Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 125.00 |
Borrower/Recipient | 25.00 |
P162712
Closed
Maria Ramirez , Lizmara Kirchner
N/A
February 22, 2017
(as of board presentation)
March 24, 2017
N/A
US$ 150.00 million
Ministry of Interior, Public Works and Housing, UCPyPFE
2017
US$ 125.00 million
A
Not Applicable
June 30, 2023
Yes
BANK APPROVED
November 14, 2022
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 125.00 |
Borrower/Recipient | 25.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 125.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 125.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 0.00 | 200000.00 |
Date | March 26, 2012 | April 28, 2017 | ||
Comment |
Number of Service providers that have a monitoring system implemented (control panel) for decision making to improve management | Value | 0.00 | 3.00 | 3.00 |
Date | March 26, 2012 | November 1, 2016 | April 28, 2017 | |
Comment |
People provided with access to “improved sanitation facilities” - urban | Value | 0.00 | 0.00 | 200000.00 |
Date | March 26, 2012 | April 28, 2017 | ||
Comment |
People provided with access to “improved sanitation facilities”- rural | Value | 0.00 | 0.00 | 0.00 |
Date | March 26, 2012 | April 28, 2017 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 450000.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment |
Number of Service providers achieving a 90 percent increase in the cost recovery ratio [1] | Value | 0.00 | 0.00 | 5.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment | [1] Measured as collected revenue from WSS bills over O&M costs | [1] Measured as collected revenue from WSS bills over O&M costs |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment |
People provided with access to improved water services under the project | Value | 0.00 | 0.00 | 250000.00 |
Date | March 26, 2012 | December 26, 2016 | February 28, 2019 | |
Comment |
People provided with access to "improved sanitation services"under the project | Value | 0.00 | 0.00 | 210000.00 |
Date | March 26, 2012 | December 26, 2016 | April 30, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 0.00 | 200000.00 |
Date | August 1, 2011 | October 14, 2016 | April 28, 2017 | |
Comment |
Km of sewerage collectors rehabilitated under the Project | Value | 0.00 | 20.00 | 25.00 |
Date | August 1, 2011 | October 14, 2016 | April 28, 2017 | |
Comment |
Number of water utilities that the project is supporting | Value | 0.00 | 4.00 | 4.00 |
Date | August 1, 2011 | October 14, 2016 | April 28, 2017 | |
Comment |
Number of subprojects prepared that meet Project elegibility criteria to be approved for funding | Value | 0.00 | 0.00 | 14.00 |
Date | August 1, 2016 | November 1, 2016 | April 30, 2020 | |
Comment |
Evidence that the UCPyPFE unit in charge of Project implementation is operational and functions effectively as evidenced by the timely preparation of financial management and other monitoring reports | Value | No | Yes | Yes |
Date | August 1, 2011 | October 14, 2016 | August 1, 2016 | |
Comment |
Development, launching anmd continuing the implementation of a Communication Strategy for the Project following the project desing guidelines | Value | No | Yes | Yes |
Date | August 1, 2011 | October 14, 2016 | August 1, 2016 | |
Comment |
Volume of treated wastewater that complies with the provincial and federal standard for effluent discharged due to investments madeunder the project | Value | 0.00 | 0.00 | 48000.00 |
Date | February 2, 2015 | April 28, 2017 | ||
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | August 1, 2011 | October 14, 2016 | April 28, 2017 | |
Comment |
Number of MRPs elaborated and approved | Value | 0.00 | 0.00 | 10.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment |
Number of service providers that have a monitoring system implemented (control panel) for decision making to improve management | Value | 3.00 | 3.00 | 5.00 |
Date | November 30, 2016 | December 26, 2016 | February 28, 2019 | |
Comment |
Number of capital cities where 90 percent of produced water is macro-metered | Value | 2.00 | 2.00 | 5.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment |
Percentage of billed connections that are metered and read | Value | 41.00 | 41.00 | 60.00 |
Date | November 30, 2016 | December 26, 2016 | April 30, 2020 | |
Comment | Percentage of connections that are metered and read over the total number of connections billed, by user type (residential and noresidential) | Percentage of connections that are metered and read over the total number of connections billed, by user type (residential and noresidential) |