Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
P162454
Active
Mohammed Qaradaghi , Mohammed Al-Ani, Waleed Alhaddad
Republic of Iraq
Iraq
October 19, 2017
(as of board presentation)
May 2, 2019
February 6, 2020
US$ 200.00 million
South Electricity Distribution Company,South Electricity Transmission Company
2019
US$ 200.00 million
B
March 1, 2024
June 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 1, 2023 | IBRD-89600 | Int Charges | 1,135,819.90 |
Nov 1, 2023 | IBRD-89600 | Int Charges | 12,667.66 |
Jun 14, 2024 | IBRD-89600 | Loan Disb | 19,065.01 |
Apr 8, 2024 | IBRD-89600 | Loan Disb | 28,597.51 |
May 2, 2019 | IBRD-89600 | Loan Commitment | 200,000,000.00 |
May 1, 2020 | IBRD-89600 | Int Charges | 326,654.10 |
May 1, 2020 | IBRD-89600 | Int Charges | 2,963.18 |
Feb 6, 2020 | IBRD-89600 | Loan Disb | 500,000.00 |
Feb 6, 2020 | IBRD-89600 | Fee Charges | 500,000.00 |
Nov 1, 2020 | IBRD-89600 | Int Charges | 250,737.70 |
Nov 1, 2020 | IBRD-89600 | Int Charges | 3,552.22 |
Mar 10, 2021 | IBRD-89600 | Loan Disb | 50,000.00 |
May 1, 2022 | IBRD-89600 | Int Charges | 2,563.80 |
May 12, 2022 | IBRD-89600 | Loan Disb | 1,292,441.00 |
Jun 9, 2022 | IBRD-89600 | Loan Disb | 162,785.60 |
May 5, 2022 | IBRD-89600 | Loan Disb | 50,000.00 |
May 6, 2022 | IBRD-89600 | Loan Disb | 50,000.00 |
Nov 1, 2021 | IBRD-89600 | Int Charges | 42.86 |
Nov 1, 2021 | IBRD-89600 | Int Charges | 251,317.47 |
Nov 1, 2021 | IBRD-89600 | Int Charges | 2,511.83 |
Jun 25, 2021 | IBRD-89600 | Loan Disb | 50,000.00 |
Nov 1, 2021 | IBRD-89600 | Int Charges | 17.80 |
May 1, 2021 | IBRD-89600 | Int Charges | 247,079.80 |
May 1, 2021 | IBRD-89600 | Int Charges | 2,111.68 |
Nov 28, 2022 | IBRD-89600 | Int Charges | 438.70 |
Nov 28, 2022 | IBRD-89600 | Int Charges | 240,317.16 |
Nov 28, 2022 | IBRD-89600 | Int Charges | 146,764.55 |
Jan 12, 2022 | IBRD-89600 | Loan Disb | 36,306.00 |
Mar 29, 2022 | IBRD-89600 | Loan Disb | 834,595.00 |
Jun 7, 2022 | IBRD-89600 | Loan Disb | 752,053.30 |
May 31, 2022 | IBRD-89600 | Loan Disb | 489,900.00 |
Jul 12, 2022 | IBRD-89600 | Loan Disb | 3,666,335.50 |
May 24, 2022 | IBRD-89600 | Loan Disb | 3,594,641.00 |
May 1, 2022 | IBRD-89600 | Int Charges | 246,985.62 |
Feb 21, 2023 | IBRD-89600 | Loan Disb | 150,481.61 |
Feb 21, 2023 | IBRD-89600 | Loan Disb | 98,732.11 |
May 9, 2023 | IBRD-89600 | Loan Disb | 504,303.00 |
May 9, 2023 | IBRD-89600 | Loan Disb | 255,833.00 |
Feb 7, 2023 | IBRD-89600 | Loan Disb | 333,557.00 |
May 17, 2023 | IBRD-89600 | Loan Disb | 341,875.00 |
May 1, 2023 | IBRD-89600 | Int Charges | 17.40 |
May 1, 2023 | IBRD-89600 | Int Charges | 10,028.66 |
May 1, 2023 | IBRD-89600 | Int Charges | 217,032.34 |
May 1, 2023 | IBRD-89600 | Int Charges | 634,724.80 |
May 10, 2023 | IBRD-89600 | Loan Disb | 2,923,808.50 |
Nov 16, 2022 | IBRD-89600 | Loan Disb | 163,035.33 |
Dec 16, 2022 | IBRD-89600 | Loan Disb | 4,512,320.00 |
Dec 16, 2022 | IBRD-89600 | Loan Disb | 4,262,130.00 |
Jan 10, 2023 | IBRD-89600 | Loan Disb | 7,351,720.00 |
Nov 1, 2022 | IBRD-89600 | Int Charges | 188.64 |
Dec 9, 2022 | IBRD-89600 | Loan Disb | 69,492.84 |
Nov 15, 2022 | IBRD-89600 | Loan Disb | 887,906.50 |
Sep 21, 2022 | IBRD-89600 | Loan Disb | 61,962.16 |
Oct 24, 2023 | IBRD-89600 | Loan Disb | 6,708,922.50 |
May 18, 2023 | IBRD-89600 | Loan Disb | 156,758.47 |
Jun 2, 2023 | IBRD-89600 | Loan Disb | 113,949.92 |
Jun 2, 2023 | IBRD-89600 | Loan Disb | 1,302,284.80 |
Aug 29, 2023 | IBRD-89600 | Loan Disb | 4,632.01 |
Sep 21, 2023 | IBRD-89600 | Loan Disb | 9,240.00 |
Feb 23, 2023 | IBRD-89600 | Loan Disb | 80,487.04 |
Feb 24, 2023 | IBRD-89600 | Loan Disb | 643,275.50 |
Feb 27, 2023 | IBRD-89600 | Loan Disb | 2,030,543.80 |
Feb 20, 2024 | IBRD-89600 | Loan Disb | 313,516.94 |
May 1, 2024 | IBRD-89600 | Int Charges | 370.22 |
May 1, 2024 | IBRD-89600 | Int Charges | 15,867.36 |
May 1, 2024 | IBRD-89600 | Int Charges | 193,257.03 |
May 1, 2024 | IBRD-89600 | Int Charges | 1,444,027.90 |
Jan 23, 2024 | IBRD-89600 | Loan Disb | 120,336.35 |
Nov 1, 2023 | IBRD-89600 | Int Charges | 204,665.60 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-02-05 |
Project Management | Satisfactory | 2025-02-05 |
Financial Management | Satisfactory | 2025-02-05 |
Procurement | Moderately Satisfactory | 2025-02-05 |
Monitoring and Evaluation | Satisfactory | 2025-02-05 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased efficiency of transmission and distribution network infrastructure | Value | 0.00 | 0.00 | 50.00 |
Date | December 29, 2017 | November 22, 2023 | June 30, 2024 | |
Comment |
Increase in billed to supplied energy ratio | Value | 35.00 | 35.00 | 60.00 |
Date | December 31, 2017 | November 22, 2023 | June 30, 2024 | |
Comment |
Reduction percentage in technical losses | Value | 0.00 | 0.00 | 15.00 |
Date | December 29, 2017 | November 22, 2023 | June 30, 2024 | |
Comment |
Percentage increase in efficiency of transmission and distribution network infrastructure | Value | 111.00 | 111.00 | 42.50 |
Date | December 31, 2017 | November 22, 2023 | December 6, 2024 | |
Comment |
Reduction in technical losses | Value | 10.90 | 10.90 | 9.30 |
Date | December 31, 2017 | November 22, 2023 | December 6, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Capacity of new substations constructed | Value | 0.00 | 0.00 | 750000.00 |
Date | December 29, 2017 | November 22, 2023 | June 30, 2024 | |
Comment |
New 132kV transmission line constructed | Value | 0.00 | 0.00 | 40.00 |
Date | December 29, 2017 | November 22, 2023 | June 30, 2024 | |
Comment |
Women reported engaging in income-generating activities (IGA) due to improvements in electricity service | Value | 0.00 | 0.00 | 20.00 |
Date | June 29, 2018 | November 22, 2023 | June 30, 2024 | |
Comment |
SEDC Business Improvement Plan Prepared and Adopted | Value | No | No | Yes |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
Revenue Protection Program (Energy Meters Installed at Industrial and Commercial Consumers) | Value | 0.00 | 0.00 | 100.00 |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
New substation capacity | Value | 0.00 | 0.00 | 1720000.00 |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
Women-owned businesses reporting increased income due to improved electricity services (percentage) | Value | 0.00 | 0.00 | 20.00 |
Date | June 28, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
SEDC publishes quarterly on its website, Quarterly Performance Reports including Energy Supplied, Billed and Revenue Collections | Value | No | No | Yes |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
Increase in business enterprises reporting increased productivity as a result of improved electricty services reliability | Value | 0.00 | 0.00 | 50.00 |
Date | December 19, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
SEDC publishes on its websites the Electricity Consumers Satisfaction Survey Report | Value | No | No | Yes |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
Increase in jobs | Value | 0.00 | 0.00 | 20.00 |
Date | June 30, 2020 | November 22, 2023 | June 30, 2024 | |
Comment |
Customers satisfied with service provided by SEDC | Value | 0.00 | 0.00 | 25.00 |
Date | March 25, 2019 | November 15, 2023 | June 30, 2024 | |
Comment |
People provided with new or improved electricity service | Value | 0.00 | 0.00 | 2000000.00 |
Date | March 25, 2019 | November 22, 2023 | June 30, 2024 | |
Comment |
People provided with new or improved electricity service - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |