Financier | Commitments |
---|---|
IDA Credit | 15.00 |
P161923
Active
Philippe Neves , Nabil Samir
Ministry of Economy, Planning, and Regional Integration
March 15, 2017
(as of board presentation)
July 1, 2019
October 15, 2019
US$ 15.00 million
Ministry of Public Works, Construction and Urbanism
2020
US$ 15.00 million
B
January 22, 2024
May 15, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 15.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.00 |
IBRD + IDA Commitment | 15.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2024 | IDA-64440 | Int Charges | 148.88 |
Jun 22, 2022 | IDA-64440 | Loan Disb | 261,913.84 |
Jun 22, 2022 | IDA-64440 | Loan Disb | 44,297.83 |
Jun 22, 2022 | IDA-64440 | Loan Disb | 97,687.16 |
Feb 15, 2022 | IDA-64440 | Int Charges | 1,324.60 |
Feb 15, 2022 | IDA-64440 | Int Charges | 1,324.60 |
Feb 15, 2022 | IDA-64440 | Int Charges | 18,000.60 |
Feb 15, 2022 | IDA-64440 | Int Charges | 18,000.60 |
May 23, 2022 | IDA-64440 | Loan Disb | 371,737.70 |
Jan 4, 2023 | IDA-64440 | Loan Disb | 235,892.70 |
Jul 1, 2019 | IDA-64440 | Loan Commitment | 15,000,000.00 |
Aug 15, 2023 | IDA-64440 | Int Charges | 430.74 |
Aug 15, 2023 | IDA-64440 | Int Charges | 430.74 |
Mar 19, 2021 | IDA-64440 | Loan Disb | 90,113.36 |
Mar 19, 2021 | IDA-64440 | Loan Disb | 30,216.42 |
Oct 16, 2020 | IDA-64440 | Loan Disb | 824,547.60 |
Feb 15, 2021 | IDA-64440 | Int Charges | 43.65 |
Feb 15, 2021 | IDA-64440 | Int Charges | 43.65 |
Oct 22, 2020 | IDA-64440 | Loan Disb | 84,414.22 |
Oct 22, 2020 | IDA-64440 | Loan Disb | 14,857.37 |
Aug 15, 2020 | IDA-64440 | Int Charges | 1,050.20 |
Aug 15, 2020 | IDA-64440 | Int Charges | 1,050.20 |
Nov 19, 2020 | IDA-64440 | Loan Disb | 47,792.11 |
Jan 19, 2021 | IDA-64440 | Loan Disb | 19,448.22 |
Aug 15, 2023 | IDA-64440 | Int Charges | 33,264.66 |
Aug 15, 2023 | IDA-64440 | Int Charges | 33,264.66 |
Jan 2, 2024 | IDA-64440 | Loan Disb | 110,125.49 |
Dec 14, 2023 | IDA-64440 | Loan Disb | 163,035.88 |
Dec 29, 2023 | IDA-64440 | Loan Disb | 161,590.60 |
Oct 17, 2023 | IDA-64440 | Loan Disb | 42,997.51 |
Apr 9, 2024 | IDA-64440 | Loan Disb | 500,070.34 |
May 23, 2024 | IDA-64440 | Loan Disb | 48,607.19 |
Aug 15, 2024 | IDA-64440 | Int Charges | 93.59 |
Aug 15, 2024 | IDA-64440 | Int Charges | 179.43 |
Aug 15, 2024 | IDA-64440 | Int Charges | 179.43 |
Aug 15, 2024 | IDA-64440 | Int Charges | 41,695.01 |
Aug 15, 2024 | IDA-64440 | Int Charges | 41,695.01 |
Aug 20, 2024 | IDA-64440 | Loan Disb | 163,912.05 |
Oct 17, 2023 | IDA-64440 | Loan Disb | 65.54 |
Aug 15, 2024 | IDA-64440 | Int Charges | 93.59 |
Feb 15, 2024 | IDA-64440 | Int Charges | 34,308.85 |
Feb 15, 2024 | IDA-64440 | Int Charges | 34,308.85 |
Jan 19, 2024 | IDA-64440 | Loan Disb | 36,610.01 |
Mar 26, 2024 | IDA-64440 | Loan Disb | 109,897.00 |
Feb 21, 2024 | IDA-64440 | Loan Disb | 412,442.12 |
Feb 21, 2024 | IDA-64440 | Loan Disb | 90,818.15 |
Jul 9, 2024 | IDA-64440 | Loan Disb | 71,479.00 |
May 24, 2024 | IDA-64440 | Loan Disb | 195,269.90 |
Mar 12, 2024 | IDA-64440 | Loan Disb | 29,003.94 |
Mar 12, 2024 | IDA-64440 | Loan Disb | 28,940.33 |
Jul 11, 2024 | IDA-64440 | Loan Disb | 166,053.89 |
Jun 7, 2024 | IDA-64440 | Loan Disb | 53,491.17 |
Jun 3, 2024 | IDA-64440 | Loan Disb | 300,268.20 |
Jun 24, 2024 | IDA-64440 | Loan Disb | 305,070.80 |
Jun 28, 2024 | IDA-64440 | Loan Disb | 103,619.65 |
Apr 17, 2024 | IDA-64440 | Loan Disb | 78,963.86 |
Feb 15, 2024 | IDA-64440 | Int Charges | 148.88 |
Feb 15, 2021 | IDA-64440 | Int Charges | 44.29 |
Feb 15, 2021 | IDA-64440 | Int Charges | 44.29 |
Feb 15, 2021 | IDA-64440 | Int Charges | 4,526.81 |
Feb 15, 2021 | IDA-64440 | Int Charges | 4,526.81 |
Feb 15, 2021 | IDA-64440 | Int Charges | 604.24 |
Feb 15, 2021 | IDA-64440 | Int Charges | 604.24 |
Mar 26, 2021 | IDA-64440 | Loan Disb | 28,209.48 |
May 27, 2021 | IDA-64440 | Loan Disb | 70,110.27 |
May 26, 2021 | IDA-64440 | Loan Disb | 65,442.85 |
May 26, 2021 | IDA-64440 | Loan Disb | 218,817.40 |
Aug 23, 2021 | IDA-64440 | Loan Disb | 96,967.12 |
Aug 23, 2021 | IDA-64440 | Loan Disb | 28,985.45 |
Oct 6, 2021 | IDA-64440 | Loan Disb | 86,030.56 |
Jul 2, 2021 | IDA-64440 | Loan Disb | 73,074.32 |
Jul 2, 2021 | IDA-64440 | Loan Disb | 1,462,638.10 |
Apr 19, 2022 | IDA-64440 | Loan Disb | 88,582.02 |
Dec 14, 2021 | IDA-64440 | Loan Disb | 86,198.50 |
Dec 14, 2021 | IDA-64440 | Loan Disb | 71,832.22 |
Dec 14, 2021 | IDA-64440 | Loan Disb | 25,583.18 |
Dec 14, 2021 | IDA-64440 | Loan Disb | 383,032.53 |
Dec 14, 2021 | IDA-64440 | Loan Disb | 54,256.85 |
May 23, 2022 | IDA-64440 | Loan Disb | 70,665.01 |
Mar 18, 2022 | IDA-64440 | Loan Disb | 30,956.80 |
Apr 20, 2022 | IDA-64440 | Loan Disb | 156,603.62 |
Apr 26, 2022 | IDA-64440 | Loan Disb | 232,188.84 |
Aug 15, 2021 | IDA-64440 | Int Charges | 9,431.97 |
Aug 15, 2021 | IDA-64440 | Int Charges | 9,431.97 |
Aug 15, 2021 | IDA-64440 | Int Charges | 2,059.79 |
Aug 15, 2021 | IDA-64440 | Int Charges | 2,059.79 |
Oct 15, 2021 | IDA-64440 | Loan Disb | 139,011.19 |
Oct 15, 2021 | IDA-64440 | Loan Disb | 331,415.78 |
Jul 19, 2022 | IDA-64440 | Loan Disb | 43,282.41 |
Dec 19, 2019 | IDA-64440 | Loan Disb | 848,188.25 |
Aug 15, 2020 | IDA-64440 | Int Charges | 3,944.30 |
Aug 15, 2020 | IDA-64440 | Int Charges | 3,944.30 |
May 15, 2020 | IDA-64440 | Loan Disb | 56,878.36 |
Aug 15, 2022 | IDA-64440 | Int Charges | 42.22 |
Aug 15, 2022 | IDA-64440 | Int Charges | 42.22 |
Aug 15, 2022 | IDA-64440 | Int Charges | 21,844.43 |
Aug 15, 2022 | IDA-64440 | Int Charges | 21,844.43 |
Aug 4, 2022 | IDA-64440 | Loan Disb | 34,965.88 |
Feb 14, 2022 | IDA-64440 | Loan Disb | 260,854.95 |
Feb 14, 2022 | IDA-64440 | Loan Disb | 77,350.96 |
Feb 14, 2022 | IDA-64440 | Loan Disb | 55,747.77 |
Aug 18, 2022 | IDA-64440 | Loan Disb | 72,869.10 |
Aug 4, 2022 | IDA-64440 | Loan Disb | 89,080.92 |
Aug 4, 2022 | IDA-64440 | Loan Disb | 86,462.76 |
Jul 26, 2022 | IDA-64440 | Loan Disb | 192,043.55 |
Mar 4, 2022 | IDA-64440 | Loan Disb | 147,596.60 |
Nov 7, 2022 | IDA-64440 | Loan Disb | 20,736.88 |
Oct 14, 2022 | IDA-64440 | Loan Disb | 72,453.83 |
Nov 28, 2022 | IDA-64440 | Loan Disb | 22,048.91 |
Nov 28, 2022 | IDA-64440 | Loan Disb | 28,002.72 |
Dec 23, 2022 | IDA-64440 | Loan Disb | 92,987.74 |
Dec 23, 2022 | IDA-64440 | Loan Disb | 40,967.24 |
Feb 20, 2023 | IDA-64440 | Int Charges | 28,537.85 |
Feb 20, 2023 | IDA-64440 | Int Charges | 28,537.85 |
Jan 30, 2023 | IDA-64440 | Loan Disb | 43,465.01 |
Sep 26, 2022 | IDA-64440 | Loan Disb | 37,475.37 |
Mar 21, 2023 | IDA-64440 | Loan Disb | 59,107.74 |
Feb 24, 2023 | IDA-64440 | Loan Disb | 72,935.77 |
Feb 22, 2023 | IDA-64440 | Loan Disb | 18,652.09 |
Feb 22, 2023 | IDA-64440 | Loan Disb | 252,591.61 |
Apr 18, 2023 | IDA-64440 | Loan Disb | 199,805.81 |
Apr 24, 2023 | IDA-64440 | Loan Disb | 87,220.35 |
Feb 20, 2023 | IDA-64440 | Int Charges | 653.96 |
Feb 20, 2023 | IDA-64440 | Int Charges | 653.96 |
Dec 1, 2023 | IDA-64440 | Loan Disb | 36,831.49 |
May 24, 2023 | IDA-64440 | Loan Disb | 27,668.42 |
Jul 11, 2023 | IDA-64440 | Loan Disb | 83,729.00 |
Jul 11, 2023 | IDA-64440 | Loan Disb | 35,778.88 |
Sep 22, 2023 | IDA-64440 | Loan Disb | 29,885.06 |
Aug 29, 2023 | IDA-64440 | Loan Disb | 44,345.04 |
Apr 20, 2020 | IDA-64440 | Loan Disb | 23,297.07 |
Apr 20, 2020 | IDA-64440 | Loan Disb | 150,310.77 |
Jul 24, 2020 | IDA-64440 | Loan Disb | 15,285.55 |
Jul 24, 2020 | IDA-64440 | Loan Disb | 17,080.56 |
Jul 24, 2020 | IDA-64440 | Loan Disb | 62,912.76 |
Oct 22, 2020 | IDA-64440 | Loan Disb | 16,159.39 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-07-25 |
Financial Management | Satisfactory | 2024-07-25 |
Monitoring and Evaluation | Satisfactory | 2024-07-25 |
Procurement | Moderately Satisfactory | 2024-07-25 |
Project Management | Moderately Satisfactory | 2024-07-25 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-07-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of markets accessible all year by road | Value | 0.00 | 3.00 | 5.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Number of schools and health centers accessible all year by road | Value | 0.00 | 22.00 | 29.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Number of direct beneficiaries | Value | 0.00 | 26161.00 | 30000.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehablitated | Value | 0.00 | 53.00 | 110.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Preparation of a national strategy for road maintenance | Value | No | No | Yes |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Grievances responded and/or resolved within the stipulated service standards for response time | Value | 0.00 | 100.00 | 90.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Preparation of a national plan for transport and logistics | Value | No | No | Yes |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Percentage of workers that have signed the GBV code of conduct | Value | 0.00 | 100.00 | 100.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Travel time on National Road 3 connecting with regional transport corridor | Value | 3.50 | 1.50 | 1.25 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Rural roads benefiting from routine maintenance in the project area | Value | 0.00 | 0.00 | 110.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Percentage of sensitive areas benefiting from physical measures of speed reduction | Value | 0.00 | 100.00 | 100.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |
Share of women employed in rehabilitation and routine maintenance road works | Value | 0.00 | 15.75 | 10.00 |
Date | May 31, 2019 | December 20, 2023 | May 15, 2025 | |
Comment |