Financier | Commitments |
---|---|
IDA Credit | 300.00 |
P163593
Closed
Hemang Karelia
N/A
November 16, 2017
(as of board presentation)
December 15, 2017
N/A
US$ 300.00 million
N/A
2018
US$ 300.00 million
B
Not Applicable
June 30, 2023
Yes
BANK APPROVED
August 15, 2024
Financier | Commitments |
---|---|
IDA Credit | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 300.00 |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.00 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Households with resilient core housing reconstructed under the project | Value | 0.00 | 31776.00 | 151000.00 |
Date | July 31, 2015 | October 5, 2017 | June 30, 2023 | |
Comment | The number of houses found compliant during the house inspection for second tranche of housing grant. As houses beingreconstructed are under different stages of the reconstruction, first inspection has been taken as basis for this calculation. | Cumulative Target |
Citizens made aware of earthquake resilient reconstruction | Value | 0.00 | 31776.00 | 151000.00 |
Date | July 31, 2015 | October 5, 2017 | June 30, 2023 | |
Comment | The number of beneficiaries whose houses found compliant during the house inspection for second tranche of housing grant. Ashouses being reconstructed are under different stages of the reconstruction, first inspection has been taken as basis for thiscalculation. | Cumulative Target |
Government officials trained on Disaster Risk Management | Value | 0.00 | 27.00 | 200.00 |
Date | July 31, 2015 | October 5, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. | Cumulative Target. |
Out of which women headed households | Value | 0.00 | 8261.00 | 39260.00 |
Date | July 31, 2015 | October 5, 2017 | June 30, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 136637.00 | 649300.00 |
Date | July 31, 2015 | October 5, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. | 4.3 times the actual households with resilient core housing reconstructed so far. | Cumulative Target4.3 times the total households with resilient core housing to be reconstructed under the project. |
Intended beneficiaries aware of project info. and project investments (%) | Value | 0.00 | 57.77 | 100.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 92.61 | 95.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. |
Improved houses reconstructed under the project | Value | 0.00 | 332.00 | 55000.00 |
Date | July 31, 2015 | May 5, 2017 | July 31, 2020 | |
Comment |
Artisans trained in multi-hazard resistant construction | Value | 0.00 | 44647.00 | 75000.00 |
Date | July 31, 2015 | October 5, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. | Actual Number of masons, plumbers, electricians, carpenters trained as of date. | Cumulative Target |
Technical studies on disaster risk management completed | Value | 0.00 | 0.00 | 4.00 |
Date | July 31, 2015 | August 31, 2017 | July 31, 2020 | |
Comment | There's no baseline for this indicator. | Cumulative Target |
Female beneficiaries | Value | 0.00 | 50.00 | 50.00 |
Date | July 31, 2015 | October 5, 2017 | July 31, 2020 | |
Comment |
Intended beneficiaries aware of project info. and project investments - female | Value | 0.00 | 8261.00 | 39260.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment |
Intended beneficiaries aware of project info. and project investments ?male | Value | 0.00 | 79862.00 | 118250.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment |
Intended beneficiaries - female (number) | Value | 0.00 | 0.00 | 118250.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment |
Intended beneficiaries - male (number) | Value | 0.00 | 0.00 | 118250.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment |
Grievances related to delivery of project benefits that are addressed-(number) | Value | 0.00 | 49051.00 | 100000.00 |
Date | July 31, 2015 | September 11, 2017 | July 31, 2020 | |
Comment |