Salado Integrated River Basin Management Support Project

Abstract*

The objective of the Salado Integrated River Basin Management Support Project for Argentina is to enhance flood protection and strengthen the capacity of the responsible institutions for integrated water resources monitoring and management in the Salado River Basin. The project has 3 components. (1) Integrated water resources management component will strengthen institutional capacity for water resources management and environmental and hydrological...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to (a) enhance flood protection and strengthen the capacity of the institutions responsible for integrated water resources monitoring and management in the Salado River Basin; and (b) support improved living conditions for Selected Beneficiaries in the Province of Buenos Aires as part of the COVID-19 pandemic recovery

Key Details

Project Details

  • P161798

  • Active

  • Nicolaas de Groot , Emma Phillips, Carina Lakovits

  • Province of Buenos Aires

  • Argentina

  • January 24, 2017

  • (as of board presentation)

    April 6, 2017

  • April 12, 2018

  • US$ 375.00 million

  • Ministry of Treasury and Finance,Ministry of Infrastructure and Public Services, Province of Buenos Aires,Undersecretary of International Financing Coordination and Execution, Ministry of Habitat and Urban

  • Latin America and Caribbean

  • 2017

  • US$ 300.00 million

  • A

  • March 13, 2024

  • December 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00
Borrower/Recipient 75.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 375.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2020 IBRD-87360 Loan Disb -6,000,000.00
Sep 15, 2020 IBRD-87360 Loan Disb 6,000,000.00
Jun 2, 2020 IBRD-87360 Loan Disb 6,000,000.00
Sep 15, 2019 IBRD-87360 Int Charges 358,856.16
Sep 15, 2019 IBRD-87360 Int Charges 124,302.22
Sep 15, 2019 IBRD-87360 Int Charges 14,106.66
Sep 15, 2019 IBRD-87360 Int Charges 131,662.22
Sep 15, 2019 IBRD-87360 Loan Disb -23,000,000.00
Sep 15, 2019 IBRD-87360 Loan Disb 23,000,000.00
Mar 15, 2020 IBRD-87360 Int Charges 15,736.52
Mar 15, 2020 IBRD-87360 Int Charges 335,267.53
Mar 15, 2020 IBRD-87360 Int Charges 11,526.67
Mar 15, 2020 IBRD-87360 Int Charges 107,582.22
Mar 15, 2020 IBRD-87360 Int Charges 353,484.44
Mar 15, 2020 IBRD-87360 Int Charges 1,130.14
Sep 4, 2019 IBRD-87360 Loan Disb 15,000,000.00
Apr 19, 2021 IBRD-87360 Loan Disb 9,000,000.00
May 25, 2021 IBRD-87360 Loan Disb 12,000,000.00
Mar 15, 2021 IBRD-87360 Int Charges 4,826.67
Mar 15, 2021 IBRD-87360 Int Charges 45,048.89
Mar 15, 2021 IBRD-87360 Int Charges 148,017.77
Mar 15, 2021 IBRD-87360 Int Charges 38,613.34
Mar 15, 2021 IBRD-87360 Int Charges 288,808.88
Mar 15, 2021 IBRD-87360 Loan Disb -20,000,000.00
Mar 15, 2021 IBRD-87360 Loan Disb 20,000,000.00
Mar 15, 2021 IBRD-87360 Int Charges 24,858.21
Mar 15, 2021 IBRD-87360 Int Charges 52,302.22
Feb 9, 2021 IBRD-87360 Loan Disb 9,000,000.00
Dec 4, 2020 IBRD-87360 Loan Disb 6,000,000.00
Mar 15, 2022 IBRD-87360 Int Charges 4,449.58
Mar 15, 2022 IBRD-87360 Int Charges 41,529.44
Mar 15, 2022 IBRD-87360 Int Charges 136,453.89
Mar 15, 2022 IBRD-87360 Int Charges 35,596.67
Mar 15, 2022 IBRD-87360 Int Charges 106,238.93
Mar 15, 2022 IBRD-87360 Int Charges 12,416.63
Mar 15, 2022 IBRD-87360 Int Charges 237,311.11
Mar 15, 2022 IBRD-87360 Int Charges 260.27
Mar 15, 2022 IBRD-87360 Int Charges 1,016.95
Mar 15, 2022 IBRD-87360 Int Charges 249,988.02
Mar 15, 2022 IBRD-87360 Loan Disb -10,000,000.00
Apr 12, 2022 IBRD-87360 Loan Disb 12,000,000.00
Sep 15, 2021 IBRD-87360 Int Charges 2,095.89
Sep 15, 2021 IBRD-87360 Int Charges 8,784.11
Sep 15, 2021 IBRD-87360 Int Charges 277,209.03
Sep 15, 2021 IBRD-87360 Int Charges 10,619.73
Sep 15, 2021 IBRD-87360 Int Charges 90,649.17
Sep 15, 2021 IBRD-87360 Int Charges 4,638.34
Sep 15, 2021 IBRD-87360 Int Charges 43,291.10
Sep 15, 2021 IBRD-87360 Int Charges 142,242.22
Sep 15, 2021 IBRD-87360 Int Charges 37,106.66
Sep 15, 2021 IBRD-87360 Int Charges 123,688.90
Mar 15, 2024 IBRD-87360 Int Charges 1,357,122.80
Mar 15, 2024 IBRD-87360 Int Charges 145,422.22
Mar 15, 2024 IBRD-87360 Int Charges 339,280.70
Mar 15, 2024 IBRD-87360 Int Charges 678,561.30
Mar 15, 2024 IBRD-87360 Int Charges 3,591.53
Mar 15, 2024 IBRD-87360 Int Charges 384.80
Mar 15, 2024 IBRD-87360 Int Charges 11,800.73
Mar 15, 2024 IBRD-87360 Int Charges 3,078.44
Mar 15, 2024 IBRD-87360 Int Charges 10,261.50
Mar 15, 2024 IBRD-87360 Int Charges 20,523.01
Mar 15, 2024 IBRD-87360 Int Charges 5,130.73
Mar 15, 2024 IBRD-87360 Int Charges 101,784.20
Jul 19, 2024 IBRD-87360 Loan Disb 6,000,000.00
May 28, 2024 IBRD-87360 Loan Cancel 47,160,000.00
Sep 15, 2020 IBRD-87360 Int Charges 334,098.38
Sep 15, 2020 IBRD-87360 Int Charges 30,099.99
Sep 15, 2020 IBRD-87360 Int Charges 6,593.34
Sep 15, 2020 IBRD-87360 Int Charges 61,537.78
Sep 15, 2020 IBRD-87360 Int Charges 202,195.56
Sep 23, 2020 IBRD-87360 Loan Disb 5,000,000.00
Sep 15, 2022 IBRD-87360 Int Charges 1,986.31
Sep 15, 2022 IBRD-87360 Int Charges 7,519.25
Sep 15, 2022 IBRD-87360 Int Charges 221,220.47
Sep 15, 2022 IBRD-87360 Int Charges 7,423.36
Aug 8, 2022 IBRD-87360 Loan Disb 8,000,000.00
Feb 14, 2022 IBRD-87360 Loan Disb 10,000,000.00
Mar 15, 2022 IBRD-87360 Loan Disb 10,000,000.00
Sep 13, 2021 IBRD-87360 Loan Disb 19,000,000.00
Sep 15, 2021 IBRD-87360 Loan Disb -40,000,000.00
Sep 15, 2021 IBRD-87360 Loan Disb 40,000,000.00
Mar 15, 2023 IBRD-87360 Loan Disb 3,000,000.00
Mar 15, 2023 IBRD-87360 Int Charges 40,602.03
Mar 15, 2023 IBRD-87360 Int Charges 855.44
Mar 15, 2023 IBRD-87360 Int Charges 7,984.17
Mar 15, 2023 IBRD-87360 Int Charges 26,233.72
Mar 15, 2023 IBRD-87360 Int Charges 6,843.58
Mar 15, 2023 IBRD-87360 Int Charges 1,069,528.00
Mar 15, 2023 IBRD-87360 Int Charges 22,811.92
Dec 6, 2022 IBRD-87360 Loan Disb 3,000,000.00
Mar 15, 2023 IBRD-87360 Int Charges 267,382.00
Mar 15, 2023 IBRD-87360 Int Charges 534,764.00
Mar 15, 2023 IBRD-87360 Int Charges 45,623.84
Mar 15, 2023 IBRD-87360 Int Charges 11,405.97
Mar 15, 2023 IBRD-87360 Int Charges 212,748.28
Mar 15, 2023 IBRD-87360 Int Charges 47,496.09
Mar 15, 2023 IBRD-87360 Int Charges 20,053.64
Mar 15, 2023 IBRD-87360 Int Charges 187,167.40
Mar 15, 2023 IBRD-87360 Int Charges 614,978.56
Mar 15, 2023 IBRD-87360 Int Charges 160,429.20
Mar 15, 2023 IBRD-87360 Int Charges 534,764.00
Mar 15, 2023 IBRD-87360 Int Charges 2,082.20
Mar 15, 2023 IBRD-87360 Loan Disb -3,000,000.00
Sep 15, 2022 IBRD-87360 Int Charges 117,724.84
Sep 15, 2022 IBRD-87360 Int Charges 8,188.81
Sep 15, 2022 IBRD-87360 Int Charges 109,184.13
Sep 15, 2022 IBRD-87360 Int Charges 76,428.89
Mar 15, 2019 IBRD-87360 Loan Disb -7,000,000.00
Mar 15, 2019 IBRD-87360 Loan Disb 7,000,000.00
Apr 16, 2019 IBRD-87360 Loan Disb 8,000,000.00
Mar 15, 2019 IBRD-87360 Int Charges 366,625.00
Mar 15, 2019 IBRD-87360 Int Charges 62,815.28
Mar 15, 2019 IBRD-87360 Int Charges 13,386.47
Dec 14, 2018 IBRD-87360 Loan Disb 7,000,000.00
Sep 15, 2018 IBRD-87360 Int Charges 426,595.90
Sep 15, 2018 IBRD-87360 Int Charges 10,595.00
Sep 15, 2018 IBRD-87360 Loan Disb -750,000.00
Sep 15, 2018 IBRD-87360 Loan Disb 750,000.00
Apr 12, 2018 IBRD-87360 Loan Disb 750,000.00
Apr 12, 2018 IBRD-87360 Fee Charges 750,000.00
Apr 6, 2017 IBRD-87360 Loan Commitment 300,000,000.00
Sep 15, 2022 IBRD-87360 Int Charges 251,123.50
Sep 15, 2022 IBRD-87360 Int Charges 65,510.47
Sep 15, 2022 IBRD-87360 Int Charges 218,368.27
Sep 15, 2022 IBRD-87360 Int Charges 436,736.50
Sep 15, 2022 IBRD-87360 Loan Disb -20,000,000.00
Sep 15, 2022 IBRD-87360 Loan Disb 20,000,000.00
Sep 15, 2023 IBRD-87360 Int Charges 17,366.44
Sep 15, 2023 IBRD-87360 Int Charges 15,277.51
Sep 15, 2023 IBRD-87360 Int Charges 3,819.37
Sep 15, 2023 IBRD-87360 Int Charges 7,638.75
Sep 15, 2023 IBRD-87360 Int Charges 214,561.64
Sep 15, 2023 IBRD-87360 Int Charges 23,039.63
Sep 15, 2023 IBRD-87360 Int Charges 215,036.45
Sep 15, 2023 IBRD-87360 Int Charges 706,548.40
Sep 15, 2023 IBRD-87360 Int Charges 184,316.95
Sep 15, 2023 IBRD-87360 Int Charges 614,389.90
Sep 15, 2023 IBRD-87360 Int Charges 1,228,779.80
Sep 15, 2023 IBRD-87360 Int Charges 289,828.50
Sep 15, 2023 IBRD-87360 Int Charges 614,389.90
Sep 15, 2023 IBRD-87360 Int Charges 8,784.57
Sep 15, 2023 IBRD-87360 Int Charges 2,291.62
Sep 15, 2023 IBRD-87360 Int Charges 7,638.75
Sep 15, 2023 IBRD-87360 Int Charges 979.94
Sep 15, 2023 IBRD-87360 Int Charges 286.46
Sep 15, 2023 IBRD-87360 Int Charges 2,673.56
Sep 15, 2023 IBRD-87360 Int Charges 92,158.48
Mar 15, 2024 IBRD-87360 Int Charges 66,571.47
Mar 15, 2024 IBRD-87360 Int Charges 25,446.06
Mar 15, 2024 IBRD-87360 Int Charges 237,496.45
Mar 15, 2024 IBRD-87360 Int Charges 780,345.56
Mar 15, 2024 IBRD-87360 Int Charges 10,261.50
Mar 15, 2024 IBRD-87360 Int Charges 1,539.23
Mar 15, 2024 IBRD-87360 Int Charges 203,568.40
Mar 15, 2024 IBRD-87360 Int Charges 678,561.30

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2024-12-17
Project Management Moderately Satisfactory 2024-12-17
Financial Management Satisfactory 2024-12-17
Monitoring and Evaluation Satisfactory 2024-12-17
Financial Management Satisfactory 2024-12-17
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-17
Procurement Moderately Unsatisfactory 2024-12-17
Monitoring and Evaluation Satisfactory 2024-12-17
Progress towards achievement of PDO Moderately Satisfactory 2024-12-17
Project Management Moderately Satisfactory 2024-12-17
Progress towards achievement of PDO Moderately Satisfactory 2024-12-17
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-17

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Hydromet Information System is used for integrated water resource monitoringValueNoNoYes
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • People benefiting from reduced flood risk.Value0.0065000.0075000.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Environmental and Wetlands Management Plan for the Salado River Basin developedValueNoNoYes
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Number of people benefiting from new social housingValue0.000.005400.00
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Female BeneficiariesValue0.000.0050.00
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Female beneficiariesValue50.0050.0050.00
    DateMarch 7, 2017February 8, 2018December 30, 2022
    Comment
  • Area under enhanced flood protectionValue0.00375.00435.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of hydromet stations installed and operationalValue59.0059.00162.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Km of river hydraulically enhancedValue223.00257.00257.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Project-related grievances registered and addressed under the Project Grievance Redress Mechanism.Value0.00100.00100.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Number of social housing units constructedValue0.000.001200.00
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Wetlands identified in the river basin and objectives and measures for protection defined and agreed by DPOH, ADA and OPDS.ValueNoNoYes
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Percentage of volume of river sediments/soil safely disposed in recintosValue0.00100.00100.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Number of direct jobs generated through the construction of social housingValue0.000.002400.00
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Development of the supply side of the water balance in the main Salado River BasinValueNoNoYes
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Number of bridges with increased resilience to flood events.Value0.000.005.00
    DateMarch 7, 2017February 28, 2024December 30, 2023
    Comment
  • Digital Terrain Model for the main Salado River Basin developed using LIDAR technologyValueNoNoYes
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Automatization of electronic administration processes to improve water governanceValueNoNoYes
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Number of regional monitoring centers establishedValue0.000.0017.00
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment
  • Proposal for restructuring the river basin committeesValueNoNoYes
    DateFebruary 25, 2021February 28, 2024December 30, 2023
    Comment