Financier | Commitments |
---|---|
IDA Grant | 115.00 |
P161777
Active
Jaime Palalane , Paulo Sithoe
Ministry of Economy and Finance
September 28, 2017
(as of board presentation)
May 22, 2019
September 27, 2019
US$ 115.00 million
National Directorate of Water Supply and Sanitation (DNAAS),Administração de Infraestruturas de Água e Saneamento (AIAS),Ministry of Health
2019
US$ 115.00 million
A
Not Applicable
September 30, 2025
BANK APPROVED
June 18, 2024
Financier | Commitments |
---|---|
IDA Grant | 115.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 115.00 |
IBRD + IDA Commitment | 115.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 115.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 7, 2022 | IDA-D4750 | Loan Disb | 275,569.44 |
May 31, 2022 | IDA-D4750 | Loan Disb | 733,717.90 |
Dec 20, 2021 | IDA-D4750 | Loan Disb | 78,799.99 |
Feb 9, 2022 | IDA-D4750 | Loan Disb | 1,968,430.50 |
Feb 9, 2022 | IDA-D4750 | Loan Disb | 1,544,798.10 |
Aug 26, 2022 | IDA-D4750 | Loan Disb | 19,033.33 |
Feb 1, 2022 | IDA-D4750 | Loan Disb | 2,964,000.00 |
Jan 31, 2022 | IDA-D4750 | Loan Disb | 68,588.32 |
Jan 31, 2022 | IDA-D4750 | Loan Disb | 645,000.00 |
Dec 29, 2021 | IDA-D4750 | Loan Disb | 551,200.00 |
Feb 14, 2022 | IDA-D4750 | Loan Disb | 674,368.90 |
Sep 1, 2022 | IDA-D4750 | Loan Disb | 44,090.91 |
Aug 23, 2022 | IDA-D4750 | Loan Disb | 132,708.22 |
Aug 23, 2022 | IDA-D4750 | Loan Disb | 61,275.01 |
Aug 9, 2022 | IDA-D4750 | Loan Disb | 557,918.30 |
Aug 10, 2022 | IDA-D4750 | Loan Disb | 671,112.20 |
May 2, 2023 | IDA-D4750 | Loan Disb | 1,392,240.50 |
Oct 13, 2022 | IDA-D4750 | Loan Disb | 22,532.00 |
Dec 8, 2022 | IDA-D4750 | Loan Disb | 44,818.18 |
Dec 8, 2022 | IDA-D4750 | Loan Disb | 13,078.99 |
Dec 8, 2022 | IDA-D4750 | Loan Disb | 10,155.00 |
Dec 14, 2022 | IDA-D4750 | Loan Disb | 17,888.64 |
Nov 3, 2022 | IDA-D4750 | Loan Disb | 1,588,346.90 |
Dec 14, 2022 | IDA-D4750 | Loan Disb | 1,562,461.10 |
Dec 8, 2022 | IDA-D4750 | Loan Disb | 120,200.00 |
Dec 8, 2022 | IDA-D4750 | Loan Disb | 118,200.00 |
Oct 27, 2022 | IDA-D4750 | Loan Disb | 3,072,522.00 |
Oct 26, 2022 | IDA-D4750 | Loan Disb | 840,386.30 |
Feb 17, 2023 | IDA-D4750 | Loan Disb | 731,694.25 |
Sep 8, 2023 | IDA-D4750 | Loan Disb | 11,628.30 |
Jul 12, 2023 | IDA-D4750 | Loan Disb | 70,323.11 |
Sep 11, 2023 | IDA-D4750 | Loan Disb | 95,585.08 |
Nov 16, 2023 | IDA-D4750 | Loan Disb | 1,493,311.10 |
Oct 21, 2020 | IDA-D4750 | Loan Disb | 1,174,940.40 |
Mar 18, 2021 | IDA-D4750 | Loan Disb | 10,481.10 |
Mar 18, 2021 | IDA-D4750 | Loan Disb | 31,443.27 |
Feb 1, 2021 | IDA-D4750 | Loan Disb | 15,000,000.00 |
Feb 1, 2021 | IDA-D4750 | Loan Disb | 42,692.04 |
Jan 19, 2021 | IDA-D4750 | Loan Disb | 5,400.00 |
Jun 22, 2021 | IDA-D4750 | Loan Disb | 78,800.00 |
Apr 16, 2021 | IDA-D4750 | Loan Disb | 1,082,086.20 |
Apr 14, 2021 | IDA-D4750 | Loan Disb | 55,079.80 |
Feb 23, 2021 | IDA-D4750 | Loan Disb | 1,113,942.90 |
Nov 8, 2021 | IDA-D4750 | Loan Disb | 743,604.60 |
Aug 10, 2021 | IDA-D4750 | Loan Disb | 1,017,252.75 |
Sep 17, 2021 | IDA-D4750 | Loan Disb | 5,000,000.00 |
Sep 24, 2021 | IDA-D4750 | Loan Disb | 30,050.00 |
Sep 24, 2021 | IDA-D4750 | Loan Disb | 78,800.00 |
Sep 27, 2021 | IDA-D4750 | Loan Disb | -78,800.00 |
Jun 23, 2021 | IDA-D4750 | Loan Disb | -78,800.00 |
Jul 15, 2021 | IDA-D4750 | Loan Disb | 1,046,558.06 |
Apr 21, 2022 | IDA-D4750 | Loan Disb | 743,729.25 |
May 27, 2022 | IDA-D4750 | Loan Disb | 138,697.44 |
Jun 7, 2022 | IDA-D4750 | Loan Disb | 122,382.22 |
Jul 22, 2022 | IDA-D4750 | Loan Disb | 78,800.00 |
Jul 8, 2022 | IDA-D4750 | Loan Disb | 36,104.93 |
Nov 29, 2021 | IDA-D4750 | Loan Disb | 702,881.60 |
Nov 29, 2021 | IDA-D4750 | Loan Disb | 150,250.00 |
Mar 16, 2020 | IDA-D4750 | Loan Disb | 5,000,000.00 |
Mar 10, 2020 | IDA-D4750 | Loan Disb | 4,057,621.00 |
Sep 27, 2019 | IDA-D4750 | Loan Disb | 1,602,000.00 |
Mar 12, 2024 | IDA-D9330 | Loan Disb | 1,084,233.90 |
Mar 15, 2024 | IDA-D9330 | Loan Disb | 469,151.66 |
Oct 3, 2023 | IDA-D9330 | Loan Disb | 107,259.61 |
Mar 27, 2024 | IDA-D9330 | Loan Disb | 469,173.94 |
May 3, 2024 | IDA-D9330 | Loan Disb | 321,906.03 |
Dec 9, 2021 | IDA-D9330 | Loan Commitment | 50,000,000.00 |
May 22, 2019 | IDA-D4750 | Loan Commitment | 115,000,000.00 |
Dec 27, 2023 | IDA-D9330 | Loan Disb | 107,259.60 |
Sep 27, 2023 | IDA-D9330 | Loan Disb | 46,185.69 |
Dec 27, 2022 | IDA-D9330 | Loan Disb | 1,000,000.00 |
Oct 12, 2022 | IDA-D9330 | Loan Disb | 5,000,000.00 |
Jun 24, 2024 | IDA-D9330 | Loan Disb | 2,154,014.00 |
Jan 31, 2024 | IDA-D9330 | Loan Disb | 114,126.80 |
Feb 2, 2024 | IDA-D9330 | Loan Disb | 315,461.50 |
Apr 29, 2024 | IDA-D9330 | Loan Disb | 1,288,031.20 |
Mar 12, 2024 | IDA-D9330 | Loan Disb | 1,084,285.40 |
Mar 12, 2024 | IDA-D9330 | Loan Disb | 47,625.01 |
Jan 18, 2024 | IDA-D4750 | Loan Disb | 121,596.00 |
Oct 17, 2023 | IDA-D4750 | Loan Disb | 57,941.00 |
Dec 6, 2023 | IDA-D4750 | Loan Disb | 769,361.20 |
Aug 2, 2023 | IDA-D4750 | Loan Disb | 661,093.00 |
Sep 7, 2023 | IDA-D4750 | Loan Disb | 52,393.19 |
Jun 26, 2024 | IDA-D4750 | Loan Disb | 1,678,133.10 |
Mar 15, 2024 | IDA-D4750 | Loan Disb | 71,550.80 |
Aug 28, 2024 | IDA-D4750 | Loan Disb | 30,275.00 |
May 8, 2024 | IDA-D4750 | Loan Disb | 28,590.00 |
Aug 29, 2024 | IDA-D4750 | Loan Disb | 28,138.06 |
Oct 26, 2023 | IDA-D4750 | Loan Disb | 732,346.06 |
Jan 18, 2024 | IDA-D4750 | Loan Disb | 39,405.77 |
Nov 7, 2023 | IDA-D4750 | Loan Disb | 118,200.00 |
Nov 7, 2023 | IDA-D4750 | Loan Disb | 71,470.00 |
Jul 30, 2024 | IDA-D4750 | Loan Disb | 28,590.00 |
Jun 24, 2024 | IDA-D4750 | Loan Disb | 1,793,902.20 |
May 8, 2024 | IDA-D4750 | Loan Disb | -28,540.00 |
Jun 24, 2024 | IDA-D4750 | Loan Disb | 893,261.90 |
May 9, 2024 | IDA-D4750 | Loan Disb | 731,275.20 |
Mar 1, 2024 | IDA-D4750 | Loan Disb | 3,342,849.80 |
Feb 12, 2024 | IDA-D4750 | Loan Disb | 152,042.06 |
Jan 30, 2024 | IDA-D4750 | Loan Disb | 1,192,800.50 |
Mar 29, 2024 | IDA-D4750 | Loan Disb | 3,582,907.20 |
Sep 27, 2021 | IDA-D4750 | Loan Disb | 1,023,886.40 |
Sep 10, 2021 | IDA-D4750 | Loan Disb | 3,127,283.20 |
Nov 23, 2021 | IDA-D4750 | Loan Disb | 78,800.01 |
Oct 12, 2021 | IDA-D4750 | Loan Disb | 78,800.01 |
Dec 15, 2021 | IDA-D4750 | Loan Disb | 6,922,864.50 |
Mar 23, 2022 | IDA-D4750 | Loan Disb | 520,931.88 |
Jun 8, 2022 | IDA-D4750 | Loan Disb | 78,421.21 |
Oct 13, 2021 | IDA-D4750 | Loan Disb | -78,800.00 |
Feb 18, 2022 | IDA-D4750 | Loan Disb | 1,597,164.20 |
Nov 23, 2021 | IDA-D4750 | Loan Disb | -78,800.01 |
Apr 6, 2022 | IDA-D4750 | Loan Disb | 20,358.33 |
Apr 6, 2022 | IDA-D4750 | Loan Disb | 9,630.01 |
Apr 6, 2022 | IDA-D4750 | Loan Disb | 33,705.05 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-11-21 |
Progress towards achievement of PDO | Satisfactory | 2024-11-21 |
Procurement | Satisfactory | 2024-11-21 |
Financial Management | Moderately Satisfactory | 2024-11-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-21 |
Overall Safeguards Rating | Moderately Unsatisfactory | 2024-11-21 |
Overall Implementation Progress (IP) | Satisfactory | 2024-11-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cities with an operational sanitation entity compliant with Government regulatory framework | Value | 2.00 | 5.00 | 5.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
People provided with access to safely managed sanitation | Value | 0.00 | 12500.00 | 103045.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Students provided with access to improved school sanitation facilities | Value | 0.00 | 163784.00 | 145925.00 |
Date | November 23, 2021 | April 15, 2024 | September 30, 2025 | |
Comment |
Municipal bylaws approved and published | Value | 2.00 | 5.00 | 5.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Of which 50% are women | Value | 0.00 | 4000.00 | 51523.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Of which 40% are from the poorest quintiles of the population | Value | 0.00 | 2500.00 | 41218.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Sewer connections receiving safely managed sanitation services | Value | 0.00 | 2500.00 | 15609.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Household sanitation facilities receiving safely managed sanitation services | Value | 0.00 | 0.00 | 25000.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
User fees deposited in sanitation entity bank account | Value | 0.00 | 3477888.00 | 3200000.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
City Wide inclusive sanitation plans prepared | Value | 0.00 | 0.00 | 2.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Decrease in missed school days for girls | Value | 0.00 | 0.00 | 30.00 |
Date | November 23, 2021 | April 15, 2024 | September 30, 2025 | |
Comment |
BoD5 removed from septage and fecal sludge | Value | 0.00 | 0.00 | 746.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Sanitation performance improvement plans prepared by sanitation entity and approved by council | Value | 0.00 | 5.00 | 5.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Draft Water and Sanitation Law submitted to Parliament | Value | No | Yes | Yes |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Of which new connections | Value | 0.00 | 0.00 | 600.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
BoD5 removed from wastewater | Value | 0.00 | 0.00 | 2576.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Girls provided with access to improved school sanitation facilities and MHM education programs | Value | 0.00 | 87640.00 | 87555.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Customer satisfaction index for sanitation services | Value | 0.00 | 0.00 | 80.00 |
Date | June 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Length of sewers laid | Value | 0.00 | 0.00 | 38.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
People reached by sanitation marketing campaign to promote on-site sanitation financed under the project | Value | 0.00 | 0.00 | 133193.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |
Public sanitation facilities constructed (schools/markets) | Value | 0.00 | 94.00 | 110.00 |
Date | January 30, 2019 | April 15, 2024 | September 30, 2025 | |
Comment |