Financier | Commitments |
---|---|
IDA Credit | 90.00 |
P162182
Closed
Mehnaz Safavian
Ministry of Finance
March 22, 2017
(as of board presentation)
July 5, 2017
N/A
US$ 50.00 million
N/A
2018
US$ 90.00 million
A
Not Applicable
September 30, 2024
Yes
BANK APPROVED
July 15, 2022
Financier | Commitments |
---|---|
IDA Credit | 90.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 90.00 |
IBRD + IDA Commitment | 90.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Expression of Interests (EOIs) issued to prospective sponsors for three targeted PPP transactions | Value | 0.00 | 1.00 | 3.00 |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
PPP Regulations associated with the new Law agreed to with MoF | Value | No | Yes | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
PPP Fiscal Commitment and Contingent Liability Framework operationalized as measured by: upstream DMO due diligence on prospective (feasibility stage) transactions completed in line with Law | Value | No | No | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
Regular issuance of Government benchmark bonds in medium and long term maturities up to 7/10 year tenures (Number, custom) | Value | No | Yes | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
Private Capital Mobilized | Value | 0.00 | 0.00 | 1250000000000.00 |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment | 1.25 billion USD |
No. of PPP Projects that reached financial close | Value | 0.00 | 0.00 | 3.00 |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Five feasibility studies completed and submission by contracting authorities to the PPP Committee acceptable to the Association, including Safeguards; ready for market entry | Value | 0.00 | 10.00 | 5.00 |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
Line Ministries and Agencies ?Nodes? for First Mover Transactions established and operational | Value | 0.00 | 57.00 | 2.00 |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
PPP FCCL approved by National Treasury Cabinet Secretary | Value | No | In progress | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
Capital Markets Authority Bill 2011 approved by Cabinet for submission to Parliament | Value | No | Yes | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
Securities and Investments Bill 2011 approved by Cabinet for submission to Parliament | Value | No | Yes | Yes |
Date | December 31, 2012 | December 12, 2016 | December 31, 2017 | |
Comment |
PPP Training Curruculum Developed and Implemented | Value | No Curriculum | No Curriculum | Curriculum developed and approved, implementation |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment |
No. of Government officials with PPP certification from recognized institutions* | Value | 10.00 | 10.00 | 50.00 |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment | base line is "less than 10" | actual is "less than 10" |
No. of Feasibility Studies approved by the PPP Committee | Value | 10.00 | 10.00 | 25.00 |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment |
No. of EOIs/RFQ/RFP issued to prospective PPP private partners | Value | 8.00 | 8.00 | 20.00 |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment |
Report drafted on project stakeholder engagement survey | Value | No | No | Yes |
Date | January 18, 2017 | January 18, 2017 | October 31, 2022 | |
Comment | Citizen engagement will be performed at sub-project level. The surveys will be conducted 1 year after the first financial closureof any sub project. |