Financier | Commitments |
---|---|
IDA Credit | 100.00 |
P161764
Dropped
Wilhelmus Gerardus Janssen , Azeb Mekonnen
GOVERNMENT OF TANZANIA
October 26, 2016
(as of board presentation)
N/A
N/A
US$ 100.00 million
Ministry of Agriculture, Livestock and Fisheries
2018
US$ 100.00 million
B
Not Applicable
N/A
Yes
BEGIN NEGOTIATION
December 19, 2024
Financier | Commitments |
---|---|
IDA Credit | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of farmers producing non-rice crops or engaging in other agricultural enterprises | Value | 35.00 | 0.00 | 80.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Percentage of farmers adopting sustainable climate-resilient technologies | Value | 10.00 | 0.00 | 65.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Annual average sales from agriculture production in targeted irrigation schemes | Value | 16970000.00 | 0.00 | 33950000.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of business plans of IOs developed and approved as a result of the project | Value | 0.00 | 0.00 | 20.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Percentage of households adopting healthy eating practices | Value | 30.00 | 0.00 | 75.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Number of participating IOs having contractual arrangements with buyers | Value | 1.00 | 0.00 | 20.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Percentage of farmers adopting postharvest handling and management practices | Value | 25.00 | 0.00 | 70.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Percentage of the planned O&M costs covered by collected irrigation service fees | Value | 0.00 | 0.00 | 50.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Overall productivity of water for agriculture | Value | 694.00 | 0.00 | 1041.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Annual average yield for paddy in targeted irrigation schemes | Value | 3.80 | 0.00 | 7.60 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Area provided with irrigation and drainage services (ha) | Value | 0.00 | 0.00 | 14900.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Area provided with irrigation and drainage services - Improved (ha) | Value | 0.00 | 0.00 | 14771.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Number of IOs with Annual Budgets and O&M plans | Value | 13.00 | 0.00 | 20.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Number of new knowledge packages and lessons learned generated | Value | 0.00 | 0.00 | 22.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Beneficiary satisfaction rate with services provided by the project (of which female and youth 15-24) | Value | 0.00 | 0.00 | 85.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Number of government staff that have been trained through the project (disaggregated by gender) | Value | 0.00 | 0.00 | 141.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |
Time between request from government to making funds available to respond to an eligible crisis | Value | 8.00 | 0.00 | 3.00 |
Date | March 6, 2017 | March 31, 2023 | ||
Comment |