Second Additional Financing to Liberia Road Asset Management Project

Development Objective

The objective of the project is to support the Recipient's efforts to reduce transport costs along the road corridor from Monroviato the Guinea border and to maintain the road in good condition over a 10-year period.

Key Details

Project Details

  • P161939

  • Closed

  • Tojoarofenitra Ramanankirahina , Negede Lewi Teklemariam, Ajara Ceesay

  • Ministry Of Finance

  • Liberia

  • April 11, 2017

  • (as of board presentation)

    May 8, 2017

  • N/A

  • US$ 40.00 million

  • Infrastructure Implementation Unit

  • Western and Central Africa

  • 2017

  • US$ 40.00 million

  • B

  • Not Applicable

  • June 30, 2024

  • Yes

  • BANK APPROVED

  • P125574

  • January 24, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 28.00
IDA Credit from CRW 12.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 40.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Transport Cost borne by road users including vehicle operating costs and monetary value of travel time (measured in terms of roughness reduction, IRI rate)Value12< 33
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Share of rural population with access to an all-season roadValue0.0011.0011.00
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Direct project beneficiariesValue288000.00315600.00362905.00
    DateSeptember 1, 2011March 13, 2017June 30, 2022
    Comment
  • Roads in good and fair condition as a share of total classified roadsValue1.0033.7034.00
    DateSeptember 1, 2011March 31, 2017June 30, 2024
    Comment
  • Number of rural people with access to an all-season roadValue288000.00288000.00362905.00
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Female beneficiariesValue51.0051.0051.00
    DateSeptember 1, 2011March 13, 2017June 30, 2022
    Comment
  • Size of the total classified networkValue746.00746.00746.00
    DateSeptember 1, 2011March 31, 2017June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehabilitated, RuralValue0.00246.00253.00
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Roads constructed, RuralValue0.002.002.00
    DateSeptember 1, 2011March 13, 2017June 30, 2022
    Comment
  • Road maintainedValue0.00246.00253.00
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Number of staff training hours by training program (P1-P3, see methodology column)Value0.00700.001500.00
    DateSeptember 1, 2011March 31, 2017June 30, 2024
    CommentYearly; not cumulative.
  • On-the-job training provided by MCValue0.00500.00500.00
    DateSeptember 1, 2011March 31, 2017June 30, 2024
    CommentHalf-yearly; not cumulative.
  • Increased share of qualified local staff in key competency areasValue10.0050.00100.00
    DateSeptember 1, 2011March 13, 2017June 30, 2024
    Comment
  • Multi-modal Transport Plan together with Strategic Investment PlanValueNoNoYes
    DateAugust 23, 2012March 13, 2017September 30, 2017
    Comment
  • Structures at Elwa Intersection (split level intersection) builtValueNoNoYes
    DateAugust 23, 2012March 13, 2017December 31, 2019
    Comment
  • Increased share of female staff in the IIU measured as yearly percentage of new hiresValue0.000.0050.00
    DateMarch 13, 2017March 13, 2017June 30, 2024
    CommentNo baseline.009
  • Percentage of citizen complaints received through Argo platform addressed within seven daysValue0.000.0085.00
    DateMarch 13, 2017March 13, 2017June 30, 2024
    CommentNo baseline; Argo platform not yet operational.
  • RoW protection pillars installed along the project corridorValueNoNoYes
    DateMarch 13, 2017March 13, 2017June 30, 2019
    Comment
  • Number of staff trained in road safetyValue0.000.0050.00
    DateMarch 13, 2017March 13, 2017June 30, 2024
    Comment
  • RAP implemented before start of civil works for ELWA Junction to Coca Cola FactoryValueYes
    DateMarch 13, 2017March 13, 2017June 30, 2018
    CommentRAP is under preparation.
  • Number of women who have their livelihood and income restoredValue0.000.000.00
    DateMarch 13, 2017March 13, 2017June 30, 2018
    CommentNo baseline.Target to be determined based on RAP.