Enhancing Community Driven Development Project

Abstract*

The development objective of the Enhancing Community Driven Development Project for Myanmar is to enable poor rural communities to benefit from improved access to and use of basic infrastructure and services through a people-centered approach. The project comprises of four components. The first component is community block grants. Block grants are allocated through a participatory planning process comprising all villages within a village tract. The...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective is to enable poor rural communities to benefit from improved access to and use of basic infrastructure and services through a people-centered approach.

Key Details

Project Details

  • P162647

  • Closed

  • Sean Bradley , Patricia Maria Fernandes, Natacha Lemasle

  • Republic of the Union of Myanmar

  • Myanmar

  • July 5, 2017

  • (as of board presentation)

    November 9, 2020

  • November 26, 2020

  • US$ 25.00 million

  • Department of Rural Development, Ministry of Agriculture, Livestock and Irrigation

  • East Asia and Pacific

  • 2021

  • US$ 25.00 million

  • B

  • June 28, 2024

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Japan Social Development Fund 25.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 25.00
Total Project Cost** 25.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiaries (Number, Custom)Value0.000.00400000.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Female beneficiaries (Percentage, Custom Supplement)Value0.000.0050.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Number of persons having access to and use of project-built infrastructure and services (e.g. all-weather roads, water, schools, health services) (Number)Value0.000.00400000.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Percent of households in project villages participating in planning, decision-making, and implementation of sub-projects (Percentage, Custom)Value0.000.0050.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Percent of community members satisfied with the project (Percentage, Custom)Value0.000.0090.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual township stakeholder reviews conducted (Number, Custom)Value0.000.0020.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • % of annual significant financial audit findings addressed (misuse of funds, non-compliance with procedures) (Percentage, Custom)Value0.000.0095.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • #/type of rural infrastructure built (Number, Custom)Value0.000.002000.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • # of community members using their new skills in project planning, financial management, and procurement (Number, Custom)Value0.000.002500.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Grievances related to delivery of project benefits that are addressed (Percentage, Custom)Value0.000.0085.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Timeliness and satisfactory quality of financial reporting and of annual Project auditsValue0.000.0085.00
    DateJanuary 31, 2020February 19, 2021December 31, 2023
    Comment
  • % of sub-projects evaluated independently meeting project operations manual technical and safeguard specifications (Percentage, Custom)Value0.000.0085.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Number of Community Facilitators and Technical Facilitators trained and using their participatory development skillsValue0.000.00500.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • ECDDP community engagement process evaluations completedValue0.000.002.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • Allocation of adequate DRD staff for Project implementation at union and township levelsValueNoYesYes
    DateJanuary 31, 2020February 19, 2021December 31, 2023
    Comment
  • % of sub-projects evaluated as high priority by communitiesValue0.000.0090.00
    DateJanuary 15, 2019February 19, 2021March 31, 2023
    Comment
  • # of internal cross-township learning exchanges (Number, Custom)Value0.000.0010.00
    DateDecember 12, 2017February 19, 2021November 30, 2021
    Comment
  • # of Government officials using their new skills in project management, engineering, planning (Number, Custom)Value0.000.0050.00
    DateDecember 12, 2017February 19, 2021November 30, 2021
    Comment
  • Timeliness and quality of NCDDP quarterly and annual reports, with dedicated annexes on JSDF grant activitiesValue0.000.0085.00
    DateJanuary 31, 2020February 19, 2021December 31, 2023
    Comment
  • Improved community perceptions of quality of project community engagement activities over timeValue0.000.0080.00
    DateJanuary 31, 2020February 19, 2021December 31, 2023
    Comment