WAPP-APL4 (Phase 1): Côte d'Ivoire Liberia Sierra Leone and Guinea Regional Interconnector- Additional Financing

Development Objective

The revised PDOs for the WAPP CLSG Power Interconnection are to: (a) reduce the cost of electricity supply at the utility level for Liberia and Sierra Leone and (b) increase the amount of electricity traded among all the participating countries. The Development Objective of the WAPP TA is to increase the technical integration of the WAPP network.

Key Details

Project Details

  • P163033

  • Closed

  • Clemencia Torres De Mastle , Pierre Lorillou, Xavier Daudey

  • N/A

  • Western and Central Africa

  • October 16, 2017

  • (as of board presentation)

    November 17, 2017

  • N/A

  • US$ 126.98 million

  • A

  • August 15, 2024

  • March 15, 2023

  • Yes

  • BANK APPROVED

  • P113266

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 82.23
IDA Grant 40.16
GERMANY: KREDITANSTALT FUR WIEDERAUFBAU (KFW) 4.60

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 122.38
IBRD + IDA Commitment 122.38
Lending Instrument
Grant Amount 4.60
Total Project Cost** 126.98

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.