Financier | Commitments |
---|---|
IDA Grant from CRW | 20.00 |
P163194
Closed
Jean-Martin Brault , Carl Christian Gyde Jacobsen
N/A
Haiti
May 8, 2017
(as of board presentation)
June 14, 2017
N/A
US$ 20.00 million
N/A
2017
US$ 20.00 million
B
November 14, 2022
March 31, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant from CRW | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 20.00 |
IBRD + IDA Commitment | 20.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 20.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in place | Value | 0.00 | 1.00 | 5.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Required functions deconcentrated to targeted OREPA | Value | 0.00 | 0.00 | 6.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Piped water systems managed sustainably by a professional operator (OP) under the Project | Value | 0.00 | 2.00 | 25.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 20 under the Parent Grant and 5 under the AF |
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 15000.00 | 235000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 150,000 people under the Parent Grant and 85,000 under the AF |
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 0.00 | 30000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Priority cholera communes targeted under the Project | Value | 0.00 | 0.00 | 6.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 45000.00 | 685000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 300,000 beneficiaries under the Parent Grant and 385,000 under the AF |
People in rural areas provided with access to Improved Water Sources - female | Value | 0.00 | 0.00 | 117500.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People provided with access to ?improved sanitation facilities?- rural | Value | 0.00 | 0.00 | 30000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | September 30, 2015 | September 30, 2021 | ||
Comment |
Project beneficiaries in localities on the border with the DR including bi-national markets | Value | 0.00 | 0.00 | 75000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People in rural areas provided with access to "improved sanitation facilities" - female | Value | 0.00 | 0.00 | 15000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Project beneficiaries of small repairs and rehabilitation works following the passage of Hurricane Matthew | Value | 0.00 | 0.00 | 385000.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |
Piped water systems managed sustainably by a professional operator (OP) in zones affected by Hurricane Matthew | Value | 0.00 | 0.00 | 5.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |
Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane Matthew | Value | 0.00 | 0.00 | 85000.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Departments covered by WSS baseline information | Value | 0.00 | 9.00 | 10.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
DINEPA conducts an annual joint Government/ partners sector review | Value | No | No | Yes |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
At least one OREPA uses the baseline developed under the Project to prioritize interventions and inform DINEPA?s Program Budget | Value | No | No | Yes |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
At least one OREPA has installed an accounting system which facilitates the consolidation of financial information at the central level | Value | No | No | Yes |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
DINEPA supports the design of a Regional joint monitoring mechanism for pandemics is established, as evidenced by triannual meetings with the MSPP and biannual meetings with DR representatives | Value | No | No | Yes |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People benefitting from consolidation work (small repairs and expansions) | Value | 0.00 | 30000.00 | 400000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 100,000 people under the Parent Grant and 300,000 under the AF |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 200.00 | 7750.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 6,750 connections under the Parent Grant and 1,000 under the AF |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 0.00 | 135.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People trained to improve hygiene behavior/sanitation practices under the proj | Value | 0.00 | 0.00 | 75000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion andsanitation themes and activities | Value | 0.00 | 0.00 | 20.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Students and teachers benefitting from improved sanitation facilities in public schools under the Project | Value | 0.00 | 0.00 | 20000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placeunder the Project | Value | 0.00 | 0.00 | 80.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment | This end target includes 60 blocks under the Parent Grant and 20 under the AF |
Female and youth beneficiaries rating safety in access to water and sanitation services as satisfactory or better | Value | 0.00 | 0.00 | 70.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Households with latrine built during project implementation and of which use is verified | Value | 0.00 | 0.00 | 1900.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
CAEPAs that include at least 20 percent female representation in project area | Value | 0.00 | 4.00 | 70.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
A fecal sludge management service chain for rural areas and small towns is defined | Value | No | No | Yes |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 0.00 | 80.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People benefitting from consolidation work - female | Value | 0.00 | 0.00 | 200000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
People trained to improve hygiene behavior/sanitation practices - female | Value | 0.00 | 0.00 | 37500.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Students and teachers benefitting from improved sanitation facilities in public schools - female | Value | 0.00 | 0.00 | 10000.00 |
Date | September 30, 2015 | March 31, 2017 | September 30, 2021 | |
Comment |
Grievances related to delivery of project benefits that are addressed-(number) | Value | 0.00 | 0.00 | 100.00 |
Date | September 30, 2015 | October 3, 2016 | September 30, 2021 | |
Comment |
People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane Matthew | Value | 0.00 | 0.00 | 300000.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |
New piped household water connections that are resulting from project interventions in zones affected by Hurricane Matthew | Value | 0.00 | 0.00 | 1000.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |
Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in placein zones affected by Hurricane Matthew | Value | 0.00 | 0.00 | 20.00 |
Date | June 14, 2017 | June 14, 2017 | September 30, 2021 | |
Comment |