Djibouti Integrated Slum Upgrading Project

Abstract*

The development objective of the Integrated Slum Upgrading Project for Djibouti is to: (i) improve the living conditions for slum dwellers in selected urban areas, and (ii) strengthen the capacity of public institutions in charge of implementing the zero-slum program (ZSP). The project comprises of three components. The first component, elaboration of the ZSP strategic framework and investment plan objective is to provide the government with requisite...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed revised development objective is to (i) improve the living conditions of host communities and refugees in selected areas, and (ii) enhance the social and economic integration of host communities and refugees.

Key Details

Project Details

  • P162901

  • Active

  • Alexandra Le Courtois , Djeina Kalidi

  • Republic of Djibouti

  • Djibouti

  • August 31, 2018

  • (as of board presentation)

    November 9, 2018

  • March 11, 2019

  • US$ 20.00 million

  • A

  • June 26, 2024

  • December 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 15.00
Borrower/Recipient 5.00
IDA Grant 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 25.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 22, 2021 IDA-63380 Loan Disb 87,215.44
Apr 27, 2021 IDA-63380 Loan Disb 114,388.41
May 26, 2021 IDA-63380 Loan Disb 107,668.61
Jun 21, 2021 IDA-63380 Loan Disb 814,926.56
Mar 31, 2021 IDA-63380 Loan Disb 125,750.89
Mar 19, 2021 IDA-63380 Loan Disb 185,073.45
Mar 18, 2022 IDA-63380 Loan Disb 827,970.56
Aug 17, 2021 IDA-63380 Loan Disb 322,869.97
Nov 9, 2021 IDA-63380 Loan Disb 209,136.48
Sep 29, 2021 IDA-63380 Int Charges 3,394.32
Sep 29, 2021 IDA-63380 Int Charges 3,394.32
Sep 14, 2020 IDA-D3900 Loan Disb 351,602.88
Oct 20, 2020 IDA-D3900 Loan Disb 788,136.80
Apr 21, 2023 IDA-63380 Loan Disb 651,685.60
Nov 16, 2022 IDA-63380 Loan Disb 776,649.70
Sep 15, 2022 IDA-63380 Int Charges 200.17
Sep 15, 2022 IDA-63380 Int Charges 200.17
Dec 16, 2022 IDA-63380 Loan Disb 800,926.40
Sep 14, 2023 IDA-63380 Loan Disb 875,136.10
Jun 28, 2023 IDA-63380 Loan Disb 599,080.20
Aug 21, 2023 IDA-63380 Loan Disb 567,337.00
Mar 15, 2023 IDA-63380 Int Charges 436.55
Mar 15, 2023 IDA-63380 Int Charges 436.55
Mar 15, 2023 IDA-63380 Int Charges 25,617.57
Mar 15, 2023 IDA-63380 Int Charges 25,617.57
Feb 24, 2023 IDA-63380 Loan Disb 835,382.90
Oct 1, 2021 IDA-63380 Loan Disb 25,675.66
Sep 21, 2021 IDA-63380 Loan Disb 481,630.10
Oct 1, 2021 IDA-63380 Loan Disb 109,531.76
Oct 1, 2021 IDA-63380 Loan Disb 185,861.84
Mar 21, 2022 IDA-63380 Int Charges 157.34
Mar 21, 2022 IDA-63380 Int Charges 157.34
Mar 21, 2022 IDA-63380 Int Charges 10,473.46
Mar 21, 2022 IDA-63380 Int Charges 10,473.46
May 13, 2022 IDA-63380 Loan Disb 367,991.38
Jun 21, 2022 IDA-63380 Loan Disb 817,494.94
May 24, 2022 IDA-63380 Loan Disb 388,524.28
Sep 29, 2022 IDA-63380 Int Charges 16,576.27
Sep 29, 2022 IDA-63380 Int Charges 16,576.27
Jun 7, 2021 IDA-D7590 Loan Disb 1,500,000.00
Jul 5, 2024 IDA-D7590 Loan Disb 299,909.30
Jan 26, 2024 IDA-63380 Loan Disb 900,491.70
Apr 9, 2024 IDA-63380 Int Charges 44,819.82
Apr 9, 2024 IDA-63380 Int Charges 44,819.82
Apr 26, 2024 IDA-63380 Loan Disb 756,180.10
Jul 2, 2024 IDA-63380 Loan Disb 207,565.53
Mar 15, 2024 IDA-63380 Int Charges 835.65
Mar 15, 2024 IDA-63380 Int Charges 835.65
Jun 2, 2023 IDA-63380 Loan Disb 660,219.75
Oct 23, 2023 IDA-63380 Int Charges 35,727.21
Oct 23, 2023 IDA-63380 Int Charges 35,727.21
Oct 23, 2023 IDA-63380 Int Charges 34.17
Oct 23, 2023 IDA-63380 Int Charges 34.17
Dec 18, 2023 IDA-63380 Loan Disb 722,938.10
Mar 11, 2019 IDA-D3900 Loan Disb 812,694.75
Jun 30, 2020 IDA-D3900 Loan Disb 406,694.40
Jan 30, 2020 IDA-D3900 Loan Disb 190,806.58
Mar 26, 2020 IDA-D3900 Loan Disb 269,092.75
Mar 26, 2020 IDA-D3900 Loan Disb 328,651.62
Nov 12, 2019 IDA-D3900 Loan Disb 419,186.56
Dec 12, 2019 IDA-D3900 Loan Disb 334,994.00
Aug 20, 2019 IDA-D3900 Loan Disb 665,006.00
Oct 23, 2019 IDA-D3900 Loan Disb 10,061.00
Nov 30, 2020 IDA-D3900 Loan Disb 407,461.30
Jan 4, 2021 IDA-D3900 Loan Disb 14,410.84
Mar 10, 2021 IDA-D3900 Loan Disb 83.86
Aug 18, 2020 IDA-D3900 Loan Disb 334,994.00
Aug 18, 2020 IDA-D3900 Loan Disb -334,994.00
Jun 22, 2021 IDA-63380 Loan Disb 81,948.92
Oct 4, 2022 IDA-63380 Loan Disb 608,952.30
Jan 11, 2022 IDA-63380 Loan Disb 366,666.62
Jun 12, 2023 IDA-D7590 Loan Disb 234,564.38
Dec 18, 2020 IDA-68160 Loan Commitment 5,000,000.00
Dec 18, 2020 IDA-D7590 Loan Commitment 25,000,000.00
Nov 9, 2018 IDA-D3900 Loan Commitment 5,000,000.00
Nov 9, 2018 IDA-63380 Loan Commitment 15,000,000.00
Nov 29, 2022 IDA-D7590 Loan Disb 318,568.22
May 24, 2022 IDA-D7590 Loan Disb 1,434,583.10
Nov 9, 2021 IDA-D7590 Loan Disb 857,627.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2024-12-23
Procurement Moderately Satisfactory 2024-12-23
Project Management Satisfactory 2024-12-23
Overall Safeguards Rating Moderately Satisfactory 2024-12-23
Financial Management Moderately Satisfactory 2024-12-23
Monitoring and Evaluation Moderately Satisfactory 2024-12-23
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-12-23

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People targeted with improved services and socio-economic activitiesValue0.004036.00114000.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Additional land certificates delivered nation-wideValue1700.005134.0010000.00
    DateSeptember 2, 2019May 15, 2024December 31, 2025
    Comment
  • People targeted with improved services and socio-economic activities- FemaleValue0.001614.0057000.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Land certificates delivered where one of the owners is femaleValue0.001555.003000.00
    DateSeptember 1, 2020February 12, 2024December 31, 2025
    Comment
  • Refugees targeted with improved services and socio economic activitiesValue0.00159.0024000.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Land certificates delivered in selected urban slumsValue0.00968.005000.00
    DateDecember 31, 2019May 15, 2024December 31, 2025
    Comment
  • Preparation of a roadmap to implement the 2017 National Refugee Law validated by the project steering committeeValueNoYesYes
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Women members of SEDF sub-projects selection committeeValue0.0040.0033.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Assessment of socio- economic inclusion and social cohesion of refugees settled in all target areas (slum areas and refugee villages) doneValueNoNoYes
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Beneficiaries that feel project investments reflected their needsValue0.000.0080.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Refugee beneficiaries that feel project investments reflected their needsValue0.000.0080.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Female beneficiaries that feel project investments reflected their needsValue0.000.0080.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Business Plan for the development of the “Farah Had” prevention and resettlement zoneValueNoNoYes
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Beneficiaries of microcredit for construction material in relocation zone for PAPsValue0.00402.001200.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Beneficiaries of microcredit for construction material in urban slums and refugee villagesValue0.000.003000.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Refugee beneficiaries of microcredit for construction material in urban slums and refugee villagesValue0.000.00450.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Feasibility study on the Housing Material Microcredit Instrument and operational manual deliveredValue0.000.001.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Support to income generating activities led by host community members and refugeesValue0.000.00500.00
    DateNovember 16, 2020October 31, 2023December 31, 2025
    Comment
  • Support to income generating activities led by women from the host community and by women refugeesValue0.000.000.00
    Date
    Comment
  • Completion certificates for vocational training deliveredValue0.000.001000.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Completion certificates for vocational training delivered to womenValue0.000.00400.00
    DateOctober 31, 2019October 31, 2023December 31, 2026
    Comment
  • Completion certificates for vocational training delivered to refugeesValue0.000.00200.00
    DateSeptember 30, 2019October 31, 2023December 31, 2026
    Comment
  • People protected from floodsValue0.0011275.0029000.00
    DateSeptember 26, 2019May 15, 2024December 31, 2025
    Comment
  • Refugees protected from floodsValue0.0063.00980.00
    DateOctober 28, 2020May 15, 2024December 31, 2025
    Comment
  • Households that improved climate resilience of housingValue0.00507.001000.00
    DateSeptember 25, 2019May 15, 2024December 31, 2025
    Comment
  • Roads constructedValue0.001.2023.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Number of affected households that benefitted from housing repairsValue0.00440.00300.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Slum restructuring studies completedValue0.008.005.00
    DateAugust 29, 2019October 31, 2023December 31, 2025
    Comment
  • Urban development plan for Balbala NorthValue0.001.001.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • Number of COVID-19 sanitation campaigns led in the 13 slumsValue0.0033.008.00
    DateSeptember 1, 2020October 31, 2022December 31, 2025
    Comment
  • People provided with access to improved water sourcesValue0.00252.0017000.00
    DateSeptember 2, 2019May 15, 2024December 31, 2025
    Comment
  • Restructuring study for two refugee villages (Ali-Addeh et Holl-Holl)Value0.002.001.00
    DateSeptember 1, 2020March 21, 2024December 31, 2025
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.008500.00
    DateSeptember 1, 2018September 1, 2023
    Comment
  • 5-year operation plan for slum prevention completedValue0.001.001.00
    DateAugust 29, 2019October 31, 2022December 31, 2025
    Comment
  • Refugees provided with access to improved water sourcesValue0.000.005000.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Integrated Land and Cadastral Information System established and accessible to selected stakeholdersValueNoNoYes
    DateSeptember 2, 2019October 31, 2023December 31, 2025
    Comment
  • Time to process a land regularisation requestValue8.008.002.00
    DateSeptember 2, 2019October 31, 2023December 31, 2025
    Comment
  • National and local civil servants, and civil society members that were trained to foster the implementation of the 2017 Refugee LawValue0.000.00100.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Sectoral action plans prepared for the operationalization of the NRLValue0.005.004.00
    DateSeptember 1, 2020October 31, 2023December 31, 2025
    Comment
  • Short term employment generated under the project investments (person days)Value0.0087580.00150000.00
    DateSeptember 2, 2019May 15, 2024December 31, 2025
    Comment
  • Recommendations resulting from the sectoral action plans that have been implementedValue0.000.006.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Short term employment generated under the project investments executed by womenValue0.0026274.0030000.00
    DateSeptember 1, 2020May 15, 2024December 31, 2025
    Comment
  • Property access certificates delivered to refugeesValue0.000.002000.00
    DateOctober 21, 2020May 15, 2024December 31, 2025
    Comment
  • Short term employment generated under the project investments executed by RefugeeValue0.000.000.00
    Date
    Comment
  • Complaints received via institutionalized GRM channels that are adressed and responded to within a timeline that has been specifiedand publicly communicated by the projectValue0.0066.00100.00
    DateSeptember 2, 2019May 15, 2024December 31, 2025
    Comment
  • SEDF-funded sub-projects implementedValue0.0021.00250.00
    DateSeptember 2, 2019May 15, 2024December 31, 2025
    Comment
  • SEDF-funded sub-projects implemented by women-led CSOsValue0.000.000.00
    Date
    Comment
  • SEDF-funded sub-projects implemented by refugee-led CSOValue0.000.0060.00
    DateOctober 30, 2019October 31, 2023December 31, 2026
    Comment