Second Additional Financing for the Afghanistan Rural Enterprise Development Project

Development Objective

Increased income and sustainable employment opportunities for men and women through supported rural enterprises.

Key Details

Project Details

  • P163525

  • Closed

  • Abimbola Adubi , Azada Hussaini

  • N/A

  • Afghanistan

  • June 15, 2017

  • (as of board presentation)

    November 21, 2017

  • N/A

  • US$ 5.00 million

  • N/A

  • South Asia

  • 2018

  • US$ 5.00 million

  • B

  • March 8, 2022

  • June 30, 2018

  • Yes

  • BANK APPROVED

  • P110407

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 5.00
Total Project Cost** 5.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2018-06-28
Procurement Satisfactory 2018-06-28
Progress towards achievement of PDO Satisfactory 2018-06-28
Financial Management Satisfactory 2018-06-28
Monitoring and Evaluation Satisfactory 2018-06-28
Overall Implementation Progress (IP) Satisfactory 2018-06-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 60% of Enterprise Groups (EGs) will have increased their net revenues by over 20%. At least 50% female.Value182% overallof this, 63% female60% of Enterprise Groups
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment
  • 80% of EGs supported by the Project will still be operating 2 years after start up. At least 35% will be femaleValue194%80% of EGs
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment
  • At least 35% of participating enterprises will have increased direct and/or indirect employment by at least 30% (Of these at least 35% will be women)Value136% overall of this, 59% femaleAt least 35% of participating SMEs and EGs or thei
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment
  • Direct project beneficiariesValue1.0069427.0068500.00
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment
  • At least 90% of project beneficiaries have access to financial servicesValue1.00100.0090.00
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment
  • Female beneficiariesValue1.0056.0050.00
    DateJune 14, 2010October 31, 2016June 30, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • At least 40% of loan-able funds are in circulation at any given timeValue195%40% of loanable funds
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • 25% of SG members have accessed and repaid loansValue137%25% SGs
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • At least 70% of viable SGs federate into VSLAsValue170%60% / Est. 3,900 SGs and 390 VSLAs
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • VSLAs maintain at least 95% repayment rate on loans and at any given time have at least 60% of loanable fundsValue192%95% repayment rate.
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • At least 30% increase in direct/and or indirect employmentValue125.6%20% increase
    DateJune 14, 2010November 13, 2016June 30, 2018
    Comment
  • Project management's development and accreditation of technical and professional service providers results in at least 20 project supported BDS service providers providing paidfor servicesValue02020 standing offers for services delivered/province
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • Project management takes and records all necessary actions related to findings of regular monitoring, evaluation and learning reportsValue1100%Satisfactory
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • All complaints received by Project and field staff are addressed within an established timeframe adn according to agreed standardsValueNo complaints99% of the received complaints are addressed100% disposed
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • Project management satisfactorily addresses the findings of the statutory audit conductd by the Auditor General for all IDA-fonanced/managed projects; and findings from an additional commercial auditValueNo issuesFindings addressed within 3 monthsFindings addressed within 3 months
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • At least 60% SGs and 80% VSLAs receive seed capitalValue1.0038.0060.00
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • 50% of the supported SMEs report increased net revenuesValue1.0077.0050.00
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • At least 15% of project supported SMEs are female ownedValue1.0013.0015.00
    DateJune 14, 2010November 14, 2016June 30, 2018
    Comment
  • Facilitating partners for social mobilization identified and procurement arrangements for them agreed between WB, MRRD and MoFValue201705302017053020180630
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment
  • District situation analysis completed for new target provinces.Value201705302017053020180630
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment
  • Facilitating partners for social mobilization identified and procurement arrangements for them agreed between WB, MRRD and MoF.Value201705302017053020180630
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment
  • Provincial situation analysis completed for at least 5 provinces.Value201705302017053020180630
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment
  • Review of women-led SMEs completed, their challenges and needs identifiedValue0.000.001.00
    DateMay 17, 2017May 30, 2017June 30, 2018
    Comment
  • Assessment on cost effectiveness and technical capabilities of facilitating partners completedValue0.000.001.00
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment
  • Value chain and sub-sector analysis completed in key identified sector i.e. poultry, fisheries, handicraftValue0.000.000.00
    DateMay 30, 2017May 30, 2017June 30, 2018
    Comment