Financier | Commitments |
---|---|
IDA Credit | 45.70 |
P163846
Closed
Emmanuel Nkrumah
N/A
June 6, 2017
(as of board presentation)
June 28, 2017
N/A
US$ 45.70 million
N/A
2017
US$ 45.70 million
B
October 18, 2023
June 30, 2020
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 45.70 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 45.70 |
IBRD + IDA Commitment | 45.70 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 45.70 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in rural areas provided with access to Improved Water Sources under the project | Value | 0.00 | 755000.00 | 800000.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Reliability of water supply services under the project area | Value | 0.00 | 16.00 | 16.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Communities in project area declared free of open defecation (number) | Value | 0.00 | 50.00 | 550.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Water systems in project areas with ratio of revenues over O&M costs (including depreciation) >=1.0(percent) | Value | 1.00 | 0.90 | 0.90 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Percentage of installed water supply system functional | Value | 0.00 | 100.00 | 100.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 343905.00 | 600000.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 755000.00 | 800000.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
People provided with access to ?improved sanitation facilities?- rural | Value | 0.00 | 343905.00 | 600000.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Female beneficiaries | Value | 0.00 | 52.00 | 52.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New water systems for small towns operational (number) | Value | 0.00 | 57.00 | 60.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
New mechanized boreholes operational | Value | 0.00 | 58.00 | 60.00 |
Date | June 22, 2010 | June 13, 2016 | December 31, 2019 | |
Comment |
New water systems based on boreholes fitted with hand pumps operational | Value | 0.00 | 998.00 | 1200.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
New community water systems fed from GWCL | Value | 0.00 | 0.00 | 5.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Former GWCL systems transferred to communities rehabilitated | Value | 0.00 | 6.00 | 15.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Orphan boreholes rehabilitated | Value | 0.00 | 400.00 | 300.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
New Institutional toilet facilities constructed and operational | Value | 0.00 | 437.00 | 400.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Communities sensitized about hygiene practices and eradication of open free defecation | Value | 0.00 | 1489.00 | 600.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Subproject implementation in accordance with timetable in procurement plan (percent for each participating DA) | Value | 0.00 | 0.80 | 0.95 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Acceptable implementation (including safeguards) quarterly reports delivered on time (percent for each participating DA) | Value | 0.00 | 0.80 | 1.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Timely submittal of clean (unqualified) FM audit reports (percent for each participating DA) | Value | 0.00 | 0.70 | 1.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
District Assemblies operating DiMES | Value | 0.00 | 64.00 | 94.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Key institutions (CWSA, MOFEP, MWRWH, MLGRD) trained in the use Sector Information Systems | Value | 0.00 | 4.00 | 4.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |
Improved latrines constructed under the project | Value | 0.00 | 22927.00 | 40000.00 |
Date | June 22, 2010 | December 14, 2016 | December 31, 2019 | |
Comment |