Skip to Main Navigation

AF- Sustainable Management of Natural Resources and Climate Change

Development Objective

The development objective of the project is to support Uruguay's efforts to promote farmer adoption of climate smart agricultural and livestock practices, and improved natural resource management practices in project areas.

Key Details

Project Details

  • P163444

  • Closed

  • Remi Trier , Katie Freeman

  • N/A

  • Uruguay

  • September 22, 2017

  • (as of board presentation)

    November 30, 2017

  • N/A

  • US$ 42.00 million

  • B

  • May 10, 2022

  • November 16, 2021

  • Yes

  • BANK APPROVED

  • P124181

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 42.00
Borrower/Recipient 5.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 42.00
IDA Commitment N/A
IBRD + IDA Commitment 42.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 47.20

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Information Decision Support System (IDSS) functioningValueNoYesYes
    DateOctober 17, 2011April 20, 2017March 1, 2017
    CommentAchieved. Replaced by the indicator on the Number of data Products generated by the interoperability.
  • Land area where sustainable land mgt. practices were adopted as a result of projValue0.002908000.002700000.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    CommentReplaced by the corporate indicator 'Land Area under Sustainable Landscape Management practices'
  • Number of people trained in project objectivesValue0.008861.003500.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    CommentReplaced by the corporate indicator.
  • Climate Change Adaptive Capacity Index (%)Value0.000.240.30
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Number of people trained in project objectives - FemaleValue0.001240.002000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Number of people trained in project objectivesValue0.006200.008000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 4: technical staffs MGAP and outside, farmers (formal events and e-learning)
  • Number of people trained in project objectives - MaleValue0.004960.006000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Land area under sustainable landscape management practicesValue0.002908000.003600000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponents 2 and 3: Soil Management Plans & subprojects
  • Farmers adopting improved agricultural technologyValue0.004700.007000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 2
  • Farmers adopting improved agricultural technology - FemaleValue0.00940.001400.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Farmers adopting improved agricultural technology - maleValue0.003760.005600.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Data products generated by the interoperability of IDSS/SNIA and made available to usersValue0.0021.0030.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 1

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Data products developed for IDSS and made available to usersValue0.0021.0020.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    CommentIncluded in the PDO indicators
  • Number of institutions which contribute information to the IDSSValue0.0037.0023.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Technical assistance provided to producers (individuals)Value0.0034671.0032800.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Project activities widely communicated and disseminatedValue0.002859.00650.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Management support tools developed by projectValue0.0022.0021.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Number of IDSS / SNIA UsersValue0.003700.005000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 1: registered users to the SNIA or modules
  • Decisions made by the public sector based on information from the IDSSValue058
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 1. Decisions with ministerial decree
  • Climate-smart on-farm subprojects funded by projectValue0.002600.004000.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Completion ratio of climate-smart subprojects with producersValue0.0089.0090.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Activities (as actions) financed under subprojects promoting sustainable natural resources managementValue0.006757.008500.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 2
  • Cartographic updated (1:50,000) and made available to general publicValueNoNoYes
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Soil-Use Management Plans for agricultural producers with more than 100 ha under cultivation monitored by RENARE and presented in digital format compatible with RENARE's information mng. syst.Value0.0096.0096.00
    DateOctober 17, 2011September 24, 2017March 1, 2017
    Commentalready achieved
  • Regional RENARE offices establishedValue0.008.008.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Potential surface area for application of NRM models developed by projectValue0.001628278.0035000000.00
    DateOctober 17, 2011September 16, 2016March 1, 2017
    CommentIncluded in the corporate indicator at PDO level
  • Integrated M&E System developed and integratedValue0.0020487.0018000.00
    DateOctober 17, 2011April 20, 2017March 1, 2017
    Comment
  • Technical assistance provided to producer organizationsValue0.003732.003600.00
    DateOctober 17, 2011September 16, 2016March 1, 2017
    Comment
  • Climate smart on-farm subprojects with producer organizations funded by projectValue0.00114.00130.00
    DateOctober 17, 2011September 16, 2016November 16, 2021
    Comment
  • Completion ratio of climate-smart subprojects with producer organizationsValue0.0056.0090.00
    DateOctober 17, 2011September 16, 2016March 1, 2017
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.00400.003500.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 2. Collective (EAAPs) and individual subprojects200ha de EAAPs + 200ha de Agua Para Produccion3,000ha de EAAPs + 500ha de Agua Para Produccion
  • Monitoring of Soil Management Plan implementation - % of SMP audited -Value0.0010.0040.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 3. audited on the field. Cumulative indicator.
  • Grievances registered related to project benefits that are addressed (%)Value0.000.0090.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    CommentComponent 4
  • Area provided with new irrigation or drainage servicesValue0.00280.002450.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Area provided with improved irrigation or drainage servicesValue0.00120.001050.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment
  • Area of country with cartographic updated (1:40,000) - % -Value0.0035.0075.00
    DateOctober 17, 2011September 24, 2017November 16, 2021
    Comment