Moderately Satisfactory 2021-12-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 04-24-2023
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of other water service providers that the project is supportingValue0.00110.00110.00
    DateOctober 29, 2018February 28, 2022August 31, 2022
    Comment
  • Direct project beneficiariesValue0.00500000.00472436.00
    DateOctober 29, 2018February 28, 2022August 31, 2022
    Comment
  • Voume(mass) of COD pollution load reduction achieved under the projectValue0.001000.001087.00
    DateOctober 29, 2018February 28, 2022August 31, 2022
    Comment
  • Female beneficiariesValue0.0051.0051.00
    DateOctober 29, 2018February 28, 2022August 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of CBWSOs sensitized and trainedValue0.00110.00110.00
    DateOctober 29, 2018February 28, 2022December 1, 2021
    Comment