Financier | Commitments |
---|---|
Afghanistan Resilience Trust Fund | 44.30 |
IDA recommitted as a Grant | 41.90 |
IDA Grant | 85.80 |
P163468
Active
Janamejay Singh
N/A
May 23, 2017
(as of board presentation)
June 13, 2017
N/A
US$ 172.00 million
N/A
2017
US$ 172.00 million
B
May 1, 2024
June 30, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Afghanistan Resilience Trust Fund | 44.30 |
IDA recommitted as a Grant | 41.90 |
IDA Grant | 85.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 127.70 |
IBRD + IDA Commitment | 127.70 |
Lending Instrument | |
---|---|
Grant Amount | 44.30 |
Total Project Cost** | 172.00 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of CDCs in rural and urban areas able to plan and manage their own development projects | Value | 0.00 | 0.00 | 11750.00 |
Date | October 1, 2016 | October 31, 2021 | ||
Comment |
Direct project beneficiaries | Value | 0.00 | 0.00 | 1000000.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of communities meeting all minimum service standards | Value | 0.00 | 0.00 | 9600.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Rural CDCs able to plan and manage their own development projects | Value | 0.00 | 0.00 | 11000.00 |
Date | October 1, 2016 | October 31, 2021 | ||
Comment |
Urban CDCs able to plan and manage their own development projects | Value | 0.00 | 0.00 | 750.00 |
Date | October 1, 2016 | October 31, 2021 | ||
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 35.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Rural communities meeting all minimum service standards | Value | 0.00 | 0.00 | 9000.00 |
Date | October 1, 2016 | October 31, 2021 | ||
Comment |
Urban communities meeting all minimum service standards | Value | 0.00 | 0.00 | 600.00 |
Date | October 1, 2016 | October 31, 2021 | ||
Comment |
Number of targeted high IDP/returnee communities provided with emergency support | Value | 0.00 | 0.00 | 2200.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of rural targeted high IDP/returnee communities provided with emergency support | Value | 0.00 | 0.00 | 2000.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of urban targeted high IDP/returnee communities provided with emergency support | Value | 0.00 | 0.00 | 200.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% of sampled CDCs/communities whose CDPs include at least one women's priority activity | Value | 0.00 | 0.00 | 60.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of sampled community respondents (male/female) satisfied with CDC's performance in their mandated roles | Value | 0.00 | 0.00 | 60.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of sampled community respondents (male/female) satisfied with subproject/grant investments | Value | 0.00 | 0.00 | 60.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of districts/cities where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/Gozars | Value | 0.00 | 0.00 | 74.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of rural and urban CDCs reporting semi-annually on service standard targets | Value | 0.00 | 0.00 | 9600.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Rural areas - Number/Type of rural subprojects completed (for water points, roads, irrigation, electricity) | Value | 0.00 | 0.00 | 9000.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Rural areas - Number of people (male/female) benefitting from each type of subproject (access to water, roads, irrigation and electricity) | Value | 0 | TBD | |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of government provincial and municipalities whose abilities are strengthened in engineering, project management, FM & procurement | Value | TBD | 38 | |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Urban areas - Number/type of urban subprojects completed (drainage, streets, street lighting, parks) | Value | 0.00 | 0.00 | 600.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Urban areas - Number of urban residents (male/female) benefitting from each type of subproject (drainage, streets, street lighting,parks) | Value | 0 | TBD | |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of CDCs initiating activities to benefit marginalized and vulnerable groups such as women, IDPs/returnees (in addition to servicestandards) | Value | 0.00 | 0.00 | 35.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of evaluations and studies completed | Value | 0.00 | 0.00 | 6.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of rural CDC cross-visits that include women CDC members | Value | 0.00 | 0.00 | 20.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of CDC members in rural areas who are women | Value | 0.00 | 0.00 | 35.00 |
Date | October 27, 2016 | October 31, 2021 | ||
Comment |
% of CDC members in urban areas who are women | Value | 0.00 | 0.00 | 40.00 |
Date | October 27, 2016 | October 31, 2021 | ||
Comment |
% of urban CDC cross-visits that include women CDC members | Value | 0.00 | 0.00 | 50.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
% of grievances received which are resolved | Value | 0.00 | 0.00 | 70.00 |
Date | October 27, 2016 | October 31, 2021 | ||
Comment |
Number of cities where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/Gozars | Value | 0.00 | 0.00 | 4.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of rural districts where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/Gozars | Value | 0.00 | 0.00 | 76.00 |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of provinces whose abilities are strengthened in engineering, project management, FM and procurement | Value | TBD | 34 | |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of municipalities whose abilities are strengthened in engineering, project management, FM and procurement | Value | TBD | 4 | |
Date | July 1, 2016 | October 31, 2021 | ||
Comment |
Number of vulnerable households receiving MCCG support | Value | 0.00 | 0.00 | 115000.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of vulnerable households benefitting from social inclusion grant | Value | 0.00 | 0.00 | 20000.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of communities in rural areas receiving MCCG grants within 6 months after AF effectiveness | Value | 0.00 | 0.00 | 700.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of vulnerable female-headed households benefitting from social inclusion grant | Value | 0.00 | 0.00 | 10000.00 |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of vulnerable IDP/R households receiving MCCG Support | Value | 0.00 | Monitored | |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of vulnerable IDP/R households benefitting from social inclusion grant | Value | 0.0 | Monitored | |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |
Number of vulnerable disabled households benefitting from social inclusion grant | Value | 0.00 | Monitored | |
Date | May 31, 2017 | October 31, 2021 | ||
Comment |