Financier | Commitments |
---|---|
Strategic Climate Fund Credit | 6.40 |
Strategic Climate Fund Grant | 5.80 |
P163023
Active
Mizushi Satoh
Ministry of Economy and Finance
May 26, 2017
(as of board presentation)
January 4, 2019
May 8, 2019
US$ 12.20 million
Ministry of Environment and Natural Resources
2019
US$ 12.20 million
B
December 21, 2023
August 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Strategic Climate Fund Credit | 6.40 |
Strategic Climate Fund Grant | 5.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 12.20 |
Total Project Cost** | 12.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 4, 2019 | TF-A8845 | Loan Commitment | 6,400,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-12-12 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-12 |
Procurement | Satisfactory | 2024-12-12 |
Financial Management | Moderately Satisfactory | 2024-12-12 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-12 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-12 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area under sustainable landscape management practices | Value | 0.00 | 0.00 | 380500.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Indigenous communities with usage or ownership rights | Value | 0.00 | 0.00 | 23.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Land users adopting sustainable land management practices as a result of the project (direct beneficiaries disaggregated by gender) | Value | 0.00 | 0.00 | 2300.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Share of target beneficiaries satisfied with their participation in forest and land-use decisions that affect them (disaggregated by gender) | Value | 0.00 | 0.00 | 75.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Index of forest entrepreneurship | Value | 0.00 | 0.00 | 60.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Forest area under monitoring and surveillance | Value | 0.00 | 0.00 | 380500.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Number of incentive projects under implementation | Value | 0.00 | 0.00 | 50.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Life plans approved by comunity | Value | 0.00 | 33.00 | 30.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Share of registered questions and grievances, related to project benefit delivery, that are addressed | Value | 0.00 | 0.00 | 85.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Number of Community Monitoring and Oversight Committees established and operating | Value | 0.00 | 0.00 | 50.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Net greenhouse gas emissions | Value | 0.00 | 0.00 | 3108737.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |
Subprojects financed under the incentive fund, submitted by associations which have at least 30% women sitting on their boards. | Value | 0.00 | 0.00 | 30.00 |
Date | November 16, 2018 | September 30, 2023 | August 31, 2024 | |
Comment |