Skip to Main Navigation

National Urban Cadaster and Municipal Support Project

Abstract*

The development objective of National Urban Cadaster and Municipal Support Project for Peru is to improve the coverage of urban cadaster services in selected municipalities to enhance local government capacities for revenue generation and urban management. This project has three components. 1) The first component, Strengthening municipal systems, services and capacities to generate and maintain urban cadasters in project municipalities, has the following...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve the coverage of urban cadaster services in selected municipalities to enhance local government capacities for revenue generation and urban management.

Key Details

Project Details

  • P162278

  • Active

  • Gabriel Arrisueno Fajardo , Ivonne Moreno Horta

  • The Republic of Peru

  • Peru

  • November 5, 2018

  • (as of board presentation)

    January 10, 2020

  • August 19, 2020

  • US$ 80.90 million

  • Agency for the Formalization of Informal Property - COFOPRI

  • Latin America and Caribbean

  • 2020

  • US$ 50.00 million

  • B

  • Not Applicable

  • July 31, 2026

  • Yes

  • BANK APPROVED

  • February 8, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 50.00
Borrower/Recipient 30.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 80.90

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 13, 2023 IBRD-90350 Loan Disb 214,504.31
Nov 15, 2023 IBRD-90350 Loan Disb 2,274,765.00
Feb 1, 2021 IBRD-90350 Int Charges 66,627.36
Oct 15, 2020 IBRD-90350 Fee Charges 125,000.00
Jun 7, 2024 IBRD-90350 Loan Disb 1,281,219.00
Feb 1, 2024 IBRD-90350 Int Charges 480.27
Aug 1, 2021 IBRD-90350 Int Charges 61,986.30
Feb 1, 2024 IBRD-90350 Int Charges 58,563.82
Feb 1, 2024 IBRD-90350 Int Charges 110,863.31
Jan 30, 2024 IBRD-90350 Loan Disb 664,257.00
Aug 1, 2024 IBRD-90350 Int Charges 883.18
Aug 1, 2024 IBRD-90350 Int Charges 54,867.56
Aug 1, 2024 IBRD-90350 Int Charges 174,152.90
Aug 1, 2024 IBRD-90350 Int Charges 9.07
Jan 10, 2020 IBRD-90350 Loan Commitment 50,000,000.00
Oct 7, 2022 IBRD-90350 Loan Disb 551,406.75
Feb 1, 2022 IBRD-90350 Int Charges 62,982.13
Sep 6, 2022 IBRD-90350 Loan Disb 18,299.06
Aug 1, 2022 IBRD-90350 Int Charges 55.49
Aug 1, 2022 IBRD-90350 Int Charges 61,578.18
Aug 1, 2022 IBRD-90350 Int Charges 1,821.25
Aug 1, 2022 IBRD-90350 Int Charges 31.57
Jan 18, 2022 IBRD-90350 Loan Disb 329,214.38
Aug 1, 2023 IBRD-90350 Int Charges 749.22
Aug 1, 2023 IBRD-90350 Int Charges 59,522.66
Aug 1, 2023 IBRD-90350 Int Charges 54,357.18
Apr 6, 2023 IBRD-90350 Loan Disb 1,425,155.20
Feb 1, 2023 IBRD-90350 Int Charges 364.91
Feb 1, 2023 IBRD-90350 Int Charges 62,138.36
Feb 1, 2023 IBRD-90350 Int Charges 15,584.72

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2024-12-13
Progress towards achievement of PDO Moderately Satisfactory 2024-12-13
Financial Management Moderately Satisfactory 2024-12-13
Project Management Satisfactory 2024-12-13
Monitoring and Evaluation Satisfactory 2024-12-13
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in the property tax base of project municipalitiesValue0.000.0060.00
    DateJune 28, 2019January 24, 2024February 28, 2025
    Comment
  • Number of people living in project municipalities with improved hazard exposure dataValue0.000.004700000.00
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Of which are femaleValue0.000.000.00
    Date
    Comment
  • Percentage of plots registered by the Project that are linked to land use and zoning dataValue0.000.0075.00
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Methodology updated for improved urban cadastral data collection and maintenanceValueNoNoYes
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Municipalities with property value maps generatedValue0.000.0022.00
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Percentage of grievances/complaints resolved in 20 working daysValue0.00100.0080.00
    DateSeptember 23, 2019January 24, 2024February 28, 2025
    Comment
  • Adoption of updated property valuation methodologyValueNoNoYes
    DateDecember 12, 2019January 24, 2024February 28, 2025
    Comment
  • Communication strategy implemented to inform the target population about the cadastral survey process and its benefitsValueNoNoYes
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Guidelines to ensure urban cadasters are linked to hazard data establishedValueNoNoYes
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Relevant municipal staff trained and certified in management and use of the urban cadasterValue0.000.00100.00
    DateMarch 19, 2019January 24, 2024February 28, 2025
    Comment
  • Percentage of cadastral units updated by the project that register both men and women as property tax payersValue0.000.00100.00
    DateSeptember 23, 2019January 24, 2024February 28, 2025
    Comment