Financier | Commitments |
---|---|
Somalia Multi-Partner Fund | 9.00 |
P163857
Closed
Makiko Watanabe
Ministry of Finance
June 29, 2018
(as of board presentation)
August 2, 2018
October 18, 2018
US$ 9.00 million
Garowe Municipality,Benadir Regional Administration
2019
US$ 9.00 million
B
August 5, 2024
September 30, 2021
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Somalia Multi-Partner Fund | 9.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 9.00 |
Total Project Cost** | 9.00 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2021-07-07 |
Financial Management | Moderately Satisfactory | 2021-07-07 |
Project Management | Moderately Satisfactory | 2021-07-07 |
Progress towards achievement of PDO | Satisfactory | 2021-07-07 |
Monitoring and Evaluation | Satisfactory | 2021-07-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-07-07 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-06-2022 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People with access to all season roads within a 500 meter range (number, % female, % IDPs, % host communities) | Value | 0.00 | 2000.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
Beneficiaries satisfied that infrastructure met their needs (number, % female, % IDPs) | Value | 0.00 | 90.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
Sub projects with post-construction community engagement/O&M plans | Value | 0.00 | 23.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
People’s satisfaction of the municipal government performance on road rehabilitation | Value | 0.00 | 60.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Person days of employment created (days, % female, % IDPs, % host communities) | Value | 0.00 | 22000.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Project and government staff formally trained (number) | Value | 0.00 | 20.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
Maintenance Committees established and functioning (number, broken down by IDPs, gender) | Value | 0.00 | 7.00 | 0.00 |
Date | August 1, 2018 | September 30, 2021 | ||
Comment |
Person days of employment created (days,%female, %IDPs, %host communities) | Value | 0.00 | 18000.00 | 0.00 |
Date | June 21, 2018 | September 30, 2021 | ||
Comment |
Project and Government staff formally trained | Value | 0.00 | 30.00 | 0.00 |
Date | June 21, 2018 | September 30, 2021 | ||
Comment |
Maintenance Committees established and functioning (number, broken down by IDPs, gender) | Value | 0.00 | 1.00 | 0.00 |
Date | June 21, 2018 | September 30, 2021 | ||
Comment |
Roads rehablitated | Value | 0.00 | 7.50 | 0.00 |
Date | July 30, 2018 | September 30, 2021 | ||
Comment |
Roads rehablitated | Value | 0.00 | 4.40 | 0.00 |
Date | June 21, 2018 | September 30, 2021 | ||
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | July 30, 2018 | November 26, 2018 | ||
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | July 30, 2018 | November 26, 2018 | ||
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | July 30, 2018 | November 26, 2018 | ||
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | July 30, 2018 | November 26, 2018 | ||
Comment |