Renewable Energy Guarantees Program

Abstract*

The objective of the Renewable Energy Guarantees Program Project for Ethiopia is to increase renewable energy generation capacity through private sector participation in Ethiopia. There is one component to the project, the first component being Metehara Solar IPP. The REGREP first phase consists of IDA guarantee support to the Metehara Solar IPP (100 MW), which is the most advanced IPP transaction. The Metehara Solar IPP is expected to be operational...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO for REGREP Phase 1 is to increase renewable energy generation capacity t hrough private sector participation in Ethiopia.

Key Details

Project Details

  • P162607

  • Active

  • Yun Wu , Vincent Launay

  • Ministry of Finance

  • Ethiopia

  • April 23, 2019

  • (as of board presentation)

    May 23, 2019

  • N/A

  • US$ 0.00 million

  • N/A

  • December 19, 2024

  • December 31, 2025

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Guarantee 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount N/A
Total Project Cost** 130.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 23, 2019 IDA-G2850 Loan Commitment 10,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2022-03-30
Monitoring and Evaluation Satisfactory 2022-03-30
Progress towards achievement of PDO Moderately Satisfactory 2022-03-30
Procurement Satisfactory 2022-03-30
Project Management Satisfactory 2022-03-30
Overall Implementation Progress (IP) Moderately Satisfactory 2022-03-30

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of energy constructed or rehabilitatedValue0.000.001000.00
    DateDecember 31, 2018November 24, 2021December 31, 2025
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.000.001000.00
    DateDecember 31, 2018November 24, 2021December 31, 2025
    Comment
  • Amount of private capital mobilized under the IPP programValue0.000.00800.00
    DateDecember 31, 2018November 24, 2021December 31, 2025
    Comment
  • Share of private capital (equity and debt) deployed in new IPPsValue25.0025.0065.00
    DateDecember 31, 2018November 24, 2021December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual greenhouse gas emission reductionsValue0.000.001000.00
    DateDecember 31, 2018March 20, 2024December 30, 2022
    Comment
  • Increased renewable energy generation capacity under the IPP program that has reached financial closeValue0.000.00100.00
    DateDecember 31, 2018March 20, 2024June 30, 2020
    Comment
  • Total number of IPP plants that have completed constructionValue0.000.001.00
    DateDecember 31, 2018March 20, 2024June 30, 2021
    Comment
  • Total number of IPP plants that have begun constructionValue0.000.001.00
    DateDecember 31, 2018March 20, 2024June 30, 2020
    Comment
  • Standard documents for IPP procurement published onlineValue0.002.004.00
    DateDecember 31, 2018March 20, 2024December 31, 2020
    Comment
  • EEP’s Gender Action Plan under implementation with regular progress reportingValueNoYesYes
    DateDecember 31, 2018March 20, 2024December 31, 2019
    Comment
  • Response rate under the project’s GRMValue0.000.00100.00
    DateDecember 31, 2018March 20, 2024December 31, 2019
    Comment