Skip to Main Navigation

Sustainable Forests & Livelihoods (SUFAL) Project

Development Objective

To improve collaborative forest management and increase benefits for forest dependent communities in targeted sites.

Key Details

Project Details

  • P161996

  • Active

  • Md Sobhan , Md Sobhan

  • Government of Bangladesh

  • Bangladesh

  • August 3, 2017

  • (as of board presentation)

    October 5, 2018

  • November 21, 2018

  • US$ 178.90 million

  • Bangladesh Forest Research Institute,Public Works Department, Ministry of Housing and Public Works,Bangladesh Forest Department (BFD),Bangladesh National Herbarium

  • South Asia

  • 2019

  • US$ 175.00 million

  • B

  • October 9, 2024

  • June 30, 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 175.00
Borrower/Recipient 3.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 175.00
IBRD + IDA Commitment 175.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 178.90

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2021 IDA-63250 Int Charges 198,567.78
Nov 15, 2021 IDA-63250 Int Charges 330,946.28
Aug 16, 2021 IDA-63250 Loan Disb 3,627,487.50
Nov 1, 2021 IDA-63250 Loan Disb 1,982,220.80
Jun 1, 2022 IDA-63250 Loan Disb 147,895.34
Jun 1, 2022 IDA-63250 Loan Disb 1,947,058.00
Jun 15, 2022 IDA-63250 Loan Disb 707,047.56
Jun 27, 2022 IDA-63250 Loan Disb 3,373,324.80
Apr 21, 2022 IDA-63250 Loan Disb 1,218,341.80
Jun 27, 2022 IDA-63250 Loan Disb 112,750.54
May 31, 2022 IDA-63250 Loan Disb 85,324.24
May 15, 2022 IDA-63250 Int Charges 214,309.58
May 15, 2022 IDA-63250 Int Charges 214,309.58
Jun 22, 2022 IDA-63250 Loan Disb 80,818.98
Mar 24, 2022 IDA-63250 Loan Disb 1,598,590.00
Jun 29, 2022 IDA-63250 Loan Disb 194,682.31
May 15, 2022 IDA-63250 Int Charges 365,380.25
May 15, 2022 IDA-63250 Int Charges 4,918.57
May 15, 2022 IDA-63250 Int Charges 4,918.57
Jun 9, 2022 IDA-63250 Loan Disb 2,136,396.00
Dec 9, 2021 IDA-63250 Loan Disb 874,357.25
Aug 22, 2022 IDA-63250 Loan Disb 132,206.80
Aug 8, 2022 IDA-63250 Loan Disb 79,176.56
Feb 8, 2022 IDA-63250 Loan Disb 2,202,783.20
Mar 7, 2024 IDA-63250 Loan Disb 2,289,425.00
Jun 20, 2024 IDA-63250 Loan Disb 35,044.44
May 15, 2024 IDA-63250 Loan Repay 1,596,739.00
May 15, 2024 IDA-63250 Int Charges 25,723.86
Mar 7, 2024 IDA-63250 Loan Disb 410,394.16
Jun 24, 2024 IDA-63250 Loan Disb 2,504,538.00
Jun 24, 2024 IDA-63250 Loan Disb 105,272.35
Jun 24, 2024 IDA-63250 Loan Disb 348,773.25
Jun 24, 2024 IDA-63250 Loan Disb 3,127,288.80
Jun 27, 2024 IDA-63250 Loan Disb 363,634.00
May 15, 2024 IDA-63250 Loan Repay 1,130,425.00
May 15, 2024 IDA-63250 Int Charges 423,569.70
May 15, 2024 IDA-63250 Int Charges 423,569.70
May 15, 2024 IDA-63250 Int Charges 705,949.50
Feb 8, 2024 IDA-63250 Loan Disb 474,805.88
Feb 8, 2024 IDA-63250 Loan Disb 2,044,199.10
May 11, 2023 IDA-63250 Loan Disb 2,552,465.00
Apr 24, 2023 IDA-63250 Loan Disb 217,853.77
Mar 9, 2023 IDA-63250 Loan Disb 2,117,965.00
Sep 11, 2023 IDA-63250 Loan Disb 699,632.44
Aug 22, 2023 IDA-63250 Loan Disb 7,243,925.50
Jul 26, 2023 IDA-63250 Loan Disb 19,568.62
Jun 20, 2023 IDA-63250 Loan Disb 57,727.55
Jun 20, 2023 IDA-63250 Loan Disb 872,954.94
Jun 20, 2023 IDA-63250 Loan Disb 4,530.45
Oct 5, 2018 IDA-63250 Loan Commitment 175,000,000.00
Oct 26, 2023 IDA-63250 Loan Disb 5,720.98
Oct 3, 2023 IDA-63250 Loan Disb 49,080.53
Oct 3, 2023 IDA-63250 Loan Disb 990,652.60
Dec 27, 2023 IDA-63250 Loan Disb 2,357,022.20
Jan 5, 2024 IDA-63250 Loan Disb 1,360,676.00
Apr 15, 2024 IDA-63250 Loan Disb 2,914,749.50
May 23, 2024 IDA-63250 Loan Disb 267,726.84
Apr 1, 2024 IDA-63250 Loan Disb 498,981.20
Apr 15, 2024 IDA-63250 Loan Disb 13,743.61
Jan 23, 2024 IDA-63250 Loan Disb 22,605.43
Sep 21, 2021 IDA-63250 Loan Disb 523,374.20
Nov 15, 2021 IDA-63250 Int Charges 7,520.06
Nov 15, 2021 IDA-63250 Int Charges 198,567.78
Aug 3, 2020 IDA-63250 Loan Disb 4,347,612.00
Dec 17, 2020 IDA-63250 Loan Disb 1,465,914.60
Dec 17, 2020 IDA-63250 Loan Disb 850,021.80
Nov 15, 2020 IDA-63250 Int Charges 2,189.05
Nov 15, 2020 IDA-63250 Int Charges 117,004.78
Mar 11, 2021 IDA-63250 Loan Disb 1,522,835.80
Feb 23, 2021 IDA-63250 Loan Disb 1,161,556.20
Nov 15, 2020 IDA-63250 Int Charges 117,004.78
Nov 15, 2020 IDA-63250 Int Charges 194,304.28
Nov 19, 2020 IDA-63250 Loan Disb 1,040,939.56
Nov 19, 2020 IDA-63250 Loan Disb 132,142.88
May 15, 2021 IDA-63250 Int Charges 241,492.38
May 15, 2021 IDA-63250 Int Charges 713.08
Mar 24, 2021 IDA-63250 Loan Disb 1,407,838.80
May 27, 2021 IDA-63250 Loan Disb 3,138,374.00
Jun 21, 2021 IDA-63250 Loan Disb 3,596,993.20
Aug 1, 2019 IDA-63250 Loan Disb 3,017,631.80
Nov 15, 2019 IDA-63250 Int Charges 1,393.23
Nov 15, 2019 IDA-63250 Int Charges 64,060.21
Nov 15, 2019 IDA-63250 Int Charges 64,060.21
Nov 15, 2019 IDA-63250 Int Charges 105,355.50
Jun 20, 2019 IDA-63250 Loan Disb 432,801.28
Mar 11, 2019 IDA-63250 Loan Disb 14,260,250.00
Apr 2, 2019 IDA-63250 Loan Disb 671,161.50
May 15, 2019 IDA-63250 Int Charges 19,606.53
May 15, 2019 IDA-63250 Int Charges 19,606.53
Jun 15, 2023 IDA-63250 Loan Disb 6,100,344.00
May 23, 2023 IDA-63250 Loan Disb 2,931,886.80
May 15, 2023 IDA-63250 Int Charges 12,789.95
May 15, 2023 IDA-63250 Int Charges 313,803.80
May 15, 2023 IDA-63250 Int Charges 313,803.80
May 15, 2023 IDA-63250 Int Charges 513,025.50
Nov 15, 2023 IDA-63250 Int Charges 9,859.67
Nov 15, 2023 IDA-63250 Loan Repay 2,733,408.50
Nov 15, 2023 IDA-63250 Int Charges 382,850.66
Nov 15, 2023 IDA-63250 Int Charges 382,850.66
Nov 15, 2023 IDA-63250 Int Charges 612,301.60
Nov 13, 2023 IDA-63250 Loan Disb 175,095.72
May 23, 2024 IDA-63250 Loan Disb 2,770,800.50
May 23, 2024 IDA-63250 Loan Disb 4,652.30
May 6, 2024 IDA-63250 Loan Disb 286,511.00
May 6, 2024 IDA-63250 Loan Disb 28,380.70
Jun 6, 2024 IDA-63250 Loan Disb 436,916.62
Jun 6, 2024 IDA-63250 Loan Disb 2,273,243.00
Sep 29, 2022 IDA-63250 Loan Disb 427,682.06
Nov 15, 2022 IDA-63250 Int Charges 429,153.90
Nov 15, 2022 IDA-63250 Int Charges 15,159.53
Nov 15, 2022 IDA-63250 Int Charges 15,159.53
Nov 14, 2022 IDA-63250 Loan Disb 2,124,539.00
Nov 15, 2022 IDA-63250 Int Charges 249,854.27
Nov 15, 2022 IDA-63250 Int Charges 249,854.27
Feb 6, 2023 IDA-63250 Loan Disb 2,337,790.00
Feb 6, 2023 IDA-63250 Loan Disb 133,086.60
Dec 7, 2022 IDA-63250 Loan Disb 680,096.94
Dec 15, 2022 IDA-63250 Loan Disb 891,385.20
Dec 8, 2022 IDA-63250 Loan Disb 11,414.14
Feb 27, 2023 IDA-63250 Loan Disb 41,800.54
Mar 7, 2023 IDA-63250 Loan Disb 59,047.79
Mar 7, 2023 IDA-63250 Loan Disb 1,344.40
Apr 17, 2023 IDA-63250 Loan Disb 1,266,194.80
Jan 24, 2023 IDA-63250 Loan Disb 1,077,357.90
Sep 1, 2022 IDA-63250 Loan Disb 4,933,557.00
Dec 27, 2021 IDA-63250 Loan Disb 1,095,327.20
May 15, 2019 IDA-63250 Int Charges 31,276.39
Apr 2, 2019 IDA-63250 Loan Disb 70,753.57
Mar 2, 2020 IDA-63250 Loan Disb 901,747.40
Oct 21, 2019 IDA-63250 Loan Disb 527,600.75
Sep 19, 2019 IDA-63250 Loan Disb 174,382.81
Jan 30, 2020 IDA-63250 Loan Disb 325,515.47
Mar 25, 2020 IDA-63250 Loan Disb 1,235,552.00
Feb 12, 2020 IDA-63250 Loan Disb 441,153.60
Aug 3, 2020 IDA-63250 Loan Disb 3,823,862.20
May 19, 2020 IDA-63250 Loan Disb 1,083,785.40
May 15, 2020 IDA-63250 Int Charges 76,142.97
May 15, 2020 IDA-63250 Int Charges 76,142.97
May 15, 2020 IDA-63250 Int Charges 124,809.04
May 15, 2020 IDA-63250 Int Charges 1,396.03
Feb 6, 2020 IDA-63250 Loan Disb 429,437.75
May 4, 2020 IDA-63250 Loan Disb 2,306,559.80
Jun 7, 2020 IDA-63250 Loan Disb -94,285.59
Oct 26, 2023 IDA-63250 Loan Disb 1,557,001.50
Jun 23, 2021 IDA-63250 Loan Disb 2,122,641.50
May 15, 2021 IDA-63250 Int Charges 149,515.92
May 15, 2021 IDA-63250 Int Charges 149,515.92
May 6, 2021 IDA-63250 Loan Disb 1,727,427.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-12-24
Financial Management Satisfactory 2024-12-24
Monitoring and Evaluation Satisfactory 2024-12-24
Overall Implementation Progress (IP) Satisfactory 2024-12-24
Progress towards achievement of PDO Satisfactory 2024-12-24
Procurement Satisfactory 2024-12-24
Progress towards achievement of PDO Satisfactory 2024-12-24
Procurement Satisfactory 2024-12-24
Project Management Satisfactory 2024-12-24
Financial Management Satisfactory 2024-12-24
Monitoring and Evaluation Satisfactory 2024-12-24
Overall Implementation Progress (IP) Satisfactory 2024-12-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of targeted forest-dependent people with access to alternative income generating activitiesValue0.0079.5070.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Forest areas at targeted sites managed according to site specific collaborative management plansValue0.0080588.0078930.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • disaggregated by ethnic groupValue0.0071.0070.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • disaggregated by genderValue0.0075.4470.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Collaborative Forest Management Committees with increased monetary or non-monetary benefits from forestsValue0.00100.0090.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Share of targeted forest-dependent people with rating ‘Satisfied’ or above on project interventions (livelihoods, forest management, other)Value0.0058.0075.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • disaggregated by ethnic groupValue0.0059.0075.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • disaggregted by genderValue0.0056.0075.00
    DateSeptember 28, 2018September 30, 2023December 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Organizational, functional and gender review of BFD undertakenValue0.000.001.00
    DateSeptember 28, 2018October 30, 2023September 29, 2023
    Comment
  • Area restored or re/afforested in accordance with site-specific collaborative management plansValue0.0080588.0078930.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Collaborative Forest Management Committees operational with own bank account and operating fundValue0.00600.00600.00
    DateSeptember 28, 2018October 30, 2023December 31, 2024
    Comment
  • Digital site-specific management planning system established and operationalValueNoYesYes
    DateSeptember 28, 2018October 30, 2023September 30, 2024
    Comment
  • Households in targeted communities with programs for alternative income generating activities supported by the projectValue0.0031801.0040000.00
    DateSeptember 28, 2018October 30, 2023December 31, 2024
    Comment
  • Assisted Natural RegenerationValue0.002890.002890.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Collaborative Forest Management Committees with at least 33 % female office bearersValue0.00183.00150.00
    DateSeptember 28, 2018October 30, 2023December 31, 2024
    Comment
  • Enrichment plantingValue0.0011038.0011870.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Number of staff trainedValue0.002687.002000.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Share of households with improved cookstovesValue10.0010.0030.00
    DateSeptember 28, 2018October 30, 2023December 31, 2024
    Comment
  • Mixed plantation with indigenous fast-growing speciesValue0.0019632.0014650.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • A market information system for Trees Outside Forest established and operationalValue0.000.001.00
    DateJuly 5, 2018October 30, 2023December 31, 2024
    Comment
  • Mixed plantation with indigenous slow growing speciesValue0.006160.006160.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Mangrove Afforestation (Plantation raising on new land formations) and in coastal districtsValue0.0025855.0021080.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Other types of plantations (habitat and mangrove improvement, Sal coppice, etc.)Value0.0015013.0022208.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Protected areas brought under enhanced managementValue0.0020.0020.00
    DateSeptember 28, 2018October 30, 2023December 30, 2024
    Comment
  • Forest area brought under management plansValue0.000.00811000.00
    DateSeptember 28, 2018October 23, 2023December 30, 2024
    Comment