Financier | Commitments |
---|---|
IDA Credit | 175.00 |
Borrower/Recipient | 3.90 |
P161996
Active
Md Sobhan , Md Sobhan
Government of Bangladesh
August 3, 2017
(as of board presentation)
October 5, 2018
November 21, 2018
US$ 178.90 million
Bangladesh Forest Research Institute,Public Works Department, Ministry of Housing and Public Works,Bangladesh Forest Department (BFD),Bangladesh National Herbarium
2019
US$ 175.00 million
B
October 9, 2024
June 30, 2025
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 175.00 |
Borrower/Recipient | 3.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 175.00 |
IBRD + IDA Commitment | 175.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 178.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2021 | IDA-63250 | Int Charges | 198,567.78 |
Nov 15, 2021 | IDA-63250 | Int Charges | 330,946.28 |
Aug 16, 2021 | IDA-63250 | Loan Disb | 3,627,487.50 |
Nov 1, 2021 | IDA-63250 | Loan Disb | 1,982,220.80 |
Jun 1, 2022 | IDA-63250 | Loan Disb | 147,895.34 |
Jun 1, 2022 | IDA-63250 | Loan Disb | 1,947,058.00 |
Jun 15, 2022 | IDA-63250 | Loan Disb | 707,047.56 |
Jun 27, 2022 | IDA-63250 | Loan Disb | 3,373,324.80 |
Apr 21, 2022 | IDA-63250 | Loan Disb | 1,218,341.80 |
Jun 27, 2022 | IDA-63250 | Loan Disb | 112,750.54 |
May 31, 2022 | IDA-63250 | Loan Disb | 85,324.24 |
May 15, 2022 | IDA-63250 | Int Charges | 214,309.58 |
May 15, 2022 | IDA-63250 | Int Charges | 214,309.58 |
Jun 22, 2022 | IDA-63250 | Loan Disb | 80,818.98 |
Mar 24, 2022 | IDA-63250 | Loan Disb | 1,598,590.00 |
Jun 29, 2022 | IDA-63250 | Loan Disb | 194,682.31 |
May 15, 2022 | IDA-63250 | Int Charges | 365,380.25 |
May 15, 2022 | IDA-63250 | Int Charges | 4,918.57 |
May 15, 2022 | IDA-63250 | Int Charges | 4,918.57 |
Jun 9, 2022 | IDA-63250 | Loan Disb | 2,136,396.00 |
Dec 9, 2021 | IDA-63250 | Loan Disb | 874,357.25 |
Aug 22, 2022 | IDA-63250 | Loan Disb | 132,206.80 |
Aug 8, 2022 | IDA-63250 | Loan Disb | 79,176.56 |
Feb 8, 2022 | IDA-63250 | Loan Disb | 2,202,783.20 |
Mar 7, 2024 | IDA-63250 | Loan Disb | 2,289,425.00 |
Jun 20, 2024 | IDA-63250 | Loan Disb | 35,044.44 |
May 15, 2024 | IDA-63250 | Loan Repay | 1,596,739.00 |
May 15, 2024 | IDA-63250 | Int Charges | 25,723.86 |
Mar 7, 2024 | IDA-63250 | Loan Disb | 410,394.16 |
Jun 24, 2024 | IDA-63250 | Loan Disb | 2,504,538.00 |
Jun 24, 2024 | IDA-63250 | Loan Disb | 105,272.35 |
Jun 24, 2024 | IDA-63250 | Loan Disb | 348,773.25 |
Jun 24, 2024 | IDA-63250 | Loan Disb | 3,127,288.80 |
Jun 27, 2024 | IDA-63250 | Loan Disb | 363,634.00 |
May 15, 2024 | IDA-63250 | Loan Repay | 1,130,425.00 |
May 15, 2024 | IDA-63250 | Int Charges | 423,569.70 |
May 15, 2024 | IDA-63250 | Int Charges | 423,569.70 |
May 15, 2024 | IDA-63250 | Int Charges | 705,949.50 |
Feb 8, 2024 | IDA-63250 | Loan Disb | 474,805.88 |
Feb 8, 2024 | IDA-63250 | Loan Disb | 2,044,199.10 |
May 11, 2023 | IDA-63250 | Loan Disb | 2,552,465.00 |
Apr 24, 2023 | IDA-63250 | Loan Disb | 217,853.77 |
Mar 9, 2023 | IDA-63250 | Loan Disb | 2,117,965.00 |
Sep 11, 2023 | IDA-63250 | Loan Disb | 699,632.44 |
Aug 22, 2023 | IDA-63250 | Loan Disb | 7,243,925.50 |
Jul 26, 2023 | IDA-63250 | Loan Disb | 19,568.62 |
Jun 20, 2023 | IDA-63250 | Loan Disb | 57,727.55 |
Jun 20, 2023 | IDA-63250 | Loan Disb | 872,954.94 |
Jun 20, 2023 | IDA-63250 | Loan Disb | 4,530.45 |
Oct 5, 2018 | IDA-63250 | Loan Commitment | 175,000,000.00 |
Oct 26, 2023 | IDA-63250 | Loan Disb | 5,720.98 |
Oct 3, 2023 | IDA-63250 | Loan Disb | 49,080.53 |
Oct 3, 2023 | IDA-63250 | Loan Disb | 990,652.60 |
Dec 27, 2023 | IDA-63250 | Loan Disb | 2,357,022.20 |
Jan 5, 2024 | IDA-63250 | Loan Disb | 1,360,676.00 |
Apr 15, 2024 | IDA-63250 | Loan Disb | 2,914,749.50 |
May 23, 2024 | IDA-63250 | Loan Disb | 267,726.84 |
Apr 1, 2024 | IDA-63250 | Loan Disb | 498,981.20 |
Apr 15, 2024 | IDA-63250 | Loan Disb | 13,743.61 |
Jan 23, 2024 | IDA-63250 | Loan Disb | 22,605.43 |
Sep 21, 2021 | IDA-63250 | Loan Disb | 523,374.20 |
Nov 15, 2021 | IDA-63250 | Int Charges | 7,520.06 |
Nov 15, 2021 | IDA-63250 | Int Charges | 198,567.78 |
Aug 3, 2020 | IDA-63250 | Loan Disb | 4,347,612.00 |
Dec 17, 2020 | IDA-63250 | Loan Disb | 1,465,914.60 |
Dec 17, 2020 | IDA-63250 | Loan Disb | 850,021.80 |
Nov 15, 2020 | IDA-63250 | Int Charges | 2,189.05 |
Nov 15, 2020 | IDA-63250 | Int Charges | 117,004.78 |
Mar 11, 2021 | IDA-63250 | Loan Disb | 1,522,835.80 |
Feb 23, 2021 | IDA-63250 | Loan Disb | 1,161,556.20 |
Nov 15, 2020 | IDA-63250 | Int Charges | 117,004.78 |
Nov 15, 2020 | IDA-63250 | Int Charges | 194,304.28 |
Nov 19, 2020 | IDA-63250 | Loan Disb | 1,040,939.56 |
Nov 19, 2020 | IDA-63250 | Loan Disb | 132,142.88 |
May 15, 2021 | IDA-63250 | Int Charges | 241,492.38 |
May 15, 2021 | IDA-63250 | Int Charges | 713.08 |
Mar 24, 2021 | IDA-63250 | Loan Disb | 1,407,838.80 |
May 27, 2021 | IDA-63250 | Loan Disb | 3,138,374.00 |
Jun 21, 2021 | IDA-63250 | Loan Disb | 3,596,993.20 |
Aug 1, 2019 | IDA-63250 | Loan Disb | 3,017,631.80 |
Nov 15, 2019 | IDA-63250 | Int Charges | 1,393.23 |
Nov 15, 2019 | IDA-63250 | Int Charges | 64,060.21 |
Nov 15, 2019 | IDA-63250 | Int Charges | 64,060.21 |
Nov 15, 2019 | IDA-63250 | Int Charges | 105,355.50 |
Jun 20, 2019 | IDA-63250 | Loan Disb | 432,801.28 |
Mar 11, 2019 | IDA-63250 | Loan Disb | 14,260,250.00 |
Apr 2, 2019 | IDA-63250 | Loan Disb | 671,161.50 |
May 15, 2019 | IDA-63250 | Int Charges | 19,606.53 |
May 15, 2019 | IDA-63250 | Int Charges | 19,606.53 |
Jun 15, 2023 | IDA-63250 | Loan Disb | 6,100,344.00 |
May 23, 2023 | IDA-63250 | Loan Disb | 2,931,886.80 |
May 15, 2023 | IDA-63250 | Int Charges | 12,789.95 |
May 15, 2023 | IDA-63250 | Int Charges | 313,803.80 |
May 15, 2023 | IDA-63250 | Int Charges | 313,803.80 |
May 15, 2023 | IDA-63250 | Int Charges | 513,025.50 |
Nov 15, 2023 | IDA-63250 | Int Charges | 9,859.67 |
Nov 15, 2023 | IDA-63250 | Loan Repay | 2,733,408.50 |
Nov 15, 2023 | IDA-63250 | Int Charges | 382,850.66 |
Nov 15, 2023 | IDA-63250 | Int Charges | 382,850.66 |
Nov 15, 2023 | IDA-63250 | Int Charges | 612,301.60 |
Nov 13, 2023 | IDA-63250 | Loan Disb | 175,095.72 |
May 23, 2024 | IDA-63250 | Loan Disb | 2,770,800.50 |
May 23, 2024 | IDA-63250 | Loan Disb | 4,652.30 |
May 6, 2024 | IDA-63250 | Loan Disb | 286,511.00 |
May 6, 2024 | IDA-63250 | Loan Disb | 28,380.70 |
Jun 6, 2024 | IDA-63250 | Loan Disb | 436,916.62 |
Jun 6, 2024 | IDA-63250 | Loan Disb | 2,273,243.00 |
Sep 29, 2022 | IDA-63250 | Loan Disb | 427,682.06 |
Nov 15, 2022 | IDA-63250 | Int Charges | 429,153.90 |
Nov 15, 2022 | IDA-63250 | Int Charges | 15,159.53 |
Nov 15, 2022 | IDA-63250 | Int Charges | 15,159.53 |
Nov 14, 2022 | IDA-63250 | Loan Disb | 2,124,539.00 |
Nov 15, 2022 | IDA-63250 | Int Charges | 249,854.27 |
Nov 15, 2022 | IDA-63250 | Int Charges | 249,854.27 |
Feb 6, 2023 | IDA-63250 | Loan Disb | 2,337,790.00 |
Feb 6, 2023 | IDA-63250 | Loan Disb | 133,086.60 |
Dec 7, 2022 | IDA-63250 | Loan Disb | 680,096.94 |
Dec 15, 2022 | IDA-63250 | Loan Disb | 891,385.20 |
Dec 8, 2022 | IDA-63250 | Loan Disb | 11,414.14 |
Feb 27, 2023 | IDA-63250 | Loan Disb | 41,800.54 |
Mar 7, 2023 | IDA-63250 | Loan Disb | 59,047.79 |
Mar 7, 2023 | IDA-63250 | Loan Disb | 1,344.40 |
Apr 17, 2023 | IDA-63250 | Loan Disb | 1,266,194.80 |
Jan 24, 2023 | IDA-63250 | Loan Disb | 1,077,357.90 |
Sep 1, 2022 | IDA-63250 | Loan Disb | 4,933,557.00 |
Dec 27, 2021 | IDA-63250 | Loan Disb | 1,095,327.20 |
May 15, 2019 | IDA-63250 | Int Charges | 31,276.39 |
Apr 2, 2019 | IDA-63250 | Loan Disb | 70,753.57 |
Mar 2, 2020 | IDA-63250 | Loan Disb | 901,747.40 |
Oct 21, 2019 | IDA-63250 | Loan Disb | 527,600.75 |
Sep 19, 2019 | IDA-63250 | Loan Disb | 174,382.81 |
Jan 30, 2020 | IDA-63250 | Loan Disb | 325,515.47 |
Mar 25, 2020 | IDA-63250 | Loan Disb | 1,235,552.00 |
Feb 12, 2020 | IDA-63250 | Loan Disb | 441,153.60 |
Aug 3, 2020 | IDA-63250 | Loan Disb | 3,823,862.20 |
May 19, 2020 | IDA-63250 | Loan Disb | 1,083,785.40 |
May 15, 2020 | IDA-63250 | Int Charges | 76,142.97 |
May 15, 2020 | IDA-63250 | Int Charges | 76,142.97 |
May 15, 2020 | IDA-63250 | Int Charges | 124,809.04 |
May 15, 2020 | IDA-63250 | Int Charges | 1,396.03 |
Feb 6, 2020 | IDA-63250 | Loan Disb | 429,437.75 |
May 4, 2020 | IDA-63250 | Loan Disb | 2,306,559.80 |
Jun 7, 2020 | IDA-63250 | Loan Disb | -94,285.59 |
Oct 26, 2023 | IDA-63250 | Loan Disb | 1,557,001.50 |
Jun 23, 2021 | IDA-63250 | Loan Disb | 2,122,641.50 |
May 15, 2021 | IDA-63250 | Int Charges | 149,515.92 |
May 15, 2021 | IDA-63250 | Int Charges | 149,515.92 |
May 6, 2021 | IDA-63250 | Loan Disb | 1,727,427.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-12-24 |
Financial Management | Satisfactory | 2024-12-24 |
Monitoring and Evaluation | Satisfactory | 2024-12-24 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-24 |
Progress towards achievement of PDO | Satisfactory | 2024-12-24 |
Procurement | Satisfactory | 2024-12-24 |
Progress towards achievement of PDO | Satisfactory | 2024-12-24 |
Procurement | Satisfactory | 2024-12-24 |
Project Management | Satisfactory | 2024-12-24 |
Financial Management | Satisfactory | 2024-12-24 |
Monitoring and Evaluation | Satisfactory | 2024-12-24 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of targeted forest-dependent people with access to alternative income generating activities | Value | 0.00 | 79.50 | 70.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Forest areas at targeted sites managed according to site specific collaborative management plans | Value | 0.00 | 80588.00 | 78930.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
disaggregated by ethnic group | Value | 0.00 | 71.00 | 70.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
disaggregated by gender | Value | 0.00 | 75.44 | 70.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Collaborative Forest Management Committees with increased monetary or non-monetary benefits from forests | Value | 0.00 | 100.00 | 90.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Share of targeted forest-dependent people with rating ‘Satisfied’ or above on project interventions (livelihoods, forest management, other) | Value | 0.00 | 58.00 | 75.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
disaggregated by ethnic group | Value | 0.00 | 59.00 | 75.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
disaggregted by gender | Value | 0.00 | 56.00 | 75.00 |
Date | September 28, 2018 | September 30, 2023 | December 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Organizational, functional and gender review of BFD undertaken | Value | 0.00 | 0.00 | 1.00 |
Date | September 28, 2018 | October 30, 2023 | September 29, 2023 | |
Comment |
Area restored or re/afforested in accordance with site-specific collaborative management plans | Value | 0.00 | 80588.00 | 78930.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Collaborative Forest Management Committees operational with own bank account and operating fund | Value | 0.00 | 600.00 | 600.00 |
Date | September 28, 2018 | October 30, 2023 | December 31, 2024 | |
Comment |
Digital site-specific management planning system established and operational | Value | No | Yes | Yes |
Date | September 28, 2018 | October 30, 2023 | September 30, 2024 | |
Comment |
Households in targeted communities with programs for alternative income generating activities supported by the project | Value | 0.00 | 31801.00 | 40000.00 |
Date | September 28, 2018 | October 30, 2023 | December 31, 2024 | |
Comment |
Assisted Natural Regeneration | Value | 0.00 | 2890.00 | 2890.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Collaborative Forest Management Committees with at least 33 % female office bearers | Value | 0.00 | 183.00 | 150.00 |
Date | September 28, 2018 | October 30, 2023 | December 31, 2024 | |
Comment |
Enrichment planting | Value | 0.00 | 11038.00 | 11870.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Number of staff trained | Value | 0.00 | 2687.00 | 2000.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Share of households with improved cookstoves | Value | 10.00 | 10.00 | 30.00 |
Date | September 28, 2018 | October 30, 2023 | December 31, 2024 | |
Comment |
Mixed plantation with indigenous fast-growing species | Value | 0.00 | 19632.00 | 14650.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
A market information system for Trees Outside Forest established and operational | Value | 0.00 | 0.00 | 1.00 |
Date | July 5, 2018 | October 30, 2023 | December 31, 2024 | |
Comment |
Mixed plantation with indigenous slow growing species | Value | 0.00 | 6160.00 | 6160.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Mangrove Afforestation (Plantation raising on new land formations) and in coastal districts | Value | 0.00 | 25855.00 | 21080.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Other types of plantations (habitat and mangrove improvement, Sal coppice, etc.) | Value | 0.00 | 15013.00 | 22208.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Protected areas brought under enhanced management | Value | 0.00 | 20.00 | 20.00 |
Date | September 28, 2018 | October 30, 2023 | December 30, 2024 | |
Comment |
Forest area brought under management plans | Value | 0.00 | 0.00 | 811000.00 |
Date | September 28, 2018 | October 23, 2023 | December 30, 2024 | |
Comment |