Financier | Commitments |
---|---|
Australia-Pacific Islands Partnership Trust Fund | 0.49 |
Pacific Regional Infrastructure Facility Trust Fund | 0.38 |
P163153
Closed
Artessa Saldivar-Sali
Republic of Kiribati
March 5, 2017
(as of board presentation)
October 4, 2017
N/A
US$ 0.87 million
Office of Te Beretitenti
2018
US$ 0.87 million
B
October 1, 2020
December 31, 2018
BANK APPROVED
Financier | Commitments |
---|---|
Australia-Pacific Islands Partnership Trust Fund | 0.49 |
Pacific Regional Infrastructure Facility Trust Fund | 0.38 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.87 |
Total Project Cost** | 0.87 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to improved water sources | Value | 5000.00 | 0.00 | 11000.00 |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |
People provided with access to improved water sources - Female (RMS requirement) | Value | 2500.00 | 0.00 | 6000.00 |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |
People provided with access to improved water sources - rural | Value | 3600.00 | 0.00 | 8400.00 |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |
People provided with access to improved water sources - urban | Value | 1400.00 | 0.00 | 2600.00 |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Community-led resilience sub-projects completed | Value | 35.00 | 0.00 | 80.00 |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |
The OB extension to house government services for disaster risk management and climate change adaptation is built and used. | Value | No | Yes | |
Date | July 31, 2017 | December 31, 2018 | ||
Comment |