Skip to Main Navigation

Khyber Pakhtunkhwa Irrigated-Agriculture Improvement Project

Abstract*

The development objective of the Khyber Pakhtunkhwa Irrigated-Agriculture Improvement Project for Pakistan is to improve the performance of irrigated agriculture for farmers in the project area. The project comprises of five components. The first component, improvement of community irrigation systems will improve the on-farm water supply in irrigated areas. The second component, introduction of modern irrigation technologies will provide support to...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the performance of irrigated agriculture for farmers in the project area.

Key Details

Project Details

  • P163474

  • Active

  • Olivier Durand , Maha Ahmed

  • The Islamic Republic of Pakistan

  • Pakistan

  • June 4, 2018

  • (as of board presentation)

    June 20, 2019

  • May 18, 2020

  • US$ 219.30 million

  • Department of Agriculture, Government of Khyber Pukhthukhwa

  • South Asia

  • 2019

  • US$ 171.00 million

  • B

  • February 8, 2024

  • December 31, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 171.00
Local Beneficiaries 36.90

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 171.00
IBRD + IDA Commitment 171.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 219.30

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 9, 2023 IDA-64560 Loan Disb 14,000,000.00
Jul 1, 2023 IDA-64560 Int Charges 447,489.03
Jul 1, 2023 IDA-64560 Int Charges 21,483.77
Jul 1, 2023 IDA-64560 Int Charges 272,931.10
Jul 1, 2023 IDA-64560 Int Charges 272,931.10
Jan 1, 2024 IDA-64560 Int Charges 344,473.20
Jan 1, 2024 IDA-64560 Int Charges 344,473.20
Jan 1, 2024 IDA-64560 Int Charges 551,365.25
Jan 1, 2024 IDA-64560 Int Charges 7,462.88
Sep 30, 2020 IDA-64560 Loan Disb 17,740,000.00
Jan 1, 2021 IDA-64560 Int Charges 34,413.41
Jan 1, 2021 IDA-64560 Int Charges 34,413.41
Jan 1, 2021 IDA-64560 Int Charges 55,531.48
Jun 17, 2021 IDA-64560 Loan Disb 10,690,000.00
Jul 1, 2021 IDA-64560 Int Charges 1,803.51
Jul 1, 2021 IDA-64560 Int Charges 70,404.38
Jul 1, 2021 IDA-64560 Int Charges 70,404.38
Jul 1, 2021 IDA-64560 Int Charges 110,592.76
Jun 17, 2022 IDA-64560 Loan Disb 34,400,000.00
Jul 1, 2022 IDA-64560 Int Charges 2,308.48
Jul 1, 2022 IDA-64560 Int Charges 2,308.48
Jul 1, 2022 IDA-64560 Int Charges 107,837.43
Jul 1, 2022 IDA-64560 Int Charges 107,837.43
Jul 1, 2022 IDA-64560 Int Charges 159,821.98
Jan 1, 2022 IDA-64560 Int Charges 105,401.81
Jan 1, 2022 IDA-64560 Int Charges 105,401.81
Jan 1, 2022 IDA-64560 Int Charges 175,669.66
Jun 20, 2019 IDA-64560 Loan Commitment 171,000,000.00
Jun 14, 2024 IDA-64560 Loan Disb 20,000,000.00
Jul 1, 2024 IDA-64560 Int Charges 606,123.10
Jul 1, 2024 IDA-64560 Int Charges 22,323.36
Jul 1, 2024 IDA-64560 Loan Repay 2,680,566.20
Jul 1, 2024 IDA-64560 Int Charges 377,975.94
Jul 1, 2024 IDA-64560 Int Charges 377,975.94
Mar 21, 2024 IDA-64560 Loan Disb 16,000,000.00
Jan 1, 2022 IDA-64560 Int Charges 6,632.56
Jan 1, 2023 IDA-64560 Int Charges 228,799.19
Jan 1, 2023 IDA-64560 Int Charges 228,799.19
Jan 1, 2023 IDA-64560 Int Charges 359,835.78
Jan 1, 2023 IDA-64560 Int Charges 23,771.45
Mar 8, 2023 IDA-64560 Loan Disb 16,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2025-01-09
Monitoring and Evaluation Satisfactory 2025-01-09
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-09
Progress towards achievement of PDO Moderately Satisfactory 2025-01-09
Procurement Satisfactory 2025-01-09
Project Management Satisfactory 2025-01-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in water losses in watercourses (% point)Value45.0034.9125.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Water productivity of watercoursesValue0.95 kg/m3 for wheat and maize16 percent increase in productivity of wheat and m10 % increase
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Project beneficiaries reached with agricultural assests or servicesValue0.00112399.00150000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Private Investment Mobilised by the Project (millions)Value0.0031.6275.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Number of individuals benefiting from response activities to an eligible crisis or emergencyValue0.0098944.0090000.00
    DateJanuary 5, 2023February 9, 2024October 27, 2023
    Comment
  • Water productivity of HEISValue1.03 kg/m3 for citrus and 1.17 kg/m3 vegetable usiAchievement against this indicator remains at 9 pe45% increase
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • % share of woman in total number of beneficiariesValue0.001.5030.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Production area for higher-value crops (ha.)Value0.001105.002000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Demonstration sites establsihedValue0.0022.00150.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Citizen Engagement: Beneficiaries that feel the project investments reflect their needs and provide feedbackValue0.00100.0075.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Area (ha.) brought under HEISValue0.001105.004048.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.00187130.00427000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Number of individuals, affected by 2022 floods, receiving wheat seed in a timely manner through the projectValue0.0065079.0063282.00
    DateJanuary 5, 2023February 9, 2024January 19, 2023
    Comment
  • Number of individual farmers benefiting from fruit fly management practices through the projectValue0.00100606.0070000.00
    DateJanuary 5, 2023February 9, 2024October 27, 2023
    Comment
  • Agricultural yields for selected irrigated crops (t/ha)Valuewheat and maize 2.4 t/haYield for wheat and maize has risen by 5 percent10% increase
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Area leveled (ha.) with PLLsValue0.006115.0096000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Gender: women beneficiaries that feel the project investments meet their needs and provide feedbackValue0.000.0075.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Farmers trainedValue0.00926.0035000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Operational Water Users Associations created and / or stregthenedValue0.0010839.0019000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Area Irrigated (ha.) with Water Storage TanksValue0.0015950.0022500.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Soil and water conservation infrastructure rehabilitated through projectValue89.0089.00573.00
    DateFebruary 9, 2024February 9, 2024September 15, 2023
    Comment
  • Female staff recruited in PIUValue0.0033.0030.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Women trainedValue0.000.0010500.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Improved animal feed supplied through projectValue0.000.0021870.00
    DateFebruary 9, 2024February 9, 2024October 27, 2023
    Comment
  • Net Rate of Greenhouse Gases SinkValue0.000.000.08
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Staff trainingValue0.00854.003000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Percent of women shareholders that are members of WUAsValue0.000.000.00
    Date
    Comment
  • Doses of vaccines and medicines provided through projectValue0.000.001325583.00
    DateJanuary 5, 2023February 9, 2024October 27, 2023
    Comment
  • Number of WUAs with women as executive memberValue0.000.000.00
    Date
    Comment
  • Female staff trainedValue0.00140.001000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment
  • Watercourses improvedValue0.007852.0014000.00
    DateJuly 1, 2019February 9, 2024June 30, 2025
    Comment