Financier | Commitments |
---|---|
IDA Grant | 20.00 |
Support for Small Island Developing States (SIDS) DOCK Suppo | 2.60 |
IDA Credit | 20.00 |
P162783
Closed
Claudio Miguel Jamisse Buque
Government of the Union of Comoros
February 28, 2020
(as of board presentation)
June 22, 2020
N/A
US$ 42.60 million
Ministry of Production, Environment, Energy, Industry and Handicrafts
2020
US$ 42.60 million
B
September 22, 2023
March 28, 2024
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 20.00 |
Support for Small Island Developing States (SIDS) DOCK Suppo | 2.60 |
IDA Credit | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | 2.60 |
Total Project Cost** | 42.60 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 22, 2020 | IDA-D6680 | Loan Commitment | 20,000,000.00 |
Jun 22, 2020 | IDA-66980 | Loan Commitment | 20,000,000.00 |
Jun 19, 2021 | IDA-66980 | Loan Cancel | 21,929,120.00 |
Jun 19, 2021 | IDA-D6680 | Loan Cancel | 21,002,332.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2021-10-05 |
Monitoring and Evaluation | Satisfactory | 2021-10-05 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-10-05 |
Overall Safeguards Rating | Satisfactory | 2021-10-05 |
Procurement | Moderately Satisfactory | 2021-10-05 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-10-05 |
Overall Safeguards Rating | Satisfactory | 2021-10-05 |
Project Management | Moderately Satisfactory | 2021-10-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Capacity of the National Utility to dispatch variable renewable electricity | Value | 0.00 | 0.00 | 18.50 |
Date | February 27, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Average SONELEC billing rate across all three island systems | Value | 65.00 | 65.00 | 76.00 |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
Average SONELEC collection rate across all three island systems | Value | 81.00 | 81.00 | 85.00 |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Delegated Sector Oversight and Contracting Unit (DSOCU) established | Value | No | No | Yes |
Date | December 2, 2019 | September 15, 2021 | September 30, 2020 | |
Comment |
Power storage capacity installed across the three islands | Value | 0.00 | 0.00 | 19.00 |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
Customer management software rolled out across all three islands | Value | No | No | Yes |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
Number of local energy sector staff trained or mentored under DSOCU | Value | 0.00 | 0.00 | 5.00 |
Date | February 11, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Automated dispatch and power control systems installed on all three islands | Value | No | No | Yes |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
Pre-paid meters installed | Value | 1400.00 | 1400.00 | 96400.00 |
Date | December 2, 2019 | September 15, 2021 | June 30, 2025 | |
Comment |
Electricity sector master plan updated | Value | No | No | Yes |
Date | February 11, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Generation capacity of energy constructed or rehabilitated | Value | 0.00 | 0.00 | 9.00 |
Date | February 11, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Female electricity sector employees | Value | 19.00 | 19.00 | 25.00 |
Date | February 10, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Complaints received through GRM addressed (citizen engagement indicator) | Value | 0.00 | 0.00 | 90.00 |
Date | March 4, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Baseline for electricity service quality established | Value | No | No | Yes |
Date | March 31, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |
Renewable energy generation capacity (other than hydropower) constructed under the project | Value | 0.00 | 0.00 | 9.00 |
Date | February 11, 2020 | September 15, 2021 | June 30, 2025 | |
Comment |