Financier | Commitments |
---|---|
IDA Guarantee | 10.00 |
P162607
Active
Yun Wu , Vincent Launay
Ministry of Finance
April 23, 2019
(as of board presentation)
May 23, 2019
N/A
US$ 130.00 million
Ethiopian Electric Power
2019
US$ 0.00 million
N/A
December 19, 2024
December 31, 2025
BANK APPROVED
Financier | Commitments |
---|---|
IDA Guarantee | 10.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 130.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 23, 2019 | IDA-G2850 | Loan Commitment | 10,000,000.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2022-03-30 |
Monitoring and Evaluation | Satisfactory | 2022-03-30 |
Progress towards achievement of PDO | Moderately Satisfactory | 2022-03-30 |
Procurement | Satisfactory | 2022-03-30 |
Project Management | Satisfactory | 2022-03-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-03-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 1000.00 |
Date | December 31, 2018 | November 24, 2021 | December 31, 2025 | |
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 0.00 | 1000.00 |
Date | December 31, 2018 | November 24, 2021 | December 31, 2025 | |
Comment |
Amount of private capital mobilized under the IPP program | Value | 0.00 | 0.00 | 800.00 |
Date | December 31, 2018 | November 24, 2021 | December 31, 2025 | |
Comment |
Share of private capital (equity and debt) deployed in new IPPs | Value | 25.00 | 25.00 | 65.00 |
Date | December 31, 2018 | November 24, 2021 | December 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Annual greenhouse gas emission reductions | Value | 0.00 | 0.00 | 1000.00 |
Date | December 31, 2018 | March 20, 2024 | December 30, 2022 | |
Comment |
Increased renewable energy generation capacity under the IPP program that has reached financial close | Value | 0.00 | 0.00 | 100.00 |
Date | December 31, 2018 | March 20, 2024 | June 30, 2020 | |
Comment |
Total number of IPP plants that have completed construction | Value | 0.00 | 0.00 | 1.00 |
Date | December 31, 2018 | March 20, 2024 | June 30, 2021 | |
Comment |
Total number of IPP plants that have begun construction | Value | 0.00 | 0.00 | 1.00 |
Date | December 31, 2018 | March 20, 2024 | June 30, 2020 | |
Comment |
Standard documents for IPP procurement published online | Value | 0.00 | 2.00 | 4.00 |
Date | December 31, 2018 | March 20, 2024 | December 31, 2020 | |
Comment |
EEP’s Gender Action Plan under implementation with regular progress reporting | Value | No | Yes | Yes |
Date | December 31, 2018 | March 20, 2024 | December 31, 2019 | |
Comment |
Response rate under the project’s GRM | Value | 0.00 | 0.00 | 100.00 |
Date | December 31, 2018 | March 20, 2024 | December 31, 2019 | |
Comment |