Turkey Energy Efficiency in Public Buildings

Abstract*

The objective of the Energy Efficiency in Public Buildings in Turkey is to reduce energy use in central government buildings and inform the development of sustainable financing mechanisms to support a scaled-up, national program for energy efficiency in public buildings. The first component will support the renovation of central government and central-government affiliated buildings (i.e., public buildings under central line ministries, such as schools...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objectives are to reduce energy use in central government buildings and inform the development of sustainable financing mechanisms to support a scaled-up, national program for energy efficiency in public buildings.

Key Details

Project Details

  • P162762

  • Active

  • Aditya Lukas

  • Republic of Turkey

  • Turkiye

  • May 7, 2018

  • (as of board presentation)

    November 5, 2019

  • March 16, 2020

  • US$ 200.00 million

  • Ministry of Energy and Natural Resources,Ministry of Environment, Urbanization and Climate Change, General Directorate of Construction Works

  • Europe and Central Asia

  • 2020

  • US$ 200.00 million

  • B

  • May 6, 2024

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 150.00
Clean Technology Fund 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount 50.00
Total Project Cost** 200.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2021 IBRD-90150 Loan Disb 5,152,938.50
Sep 24, 2021 IBRD-90150 Loan Disb 1,173,500.00
Jul 15, 2021 IBRD-90150 Int Charges 196,764.97
Jul 15, 2021 IBRD-90150 Int Charges 103.24
Jul 15, 2021 IBRD-90150 Int Charges 46.24
Apr 15, 2021 IBRD-90150 Loan Disb 1,351,192.40
Dec 9, 2020 IBRD-90150 Loan Disb 605,650.00
Jan 15, 2021 IBRD-90150 Int Charges 206,611.33
Jan 15, 2021 IBRD-90150 Int Charges 249.05
Jan 15, 2022 IBRD-90150 Int Charges 186,223.80
Jul 15, 2022 IBRD-90150 Int Charges 2,601.77
Jul 15, 2022 IBRD-90150 Int Charges 148,098.06
Jun 23, 2022 IBRD-90150 Loan Disb 2,968,086.20
Jun 13, 2022 IBRD-90150 Loan Disb 1,046,900.00
Jul 12, 2022 IBRD-90150 Loan Disb 3,926,530.00
Mar 11, 2022 IBRD-90150 Loan Disb 1,793,768.20
Oct 15, 2021 IBRD-90150 Loan Disb 2,201,844.80
Aug 26, 2021 IBRD-90150 Loan Disb 1,661,286.20
Dec 6, 2023 IBRD-90150 Loan Disb 6,304,871.50
May 17, 2023 IBRD-90150 Loan Disb -3,787,314.00
Aug 25, 2023 IBRD-90150 Loan Disb 3,319,448.00
Jan 15, 2023 IBRD-90150 Int Charges 152,528.50
Jan 15, 2023 IBRD-90150 Int Charges 111,140.08
Jan 15, 2023 IBRD-90150 Int Charges 784.36
Jun 1, 2023 IBRD-90150 Loan Disb 3,745,010.50
Jul 12, 2023 IBRD-90150 Loan Disb 1,844,583.10
Mar 7, 2023 IBRD-90150 Loan Disb 1,174,282.40
May 17, 2023 IBRD-90150 Loan Disb 3,787,325.00
Nov 8, 2022 IBRD-90150 Loan Disb 1,833,543.10
Mar 1, 2024 IBRD-90150 Loan Disb 3,245,700.00
May 7, 2024 IBRD-90150 Loan Disb 13,915,768.00
Jan 15, 2024 IBRD-90150 Int Charges 14,847.67
Jan 15, 2024 IBRD-90150 Int Charges 131,611.89
Jan 15, 2024 IBRD-90150 Int Charges 942,339.90
Jan 15, 2024 IBRD-90150 Int Charges 1,191.20
Apr 5, 2024 IBRD-90150 Loan Disb 14,328,921.00
Nov 27, 2023 IBRD-90150 Loan Disb 1,643,100.00
Dec 20, 2023 IBRD-90150 Loan Disb 7,356,318.00
Oct 13, 2023 IBRD-90150 Loan Disb 3,033,279.50
Nov 7, 2023 IBRD-90150 Loan Disb 9,042,884.00
Jul 15, 2023 IBRD-90150 Int Charges 474,459.12
Jul 15, 2023 IBRD-90150 Int Charges 152,574.17
Jul 15, 2024 IBRD-90150 Int Charges 3,600.08
Jul 15, 2024 IBRD-90150 Int Charges 61,444.02
Jul 15, 2024 IBRD-90150 Int Charges 69,811.10
Jul 15, 2024 IBRD-90150 Int Charges 2,015,214.50
Aug 1, 2024 IBRD-90150 Loan Disb 9,022,298.00
Mar 25, 2024 IBRD-90150 Loan Disb 6,490,800.00
Jun 11, 2024 IBRD-90150 Loan Disb 10,155,477.00
Jan 25, 2024 IBRD-90150 Loan Disb 5,963,447.50
Nov 5, 2019 IBRD-90150 Loan Commitment 150,000,000.00
Oct 29, 2020 IBRD-90150 Loan Disb -585,875.00
Jul 15, 2020 IBRD-90150 Int Charges 165,671.56
Nov 5, 2019 TF-B0782 Loan Commitment 46,200,000.00
Oct 19, 2020 IBRD-90150 Loan Disb 588,375.00
Oct 30, 2020 IBRD-90150 Loan Disb 583,650.00
May 13, 2020 IBRD-90150 Fee Charges 369,138.38
Aug 11, 2021 IBRD-90150 Loan Disb 1,171,500.00
Aug 19, 2021 IBRD-90150 Loan Disb -1,169,288.20
Dec 3, 2021 IBRD-90150 Loan Disb 2,712,168.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-12
Financial Management Satisfactory 2024-12-12
Monitoring and Evaluation Satisfactory 2024-12-12
Overall Implementation Progress (IP) Satisfactory 2024-12-12
Procurement Satisfactory 2024-12-12
Project Management Satisfactory 2024-12-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Projected energy or fuel savingsValue0.004076325285.0012000000000.00
    DateApril 11, 2019December 11, 2023December 31, 2025
    Comment
  • Design and submission for approval of sustainable financing mechanisms to support a national program for energy efficiency in public buildingsValueNo sustainable financing mechanisms in placeConsultations on sustainable financing mechanisms Sustainable financing mechanisms endorsed by MENR
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Projected lifetime energy savingsValue0.004076325285.0012000000000.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Projected lifetime emissions reductions as a result of the energy savingsValue0.00470402.001450000.00
    DateJuly 8, 2019December 11, 2023December 31, 2025
    Comment
  • Completion of policy analyses and development of recommendations to support the transition to sustainable financing in public buildingsValueNo analysis of policy and regulatory barriers for Regulatory amendments prepared and debatedRegulatory mechanisms adopted
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Annual energy savingsValue0.0056.64166.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Development of a national program for energy efficiency in public buildings with sustainable financing and institutional mechanismsValueNo national program or plans in placeDraft national program plan developedNational program plan submitted for adoption
    DateJuly 8, 2019December 11, 2023December 31, 2025
    Comment
  • Annual emissions reductions (CO2)Value0.0023520.0070000.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Percentage satisfaction with the renovation processes, including consultations, and resultsValue0.0093.0090.00
    DateJuly 22, 2019December 11, 2023December 31, 2025
    Comment
  • Number of buildings blocks commissionedValue0.0074.00340.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Percentage of femalesValue0.0063.0050.00
    DateJuly 22, 2019December 11, 2023December 31, 2025
    Comment
  • Annual energy costs savings (TRY)Value0.00118984325.00350000000.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Number of building blocks where monitoring meetings have been organizedValue0.00210.00135.00
    DateJuly 22, 2019December 11, 2023December 31, 2025
    Comment
  • Generation capacity of energy constructed or rehabilitatedValue0.004.7314.40
    DateApril 11, 2019December 11, 2023December 31, 2025
    Comment
  • Renewable energy generation capacity (other than hydropower) constructed under the projectValue0.004.7314.40
    DateApril 11, 2019December 11, 2023December 31, 2025
    Comment
  • Number of ESCO contracts signedValue0.001.001.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Number of pilot NZEBs implementedValue0.000.009.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Number of beneficiaries in renovated buildingsValue0.0021485.0071300.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Percentage of femalesValue0.0053.0045.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Number of people trainedValue0.002424.002500.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Percentage of female participantsValue0.0028.0020.00
    DateApril 29, 2019December 11, 2023December 31, 2025
    Comment
  • Number of females that participate in technical trainings organized by the PIU on energy audits, technical designs, and construction supervisionValue0.00224.00240.00
    DateJuly 8, 2019December 11, 2023December 31, 2025
    Comment
  • Percentage of women in energy audit and design/construction supervision firms contracted under Project who are key staffValue0.0038.2528.00
    DateApril 29, 2019December 11, 2023December 31, 2025