Financier | Commitments |
---|---|
IDA Credit | 82.23 |
IDA Grant | 40.16 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 4.60 |
P163033
Closed
Clemencia Torres De Mastle , Pierre Lorillou, Xavier Daudey
N/A
Western and Central Africa
October 16, 2017
(as of board presentation)
November 17, 2017
N/A
US$ 126.98 million
N/A
2018
US$ 126.98 million
A
August 15, 2024
March 15, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 82.23 |
IDA Grant | 40.16 |
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) | 4.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 122.38 |
IBRD + IDA Commitment | 122.38 |
Lending Instrument | |
---|---|
Grant Amount | 4.60 |
Total Project Cost** | 126.98 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 0.00 | 5.20 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Annual electricity supply from CLSG imports at utility level (disaggregated: Liberia Electricity Corporation, Sierra Leone NationalPower Authority, Guinea - Electricite de Guinee (Component 1) | Value | 0.00 | 0.00 | 300.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Difference between the annual weighted cost of imported electricity through the CLSG and the annual weighted cost of others sourcesof supply for utilities in Liberia and Sierra Leone (Component 1) | Value | 0.42 | 0.42 | 0.30 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised to take into account impact of EVD, lessons learned and end target date according to proposed new closing date of theproject |
Cote d' Ivoire export capability to CLSG countries (Component 1) | Value | 0.00 | 0.00 | 200.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment |
WAPP Priority projects brought to the point where investment-grade feasibility studies and associated documentation have been completed | Value | 6.00 | 6.00 | 9.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment |
Ratio of annual total hours of synchronization of WAPP Zone A against total hours in a year within TCN-CEB-GRIDCO interconnection (Component 2) | Value | 0.00 | 0.00 | 50.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 52.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Transmission line constructed from Bumbuna-Yiben | Value | 0.00 | 0.00 | 73.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Bikongor to Bumbuna | Value | 0.00 | 0.00 | 146.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Kenema-Bikongor | Value | 0.00 | 0.00 | 96.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Mano-Kenema | Value | 0.00 | 0.00 | 115.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Monrovia-Mano | Value | 0.00 | 0.00 | 107.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Buchanan-Monrovia | Value | 0.00 | 0.00 | 112.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Yekepa-Buchanan | Value | 0.00 | 0.00 | 229.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Yekepa-Nzerekore | Value | 0.00 | 0.00 | 49.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Man-Yekepa | Value | 0.00 | 0.00 | 152.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Linsan | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | October 31, 2019 | |
Comment |
Kamakwie | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Yiben | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Bumbuna | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Bokongor | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Kenema | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Mano | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Monrovia | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Buchanan | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Nzerekore | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Yekepa | Value | 0.00 | 0.00 | 1.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Number of supply alternative analyses completed at Feasibility Stage | Value | 0.00 | 1.00 | 3.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Replace former qualitative indicator with hereby proposed quantitative indicator. This indicator also clarifies what is a supplyalternative analysis (feasibility) to include quantitative monitoring of the indicator, studies on the St. Paul River in Liberiaand end target date according to proposed new closing date. |
Number of grievances received and satisfactorily resolved | Value | 0.00 | 0.00 | 100.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 1349.00 |
Date | February 4, 2013 | May 22, 2017 | October 31, 2019 | |
Comment |
225 kV Substations constructed (disaggregated by location) (Component 1) | Value | 0.00 | 0.00 | 11.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Regional Transmission Company fulfillment of obligations on time and to the quality required. (Component 1) | Value | none | yes | yes |
Date | May 4, 2012 | December 14, 2015 | December 15, 2020 | |
Comment |
Supply alternative analysis completed (Project 2) | Value | No | No | Yes |
Date | February 4, 2013 | October 26, 2016 | June 30, 2016 | |
Comment |
Key experts recruited to support WAPP Secretariat | Value | 0.00 | 1.00 | 5.00 |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment |
Synchronization equipment installed | Value | No | No | Yes |
Date | May 4, 2012 | May 22, 2017 | December 15, 2020 | |
Comment |
Transmission line from Kamakwie to Linsan | Value | 0.00 | 0.00 | 160.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |
Transmission line constructed from Yiben-Kamakwie | Value | 0.00 | 0.00 | 60.00 |
Date | February 4, 2013 | May 22, 2017 | December 15, 2020 | |
Comment | Revised end target date according to proposed new closing date of the project |