WAPP-APL4 (Phase 1): Côte d'Ivoire Liberia Sierra Leone and Guinea Regional Interconnector- Additional Financing

Development Objective

The revised PDOs for the WAPP CLSG Power Interconnection are to: (a) reduce the cost of electricity supply at the utility level for Liberia and Sierra Leone and (b) increase the amount of electricity traded among all the participating countries. The Development Objective of the WAPP TA is to increase the technical integration of the WAPP network.

Key Details

Project Details

  • P163033

  • Closed

  • Clemencia Torres De Mastle , Pierre Lorillou, Xavier Daudey

  • N/A

  • Western and Central Africa

  • October 16, 2017

  • (as of board presentation)

    November 17, 2017

  • N/A

  • US$ 126.98 million

  • A

  • August 15, 2024

  • March 15, 2023

  • Yes

  • BANK APPROVED

  • P113266

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 82.23
IDA Grant 40.16
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 4.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 122.38
IBRD + IDA Commitment 122.38
Lending Instrument
Grant Amount 4.60
Total Project Cost** 126.98

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.000.005.20
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Annual electricity supply from CLSG imports at utility level (disaggregated: Liberia Electricity Corporation, Sierra Leone NationalPower Authority, Guinea - Electricite de Guinee (Component 1)Value0.000.00300.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Difference between the annual weighted cost of imported electricity through the CLSG and the annual weighted cost of others sourcesof supply for utilities in Liberia and Sierra Leone (Component 1)Value0.420.420.30
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised to take into account impact of EVD, lessons learned and end target date according to proposed new closing date of theproject
  • Cote d' Ivoire export capability to CLSG countries (Component 1)Value0.000.00200.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    Comment
  • WAPP Priority projects brought to the point where investment-grade feasibility studies and associated documentation have been completedValue6.006.009.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    Comment
  • Ratio of annual total hours of synchronization of WAPP Zone A against total hours in a year within TCN-CEB-GRIDCO interconnection (Component 2)Value0.000.0050.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    Comment
  • Female beneficiariesValue0.000.0052.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Transmission line constructed from Bumbuna-YibenValue0.000.0073.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Bikongor to BumbunaValue0.000.00146.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Kenema-BikongorValue0.000.0096.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Mano-KenemaValue0.000.00115.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Monrovia-ManoValue0.000.00107.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Buchanan-MonroviaValue0.000.00112.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Yekepa-BuchananValue0.000.00229.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Yekepa-NzerekoreValue0.000.0049.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Man-YekepaValue0.000.00152.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission lines rehabilitated under the projectValue0.000.000.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • LinsanValue0.000.001.00
    DateMay 4, 2012May 22, 2017October 31, 2019
    Comment
  • KamakwieValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • YibenValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • BumbunaValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • BokongorValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • KenemaValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • ManoValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • MonroviaValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • BuchananValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • NzerekoreValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • YekepaValue0.000.001.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Number of supply alternative analyses completed at Feasibility StageValue0.001.003.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentReplace former qualitative indicator with hereby proposed quantitative indicator. This indicator also clarifies what is a supplyalternative analysis (feasibility) to include quantitative monitoring of the indicator, studies on the St. Paul River in Liberiaand end target date according to proposed new closing date.
  • Number of grievances received and satisfactorily resolvedValue0.000.00100.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    Comment
  • Transmission lines constructed or rehabilitated under the projectValue0.000.001349.00
    DateFebruary 4, 2013May 22, 2017October 31, 2019
    Comment
  • 225 kV Substations constructed (disaggregated by location) (Component 1)Value0.000.0011.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Regional Transmission Company fulfillment of obligations on time and to the quality required. (Component 1)Valuenoneyesyes
    DateMay 4, 2012December 14, 2015December 15, 2020
    Comment
  • Supply alternative analysis completed (Project 2)ValueNoNoYes
    DateFebruary 4, 2013October 26, 2016June 30, 2016
    Comment
  • Key experts recruited to support WAPP SecretariatValue0.001.005.00
    DateMay 4, 2012May 22, 2017December 15, 2020
    Comment
  • Synchronization equipment installedValueNoNoYes
    DateMay 4, 2012May 22, 2017December 15, 2020
    Comment
  • Transmission line from Kamakwie to LinsanValue0.000.00160.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project
  • Transmission line constructed from Yiben-KamakwieValue0.000.0060.00
    DateFebruary 4, 2013May 22, 2017December 15, 2020
    CommentRevised end target date according to proposed new closing date of the project