Financier | Commitments |
---|---|
IDA Credit | 28.00 |
IDA Credit from CRW | 12.00 |
P161939
Closed
Tojoarofenitra Ramanankirahina , Negede Lewi Teklemariam, Ajara Ceesay
Ministry Of Finance
April 11, 2017
(as of board presentation)
May 8, 2017
N/A
US$ 40.00 million
Infrastructure Implementation Unit
2017
US$ 40.00 million
B
Not Applicable
June 30, 2024
Yes
BANK APPROVED
January 24, 2023
Financier | Commitments |
---|---|
IDA Credit | 28.00 |
IDA Credit from CRW | 12.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transport Cost borne by road users including vehicle operating costs and monetary value of travel time (measured in terms of roughness reduction, IRI rate) | Value | 12 | < 3 | 3 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Share of rural population with access to an all-season road | Value | 0.00 | 11.00 | 11.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Direct project beneficiaries | Value | 288000.00 | 315600.00 | 362905.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2022 | |
Comment |
Roads in good and fair condition as a share of total classified roads | Value | 1.00 | 33.70 | 34.00 |
Date | September 1, 2011 | March 31, 2017 | June 30, 2024 | |
Comment |
Number of rural people with access to an all-season road | Value | 288000.00 | 288000.00 | 362905.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Female beneficiaries | Value | 51.00 | 51.00 | 51.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2022 | |
Comment |
Size of the total classified network | Value | 746.00 | 746.00 | 746.00 |
Date | September 1, 2011 | March 31, 2017 | June 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Rural | Value | 0.00 | 246.00 | 253.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Roads constructed, Rural | Value | 0.00 | 2.00 | 2.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2022 | |
Comment |
Road maintained | Value | 0.00 | 246.00 | 253.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Number of staff training hours by training program (P1-P3, see methodology column) | Value | 0.00 | 700.00 | 1500.00 |
Date | September 1, 2011 | March 31, 2017 | June 30, 2024 | |
Comment | Yearly; not cumulative. |
On-the-job training provided by MC | Value | 0.00 | 500.00 | 500.00 |
Date | September 1, 2011 | March 31, 2017 | June 30, 2024 | |
Comment | Half-yearly; not cumulative. |
Increased share of qualified local staff in key competency areas | Value | 10.00 | 50.00 | 100.00 |
Date | September 1, 2011 | March 13, 2017 | June 30, 2024 | |
Comment |
Multi-modal Transport Plan together with Strategic Investment Plan | Value | No | No | Yes |
Date | August 23, 2012 | March 13, 2017 | September 30, 2017 | |
Comment |
Structures at Elwa Intersection (split level intersection) built | Value | No | No | Yes |
Date | August 23, 2012 | March 13, 2017 | December 31, 2019 | |
Comment |
Increased share of female staff in the IIU measured as yearly percentage of new hires | Value | 0.00 | 0.00 | 50.00 |
Date | March 13, 2017 | March 13, 2017 | June 30, 2024 | |
Comment | No baseline. | 009 |
Percentage of citizen complaints received through Argo platform addressed within seven days | Value | 0.00 | 0.00 | 85.00 |
Date | March 13, 2017 | March 13, 2017 | June 30, 2024 | |
Comment | No baseline; Argo platform not yet operational. |
RoW protection pillars installed along the project corridor | Value | No | No | Yes |
Date | March 13, 2017 | March 13, 2017 | June 30, 2019 | |
Comment |
Number of staff trained in road safety | Value | 0.00 | 0.00 | 50.00 |
Date | March 13, 2017 | March 13, 2017 | June 30, 2024 | |
Comment |
RAP implemented before start of civil works for ELWA Junction to Coca Cola Factory | Value | Yes | ||
Date | March 13, 2017 | March 13, 2017 | June 30, 2018 | |
Comment | RAP is under preparation. |
Number of women who have their livelihood and income restored | Value | 0.00 | 0.00 | 0.00 |
Date | March 13, 2017 | March 13, 2017 | June 30, 2018 | |
Comment | No baseline. | Target to be determined based on RAP. |