Financier | Commitments |
---|---|
IDA Grant | 4.00 |
P163699
Closed
Iretomiwa Olatunji , Simone Esler
Pacific Community
Pacific Islands
May 9, 2017
(as of board presentation)
May 9, 2017
September 15, 2017
US$ 4.00 million
Pacific Community
2017
US$ 4.00 million
B
Not Applicable
March 31, 2024
Yes
BANK APPROVED
March 21, 2024
Financier | Commitments |
---|---|
IDA Grant | 4.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 4.00 |
IBRD + IDA Commitment | 4.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 4.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 19, 2022 | IDA-D1820 | Loan Disb | 55,682.46 |
Dec 9, 2021 | IDA-D1820 | Loan Disb | 34,174.41 |
Nov 2, 2022 | IDA-D1820 | Loan Disb | 147,137.56 |
Nov 7, 2022 | IDA-D1820 | Loan Disb | 113,287.57 |
Feb 21, 2023 | IDA-D1820 | Loan Disb | 42,586.54 |
Feb 24, 2023 | IDA-D1820 | Loan Disb | 143,114.55 |
Jun 20, 2023 | IDA-D1820 | Loan Disb | 37,409.17 |
Jun 22, 2023 | IDA-D1820 | Loan Disb | 103,216.21 |
Jun 22, 2023 | IDA-D1820 | Loan Disb | 70,995.51 |
Sep 25, 2023 | IDA-D1820 | Loan Disb | 129,361.25 |
Dec 22, 2023 | IDA-D1820 | Loan Disb | 193,969.66 |
Dec 19, 2023 | IDA-D1820 | Loan Disb | 96,909.93 |
Sep 28, 2023 | IDA-D1820 | Loan Disb | 57,441.76 |
Jun 18, 2024 | IDA-D1820 | Loan Disb | 28,502.53 |
Jun 17, 2024 | IDA-D1820 | Loan Disb | 251,404.19 |
Jun 12, 2024 | IDA-D1820 | Loan Disb | 127,482.73 |
May 9, 2017 | IDA-D1820 | Loan Commitment | 4,000,000.00 |
Apr 4, 2018 | IDA-D1820 | Loan Disb | 460,687.50 |
Dec 20, 2018 | IDA-D1820 | Loan Disb | 59,678.17 |
Oct 1, 2018 | IDA-D1820 | Loan Disb | 82,237.00 |
Jun 10, 2019 | IDA-D1820 | Loan Disb | 41,506.59 |
Nov 18, 2019 | IDA-D1820 | Loan Disb | 46,097.20 |
Sep 20, 2019 | IDA-D1820 | Loan Disb | 340,600.25 |
Apr 30, 2020 | IDA-D1820 | Loan Disb | 261,739.58 |
Jul 21, 2020 | IDA-D1820 | Loan Disb | 18,731.94 |
Dec 8, 2020 | IDA-D1820 | Loan Disb | 166,243.69 |
Dec 11, 2020 | IDA-D1820 | Loan Disb | 58,871.44 |
Dec 11, 2020 | IDA-D1820 | Loan Disb | 209,362.00 |
Mar 31, 2021 | IDA-D1820 | Loan Disb | 98,578.46 |
Apr 12, 2021 | IDA-D1820 | Loan Disb | 47,901.82 |
Mar 26, 2021 | IDA-D1820 | Loan Disb | 45,992.22 |
Aug 19, 2021 | IDA-D1820 | Loan Disb | 82,422.79 |
Aug 16, 2021 | IDA-D1820 | Loan Disb | 64,655.80 |
Dec 14, 2021 | IDA-D1820 | Loan Disb | 55,359.95 |
Mar 15, 2022 | IDA-D1820 | Loan Disb | 70,676.50 |
Jun 24, 2022 | IDA-D1820 | Loan Disb | 21,501.12 |
Jun 21, 2022 | IDA-D1820 | Loan Disb | 38,790.47 |
Aug 24, 2022 | IDA-D1820 | Loan Disb | 49,734.17 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2024-03-29 |
Monitoring and Evaluation | Satisfactory | 2024-03-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-03-29 |
Project Management | Moderately Satisfactory | 2024-03-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-03-29 |
Procurement | Moderately Satisfactory | 2024-03-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-10-2024 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-26-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Staff trained in early warning and preparedness apply knowledge they have acquired during disaster response or simulated drills | Value | 0.00 | 100.00 | 50.00 |
Date | March 28, 2017 | March 25, 2024 | March 28, 2017 | |
Comment |
Sector agencies are using new coastal risk assessment tool to assist with planning decision making | Value | 0.00 | 4.00 | 2.00 |
Date | March 28, 2017 | March 31, 2024 | March 28, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Staff involved in Early warning and preparedness are trained on new procedures | Value | 0.00 | 56.00 | 60.00 |
Date | February 20, 2017 | March 31, 2024 | March 28, 2017 | |
Comment |
Alternative construction aggregate resources identified and shared with government and stakeholders | Value | No | Yes | Yes |
Date | February 1, 2017 | March 31, 2024 | March 28, 2017 | |
Comment |
Relevant, understandable and usable disaster risk information available to national and local agencies | Value | No | Yes | Yes |
Date | March 28, 2017 | March 31, 2024 | March 28, 2017 | |
Comment |