Municipal Services and Social Resilience Project

Development Objective

The objective of the MSSRP is to support Jordanian municipalities affected by the influx of Syrian refugees in delivering services and employment opportunities for Jordanians and Syrians.

Key Details

Project Details

  • P161982

  • Closed

  • Lina Abdallah , Phoram Shah

  • N/A

  • Jordan

  • November 30, 2017

  • (as of board presentation)

    December 28, 2017

  • N/A

  • US$ 21.12 million

  • B

  • October 31, 2022

  • June 30, 2024

  • Yes

  • BANK APPROVED

  • P147689

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
MNA VPU Free-standing Trust Funds 21.12

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 21.12
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.002000000.003000000.00
    DateJanuary 1, 2014December 31, 2016December 31, 2020
    Comment
  • Conflict affected people receiving benefits in 1st year of project effectivenessValue0.001144083.00215215.00
    DateJanuary 1, 2014December 31, 2015December 30, 2016
    Comment
  • Participating municipalities ensuring pre-crisis levels of per capita investments in at least 2 of the following: (i) solid waste; (ii) local roads; (iii) street cleaning; (iv) parks (v) community serValue0.00100.00100.00
    DateJanuary 1, 2014December 31, 2015December 31, 2017
    Comment
  • Participating municipalities implement/facilitate at least two priority local economic development subprojects identified in local economic development plansValue0.0050.0075.00
    DateOctober 16, 2013December 31, 2015December 31, 2017
    Comment
  • Participating municipalities clearing annual financial and technical audits without adverse opinionValue0.00100.00100.00
    DateOctober 16, 2013December 31, 2015December 31, 2017
    Comment
  • Beneficiaries provided with access to basic services of which are womenValue0.00916291.801800000.00
    DateJanuary 1, 2014October 15, 2014December 31, 2020
    Comment
  • Female beneficiariesValue0.0045.0047.00
    DateJanuary 1, 2014December 31, 2016December 31, 2020
    Comment
  • Conflict affected ppl receiving benefits in 1st yr of proj. effectiveness?femaleValue0.00852296.00245250.00
    DateJanuary 1, 2014December 31, 2015December 30, 2016
    Comment
  • Percent of Syrian beneficiaries satisfied with the Projectâ??s investments in service delivery, based on independent monitoringValue0.000.0060.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment
  • Percentage of beneficiaries satisfied with the projectâ??s investments in service delivery, based on independent monitoring.Value0.000.0060.00
    DateNovember 21, 2016November 21, 2017December 31, 2020
    Comment
  • Number of working days created under MSSRPValue0.000.00110000.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment
  • of which SyriansValue0.0012.4020.00
    DateJanuary 1, 2014December 31, 2016December 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Participating municipalities spending at least 75 percent of their Municipal Grant each yearValue0.00100.00100.00
    DateJanuary 1, 2014December 30, 2016December 30, 2016
    Comment
  • Participating municipalities with service delivery needs assessments completed in participatory manner.Value0.00100.00100.00
    DateJanuary 1, 2014December 30, 2016December 31, 2017
    Comment
  • Priority service delivery/ community infrastructure projects implemented by participating municipalitiesValue0.00315.00120.00
    DateJanuary 1, 2014March 1, 2017December 31, 2017
    Comment
  • Share of innovation fund grants to sub-projects targeting females and youth as direct beneficiaries.Value0.000.0060.00
    DateNovember 20, 2017November 20, 2017December 31, 2020
    Comment
  • Participating municipalities clearing annual financial and technical audits without adverse opinionValue0.00100.00100.00
    DateNovember 17, 2014November 21, 2017December 31, 2020
    CommentAccording to the ESSRP Annual Progress Report for 2016, all participating municipalities cleared annual financial and technicalaudits without adverse opinion.
  • Share of Municipal Grants and Innovation Fund grants allocations to projects targeting females and youth as direct beneficiaries.Value0.000.0030.00
    DateNovember 20, 2017December 31, 2020
    CommentData has not been collected. This is a new indicator to be tracked following effectiveness.
  • Participating municipalities with local development plans updated/completed in participatory manner.Value0.00100.00100.00
    DateJanuary 1, 2014December 30, 2016December 31, 2017
    Comment
  • Participating municipalities that publicly disclose project budgets and audit resultsValue0.00100.0075.00
    DateJanuary 1, 2014December 31, 2016December 31, 2017
    Comment
  • Participating municipalities and governorates having emergency management plansValue0.0010.0075.00
    DateJanuary 1, 2014December 30, 2016December 31, 2017
    Comment
  • Key staff in participating municipalities and governorates trained on emergency preparedness proceduresValue0.000.0040.00
    DateJanuary 1, 2014December 31, 2015December 31, 2017
    Comment
  • Beneficiaries that feel project investments reflected their needs, of which womenValue0.0048.0050.00
    DateJanuary 1, 2014December 31, 2015December 31, 2017
    Comment
  • Beneficiaries that feel investments under MSSRP reflected their needsValue36.0034.0050.00
    DateDecember 30, 2016November 21, 2017December 31, 2020
    CommentThis is based on findings of independent monitoring report.Average extrapolated from the initial results of the ESSRP End Line Survey.
  • Percentage of beneficiaries who are satisfied with the performance of their respective participating municipalities in addressing their needs through MSSRPValue30.000.0060.00
    DateNovember 30, 2016November 21, 2017December 31, 2020
    Comment
  • Perception on MSSRP contributions to social cohesion improve.ValueNoNoYes
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment
  • Improved access to service delivery in host communities in the project areaValue00Text
    DateNovember 21, 2017November 21, 2017November 30, 2020
    Comment
  • Participating Municipalities with Action Plans for gender mainstreaming linked to sub-projects in service delivery.Value0.000.0020.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment
  • Participating Municipalities utilizing citizen feedback toolsValue0.000.0021.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment
  • Participating municipalities that publicly disclose sub-project budgets and audit resultsValue0.0016.0026.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    CommentAccording to the PMU reporting, 100% of participating municipalities met this target.The end target is revised from 75% to 100%
  • Participating municipalities that are able to link their strategic plans to service delivery sub-projects by year 2 of project implementationValue0.000.0010.00
    DateNovember 21, 2017November 21, 2017December 31, 2020
    Comment