P163138
Closed
Ladisy Chengula , Min Zhao
PEOPLE'S REPUBLIC OF CHINA
June 22, 2018
(as of board presentation)
June 22, 2018
December 14, 2018
US$ 400.00 million
Guangxi Provincial Rural Revitalization Bureau,Guangxi Department of Agriculture and Rural Affairs
2018
US$ 400.00 million
N/A
June 26, 2024
December 31, 2021
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 1, 2019 | IBRD-88900 | Int Charges | 260,145.00 |
Nov 1, 2019 | IBRD-88900 | Loan Disb | 1,111,432.80 |
Nov 1, 2019 | IBRD-88900 | Loan Disb | 391,011.30 |
Nov 1, 2019 | IBRD-88900 | Int Charges | 391,011.30 |
Nov 1, 2019 | IBRD-88900 | Int Charges | 1,111,432.80 |
Nov 1, 2019 | IBRD-88900 | Int Charges | 498,521.40 |
Dec 27, 2019 | IBRD-88900 | Loan Disb | 79,603,000.00 |
Dec 14, 2018 | IBRD-88900 | Fee Charges | 1,000,000.00 |
May 1, 2019 | IBRD-88900 | Int Charges | -437,410.97 |
May 1, 2019 | IBRD-88900 | Loan Disb | -437,410.97 |
Dec 14, 2018 | IBRD-88900 | Loan Disb | 1,000,000.00 |
Mar 14, 2019 | IBRD-88900 | Loan Disb | 50,000,000.00 |
May 1, 2019 | IBRD-88900 | Loan Disb | 437,410.97 |
May 1, 2019 | IBRD-88900 | Int Charges | 437,410.97 |
May 1, 2019 | IBRD-88900 | Loan Disb | 260,145.00 |
May 1, 2019 | IBRD-88900 | Int Charges | 260,145.00 |
Jun 14, 2019 | IBRD-88900 | Loan Disb | 50,000,000.00 |
May 1, 2019 | IBRD-88900 | Loan Disb | -260,145.00 |
May 1, 2019 | IBRD-88900 | Int Charges | -260,145.00 |
Jun 22, 2018 | IBRD-88900 | Loan Commitment | 400,000,000.00 |
Nov 1, 2023 | IBRD-88900 | Int Charges | 171,995.88 |
Nov 1, 2023 | IBRD-88900 | Int Charges | 12,787,698.00 |
May 1, 2024 | IBRD-88900 | Int Charges | 76,837.24 |
May 1, 2024 | IBRD-88900 | Int Charges | 13,533,502.00 |
May 1, 2023 | IBRD-88900 | Int Charges | 339,990.94 |
May 1, 2023 | IBRD-88900 | Int Charges | 10,600,769.00 |
Nov 1, 2022 | IBRD-88900 | Int Charges | 6,524,148.50 |
May 1, 2022 | IBRD-88900 | Int Charges | 2,247,172.00 |
May 1, 2022 | IBRD-88900 | Int Charges | 9,335.30 |
May 1, 2022 | IBRD-88900 | Int Charges | 33,824.95 |
May 1, 2022 | IBRD-88900 | Int Charges | 1,160.75 |
Sep 7, 2021 | IBRD-88900 | Loan Disb | 24,781,000.00 |
Nov 1, 2021 | IBRD-88900 | Int Charges | 53,707.38 |
Nov 1, 2021 | IBRD-88900 | Int Charges | 2,039,199.20 |
Nov 8, 2021 | IBRD-88900 | Loan Disb | 24,210,000.00 |
May 1, 2021 | IBRD-88900 | Int Charges | 115,343.79 |
May 1, 2021 | IBRD-88900 | Int Charges | 1,758,603.10 |
Jun 16, 2021 | IBRD-88900 | Loan Disb | 4,128,000.00 |
Nov 1, 2020 | IBRD-88900 | Int Charges | 272,979.84 |
Nov 1, 2020 | IBRD-88900 | Int Charges | 1,579,011.60 |
Nov 5, 2020 | IBRD-88900 | Loan Disb | 69,887,000.00 |
Dec 29, 2020 | IBRD-88900 | Loan Disb | 42,191,000.00 |
Jan 27, 2021 | IBRD-88900 | Loan Disb | 52,000,000.00 |
May 1, 2020 | IBRD-88900 | Int Charges | 2,248,966.20 |
May 1, 2020 | IBRD-88900 | Int Charges | 300,793.25 |
May 1, 2019 | IBRD-88900 | Loan Disb | 437,410.97 |
May 1, 2019 | IBRD-88900 | Int Charges | 437,410.97 |
May 1, 2019 | IBRD-88900 | Loan Disb | 260,145.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2021-12-29 |
Monitoring and Evaluation | Satisfactory | 2021-12-29 |
Overall Implementation Progress (IP) | Satisfactory | 2021-12-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-31-2022 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-28-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | High | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Production income of registered poor households in targeted counties (in RMB) | Value | 11041.00 | 15000.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Percentage of registered households with access to selected infrastructure assets according to 8+1 poverty criteria in targeted counties (1) Rural roads | Value | 96.00 | 98.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
(2) Safe drinking water | Value | 78.60 | 85.40 | 0.00 |
Date | ||||
Comment |
Integrated Consolidated Fund Program-based Performance Monitoring Report | Value | 0.00 | 3.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of enterprises accredited as Poverty Reduction Leading Enterprises | Value | 0.00 | 104.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
Number of Registered Poor Persons with New Piped Drinking Water Connections | Value | 95400.00 | 210000.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Number of Targeted Counties with Annual Program-based Budgeting Plans and Annual Program-based Expenditure Reports | Value | 0.00 | 28.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Number of targeted counties with newly accredited poverty countries with poverty reduction leading enterprises | Value | 0.00 | 28.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
Customers satisfied with the drinking water supply services | Value | 0.00 | 70.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Poverty data platform for monitoring and evaluation of poverty reduction | Value | 0.00 | 1.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
Number of Pro-poor Farmer Professional Cooperatives meeting the Operational Standards | Value | 0.00 | 515.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
Number of Targeted Counties with an IT-based infrastructure project management system | Value | 0.00 | 28.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Number of additional datasets integrated from key institutional entities into Big Data platform | Value | 0.00 | 4.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Farmers reached with agricultural assets or services | Value | 0.00 | 100000.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Paved road connectivity rate in large (=> 20 hhs) natural villages | Value | 81.30 | 85.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Farmers reached with agricultural assets or services - Female | Value | 0.00 | 30386.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Pro-poor Farmer Professional Cooperatives membership (% registered poor) | Value | 0.00 | 30.00 | 0.00 |
Date | December 31, 2017 | December 31, 2020 | ||
Comment |
Pro-poor Farmer Professional Cooperatives membership (% female) | Value | 0.00 | 30.00 | 0.00 |
Date | ||||
Comment |
Value of annual purchases of agricultural products by Poverty Reduction Leading Enterprises from farmers and farmer cooperatives (in RMB) | Value | 0.00 | 2352000000.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
Number of farmers completing New Professional Farmer Development training program | Value | 4291.00 | 41745.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |
-% of female | Value | 25.00 | 30.00 | 0.00 |
Date | ||||
Comment |
% of registered poor | Value | 10.00 | 18.00 | 0.00 |
Date | ||||
Comment |
Customers satisfied with the services provided by the New Professional Farmer Development training program | Value | 0.00 | 95.00 | 0.00 |
Date | December 31, 2017 | December 31, 2021 | ||
Comment |