West Bengal Major Irrigation and Flood Management Project

Abstract*

The development objective of West Bengal Major Irrigation and Flood Management Project for India are to improve irrigation service delivery, strengthen flood risk management and improve climate change resilience in the project area. This project has two components. 1) The first component, Irrigation Management, aims to improve the management of the DVCA irrigation scheme. It has the following five subcomponents. It has the following five subcomponents:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives are to improve irrigation service delivery, strengthen flood risk management and improve climate change resilience in the Project area. Improving irrigation services includes management reforms as pursued under Component A, and infrastructure modernization to reinforce the management improvements under Component B. Strengthening flood risk management is adressed under Component C. These improvements together will help improve the resilience of the Project area to climate change.

Key Details

Project Details

  • P162679

  • Active

  • Joop Stoutjesdijk , Qiong Lu

  • Republic of India

  • India

  • November 22, 2018

  • (as of board presentation)

    December 10, 2019

  • August 11, 2020

  • US$ 413.80 million

  • Irrigation and Waterways Department of West Bengal

  • South Asia

  • 2020

  • US$ 290.00 million

  • B

  • January 17, 2024

  • November 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Asian Infrastructure Investment Bank 145.00
International Bank for Reconstruction and Development 145.00
Borrower/Recipient 123.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 145.00
IDA Commitment N/A
IBRD + IDA Commitment 145.00
Lending Instrument
Grant Amount 145.00
Total Project Cost** 413.80

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 18, 2021 IBRD-90250 Loan Disb 2,891,081.50
Aug 11, 2020 IBRD-90250 Fee Charges 362,500.00
Aug 11, 2020 IBRD-90250 Loan Disb 362,500.00
Oct 29, 2020 IBRD-90250 Loan Disb 2,245,904.80
Sep 7, 2021 IBRD-90250 Loan Disb 1,064,043.50
Aug 12, 2021 IBRD-90250 Loan Disb 1,885,622.10
Dec 1, 2021 IBRD-90250 Int Charges 2,152.13
Dec 1, 2021 IBRD-90250 Int Charges 7,099.60
Dec 1, 2021 IBRD-90250 Int Charges 152,905.19
Dec 1, 2021 IBRD-90250 Int Charges 114,315.39
Mar 28, 2024 IBRD-90250 Loan Disb 8,722,601.00
Jun 1, 2024 IBRD-90250 Int Charges 4,973.03
Jun 1, 2024 IBRD-90250 Int Charges 136,464.58
Dec 10, 2019 IBRD-90250 Loan Commitment 145,000,000.00
Oct 8, 2021 IBRD-90250 Loan Disb 724,772.44
Nov 3, 2021 IBRD-90250 Loan Disb 2,012,543.40
Apr 27, 2021 IBRD-90250 Loan Disb 8,977,420.00
Jun 1, 2021 IBRD-90250 Int Charges 506.26
Jun 1, 2021 IBRD-90250 Int Charges 2,190.71
Sep 2, 2022 IBRD-90250 Loan Disb 5,230,356.50
Jan 13, 2022 IBRD-90250 Loan Disb 1,266,979.80
Jun 1, 2022 IBRD-90250 Int Charges 1,998.44
Jun 1, 2022 IBRD-90250 Int Charges 143,198.40
Jun 1, 2022 IBRD-90250 Int Charges 157,281.58
Jun 1, 2022 IBRD-90250 Int Charges 654.04
Mar 10, 2022 IBRD-90250 Loan Disb 1,741,861.40
Jun 29, 2022 IBRD-90250 Loan Disb 3,541,555.20
Apr 8, 2022 IBRD-90250 Loan Disb 4,450,268.50
Mar 22, 2023 IBRD-90250 Loan Disb 8,967,312.00
Apr 19, 2023 IBRD-90250 Loan Disb 5,068,078.50
Oct 24, 2022 IBRD-90250 Loan Disb 4,496,185.00
Dec 1, 2022 IBRD-90250 Int Charges 1,645.99
Dec 1, 2022 IBRD-90250 Int Charges 5,563.45
Dec 1, 2022 IBRD-90250 Int Charges 130,345.04
Dec 1, 2022 IBRD-90250 Int Charges 712,363.70
Jan 9, 2023 IBRD-90250 Loan Disb 3,669,154.80
Dec 1, 2023 IBRD-90250 Int Charges 81,238.17
Dec 1, 2023 IBRD-90250 Int Charges 2,404,400.80
Dec 1, 2023 IBRD-90250 Int Charges 1,492.65
Jun 1, 2023 IBRD-90250 Int Charges 89,968.90
Jun 1, 2023 IBRD-90250 Int Charges 111,755.60
Jun 1, 2023 IBRD-90250 Int Charges 1,469,166.80
Jun 1, 2023 IBRD-90250 Int Charges 1,170.24
Jun 6, 2023 IBRD-90250 Loan Disb 5,018,383.00
Jul 12, 2023 IBRD-90250 Loan Disb 7,554,950.00
Jun 1, 2024 IBRD-90250 Int Charges 48,665.32
Jun 1, 2024 IBRD-90250 Int Charges 3,555,075.20
Feb 1, 2024 IBRD-90250 Loan Disb 7,550,941.50
Dec 4, 2023 IBRD-90250 Loan Disb 7,555,247.00
Oct 4, 2023 IBRD-90250 Loan Disb 12,518,319.00
Dec 1, 2023 IBRD-90250 Int Charges 71,410.80
Sep 17, 2020 IBRD-90250 Loan Disb 266,692.97
Sep 3, 2020 IBRD-90250 Loan Disb 1,488,109.20
Jun 1, 2021 IBRD-90250 Int Charges 169,681.69
Jun 1, 2021 IBRD-90250 Int Charges 37,993.69
Jun 30, 2021 IBRD-90250 Loan Disb 3,198,446.20
Dec 1, 2020 IBRD-90250 Int Charges 136,836.34
Dec 1, 2020 IBRD-90250 Int Charges 7,024.64
Jan 7, 2021 IBRD-90250 Loan Disb 1,927,013.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-13
Project Management Satisfactory 2024-12-13
Progress towards achievement of PDO Satisfactory 2024-12-13
Financial Management Satisfactory 2024-12-13
Monitoring and Evaluation Satisfactory 2024-12-13
Overall Implementation Progress (IP) Satisfactory 2024-12-13

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Rate of reduced flood depth at the monitoring points compared with equivalent flood depth from 2008-2017Value0.0095.0030.00
    DateMay 29, 2018December 31, 2023November 30, 2025
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.00241611.00376448.00
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Arrest in the rate of decline of groundwater levels in semi-critical blocks in each defined groundwater management areaValue0%0.0050 percent in area south of Damodar River; 50 perr
    DateOctober 30, 2018December 31, 2023November 30, 2025
    Comment
  • No deterioration of groundwater level trends in safe blocks in each defined groundwater management areaValue0%0100 percent in area south of Damodar River; 100 pe
    DateOctober 30, 2018December 31, 2023November 30, 2025
    Comment
  • Area provided with improved irrigation or drainage servicesValue0.00241611.00376448.00
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Compliance with agreed water delivery schedule of the ISPs' contractValue0.000.0090.00
    DateMay 29, 2018December 31, 2023November 30, 2025
    Comment
  • Compliance with irrigation water supply from Main Canal to Distributary CanalValue0.000.0090.00
    DateMay 29, 2018December 31, 2023November 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Groundwater study completed to the satisfaction of the BankValueNot yet startedCompletedCompleted
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Percentage of women engineers recruited by IWDValue4.504.507.00
    DateMarch 25, 2019December 31, 2023November 30, 2025
    Comment
  • Length of main canals modernizedValue0.00127.00166.90
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Three modules of MIS functionalValueNONEFunctionalFully functional
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Length of river embankment rehabilitatedValue0.00127.00111.00
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Number of Project monitoring reports submitted on time annuallyValue0.004.004.00
    DateDecember 14, 2018December 31, 2023November 30, 2025
    Comment
  • Grievances registered related to delivery of project benefits that are resolvedValue0.0098.0080.00
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment
  • Of which femalesValue0.0020.0035.00
    DateDecember 14, 2018December 31, 2023November 30, 2025
    Comment
  • Asset Management Plan preparedValueNoNoYes
    DateJune 1, 2018December 31, 2023November 30, 2025
    Comment