Skip to Main Navigation

Improving the Performance of Non-Criminal Justice Services

Abstract*

The development objectives of Improving the Performance of Non-Criminal Justice Services Project for Peru is to improve efficiency, access, transparency, and user satisfaction, in the delivery of adequate non-criminal justice services. This project has four components. 1) The first component, Strengthening the institutionality of the non-criminal justice administration system, aims to support more efficient and transparent justice services through...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project’s development objective is to improve efficiency, access, transparency, and user satisfaction, in the delivery of adequate non-criminal justice services.

Key Details

Project Details

  • P162833

  • Active

  • Ruben Ruano Chinchilla

  • Republic of Peru

  • Peru

  • February 23, 2018

  • (as of board presentation)

    June 5, 2019

  • December 12, 2019

  • US$ 158.13 million

  • Ministry of Justice and Human Rights,Judiciary of Peru

  • Latin America and Caribbean

  • 2019

  • US$ 85.00 million

  • B

  • Not Applicable

  • August 31, 2025

  • Yes

  • BANK APPROVED

  • February 6, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 85.00
Borrower/Recipient 73.13

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 85.00
IDA Commitment N/A
IBRD + IDA Commitment 85.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 158.13

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2022 IBRD-89750 Int Charges 99,334.92
Sep 15, 2020 IBRD-89750 Int Charges 106,830.60
Dec 5, 2023 IBRD-89750 Loan Disb 896,327.00
Aug 9, 2023 IBRD-89750 Loan Disb 6,628,481.00
Sep 15, 2023 IBRD-89750 Int Charges 3,815.92
Sep 15, 2023 IBRD-89750 Int Charges 90,796.42
Sep 15, 2023 IBRD-89750 Int Charges 327,636.38
May 26, 2023 IBRD-89750 Loan Disb 1,635,603.00
Mar 15, 2023 IBRD-89750 Int Charges 7,525.59
Mar 15, 2023 IBRD-89750 Int Charges 94,640.99
Mar 15, 2023 IBRD-89750 Int Charges 214,646.44
Mar 15, 2024 IBRD-89750 Int Charges 44,084.74
Mar 15, 2024 IBRD-89750 Int Charges 81,637.06
Mar 15, 2024 IBRD-89750 Int Charges 608,751.00
Mar 15, 2024 IBRD-89750 Int Charges 1,679.81
Mar 6, 2024 IBRD-89750 Loan Disb 1,022,957.00
Jun 5, 2019 IBRD-89750 Loan Commitment 85,000,000.00
Feb 25, 2020 IBRD-89750 Fee Charges 212,500.00
Dec 11, 2020 IBRD-89750 Loan Disb 35,604.00
Dec 11, 2020 IBRD-89750 Loan Disb 177,469.00
Feb 9, 2021 IBRD-89750 Loan Disb 30,160.00
Mar 15, 2021 IBRD-89750 Int Charges 105,060.79
Mar 15, 2021 IBRD-89750 Int Charges 433.95
Sep 15, 2021 IBRD-89750 Int Charges 7.02
Sep 15, 2021 IBRD-89750 Int Charges 15.20
Sep 15, 2021 IBRD-89750 Int Charges 106,597.16
Sep 15, 2021 IBRD-89750 Int Charges 1,297.49
Aug 23, 2021 IBRD-89750 Loan Disb 479,282.00
Sep 15, 2021 IBRD-89750 Loan Disb 4,680,909.00
Mar 26, 2021 IBRD-89750 Loan Disb 121,581.00
Sep 15, 2022 IBRD-89750 Int Charges 52,885.82
Dec 2, 2022 IBRD-89750 Loan Disb 795,643.00
Mar 15, 2022 IBRD-89750 Int Charges 141.91
Mar 15, 2022 IBRD-89750 Int Charges 98,527.23
Mar 15, 2022 IBRD-89750 Int Charges 18,889.39
Mar 15, 2022 IBRD-89750 Int Charges 75.50
May 26, 2022 IBRD-89750 Loan Disb 1,075,891.00
Sep 15, 2020 IBRD-89750 Int Charges 28,449.46
Dec 15, 2022 IBRD-89750 Loan Disb 3,230,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2025-02-18
Progress towards achievement of PDO Moderately Unsatisfactory 2025-02-18
Procurement Moderately Satisfactory 2025-02-18
Financial Management Moderately Satisfactory 2025-02-18
Monitoring and Evaluation Moderately Satisfactory 2025-02-18
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Processing time between the presentation of a claim and the decision that resolves the case (not including the enforcement period) in courts where EJE will be implementedValue21.1024.8517.50
    DateJune 28, 2018January 31, 2024September 2, 2024
    Comment
  • Percentage of users who access their case file and case status onlineValueNot available3770
    DateJune 28, 2018January 31, 2024September 30, 2024
    Comment
  • Percentage of female users satisfied with the services provided at the ALEGRAsValue667181
    DateApril 15, 2021January 31, 2024June 28, 2024
    Comment
  • Percentage of users satisfied with the service provided in a representative sample of non-criminal courtsValueNot available47.465
    DateJanuary 2, 2023January 31, 2024September 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of non-criminal jurisdictional units where EJE has been implementedValue5.007.00100.00
    DateDecember 19, 2018January 31, 2024August 30, 2024
    Comment
  • An optimal statistical system designed and implemented which contributes to the monitoring and control of processes of the PJValueThe PJ does not have an adequate statistical systeA new statistical system is part of the Judiciary Statistical system contribute to the monitoring an
    DateDecember 19, 2018January 31, 2024December 29, 2023
    Comment
  • Number of ALEGRAs with the new management model implementedValue0.000.00100.00
    DateDecember 19, 2018January 31, 2024July 31, 2024
    Comment
  • Number of people who have completed courses through AMAG's e-learning platform per yearValue9600.007016.0016000.00
    DateFebruary 1, 2019January 31, 2024June 30, 2024
    Comment
  • Creation of a portal where all the judgements are published and indexed in an easily searchable mannerValueCurrently only judgements of the Supreme Court andThe PJ currently has this service, but it needs toAll judgements are published and indexed in a port
    DateDecember 19, 2018January 31, 2024June 28, 2024
    Comment
  • Indicators for monitoring performance of the TC designed and implementedValueThe TC does not have proper instruments for perforThe new administrative system will include functioA dashboard designed for performance monitoring
    DateDecember 19, 2018January 31, 2024March 31, 2022
    Comment
  • Number of requests received at the ALEGRAsValue263772.0062137.00395848.00
    DateDecember 20, 2018January 31, 2024June 30, 2024
    Comment
  • Gender gap analyses inform policy decisions that aim to enhance women's experience in courtsValueCurrently the PJ does not have enough information ToRs are finalized and the procurement of the consRegular conduct of gender gap analyses informs pol
    DateDecember 19, 2018January 31, 2024June 30, 2024
    Comment
  • Standards and processes for periodic evaluation of judges published and implementedValueThe JNJ has not been formally established.The JNJ has been formed and has published the procStandards and processes for periodic evaluation of
    DateDecember 19, 2018January 31, 2024December 31, 2022
    Comment
  • Percentage of conciliations concluded at the ALEGRAsValue20.0083.7050.00
    DateDecember 19, 2018January 31, 2024June 30, 2024
    Comment
  • Number of cases resolved through mobile Justice delivery mechanism per yearValue20788.0028621.0026531.00
    DateMay 18, 2018January 31, 2024June 30, 2024
    Comment
  • Time elapsed between the receipt of the case from PJ and the issuance of the final decision at TCValue761.00321.00404.00
    DateDecember 19, 2018January 31, 2024June 30, 2024
    Comment