| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 49.60 | 
P163896
Active
Yuko Arai
Republic of Indonesia
November 9, 2017
(as of board presentation)
June 11, 2019
November 25, 2019
US$ 49.60 million
Ministry of Public Works and Housing (MPWH),Ministry of Home Affairs (MOHA),Ministry of National Development Planning (BAPPENAS)
2019
US$ 49.60 million
B
Not Applicable
December 31, 2025
No
BANK APPROVED
January 26, 2024
| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 49.60 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | 49.60 | 
| IDA Commitment | N/A | 
| IBRD + IDA Commitment | 49.60 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 49.60 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Jun 11, 2019 | IBRD-89760 | Loan Commitment | 49,600,000.00 | 
| Jan 15, 2022 | IBRD-89760 | Int Charges | 59,280.13 | 
| Jul 15, 2022 | IBRD-89760 | Int Charges | 16,104.61 | 
| Feb 20, 2024 | IBRD-89760 | Loan Disb | 3,650,000.00 | 
| Dec 4, 2023 | IBRD-89760 | Loan Disb | 907,000.00 | 
| Nov 20, 2023 | IBRD-89760 | Loan Disb | 443,000.00 | 
| Dec 18, 2023 | IBRD-89760 | Loan Disb | 77,200.00 | 
| Jul 15, 2023 | IBRD-89760 | Int Charges | 4,043.82 | 
| Jul 15, 2023 | IBRD-89760 | Int Charges | 56,982.13 | 
| Jul 15, 2023 | IBRD-89760 | Int Charges | 109,335.40 | 
| Jul 15, 2023 | IBRD-89760 | Int Charges | 272.17 | 
| Jan 15, 2023 | IBRD-89760 | Int Charges | 59,007.96 | 
| Jul 15, 2024 | IBRD-89760 | Int Charges | 12,372.97 | 
| Jun 6, 2024 | IBRD-89760 | Loan Disb | 2,517,000.00 | 
| Jul 15, 2024 | IBRD-89760 | Int Charges | 280,384.90 | 
| Jul 15, 2024 | IBRD-89760 | Int Charges | 50,579.50 | 
| Jul 15, 2024 | IBRD-89760 | Int Charges | 445.26 | 
| Jan 15, 2024 | IBRD-89760 | Int Charges | 57,089.02 | 
| Jan 15, 2024 | IBRD-89760 | Int Charges | 132,994.50 | 
| Jul 15, 2020 | IBRD-89760 | Int Charges | 60,786.03 | 
| Jul 15, 2020 | IBRD-89760 | Int Charges | 338.80 | 
| May 26, 2020 | IBRD-89760 | Loan Disb | 2,562,500.00 | 
| Jan 15, 2020 | IBRD-89760 | Fee Charges | 124,000.00 | 
| Jul 15, 2021 | IBRD-89760 | Int Charges | 58,313.62 | 
| Jul 15, 2021 | IBRD-89760 | Int Charges | 14,172.06 | 
| Jan 15, 2021 | IBRD-89760 | Int Charges | 8,805.40 | 
| Jan 15, 2021 | IBRD-89760 | Int Charges | 59,130.50 | 
| Jan 15, 2021 | IBRD-89760 | Int Charges | 15,585.70 | 
| Jan 15, 2021 | IBRD-89760 | Int Charges | 875.16 | 
| Jan 15, 2023 | IBRD-89760 | Int Charges | 51,210.15 | 
| Aug 23, 2023 | IBRD-89760 | Loan Disb | 383,000.00 | 
| Dec 9, 2022 | IBRD-89760 | Loan Disb | 1,074,000.00 | 
| Jan 15, 2022 | IBRD-89760 | Int Charges | 13,097.24 | 
| Jul 15, 2022 | IBRD-89760 | Int Charges | 58,313.62 | 
| Name | Review | Date | 
|---|---|---|
| Monitoring and Evaluation | Satisfactory | 2025-09-30 | 
| Procurement | Moderately Satisfactory | 2025-09-30 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2025-09-30 | 
| Project Management | Satisfactory | 2025-09-30 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-09-30 | 
| Financial Management | Moderately Unsatisfactory | 2025-09-30 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| City's long-term spatial planning reflects the spatial development framework approach | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| City is utilizing spatially-informed capital investment planning and budgeting framework | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| National Urban Development Strategy completed | Value | No | No | Yes | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Inter-ministerial Coordination Team for Urban Development annual work program developed | Value | No | No | Yes | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Project management support systems established and operational | Value | No | No | Yes | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with city capacity assessment completed | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| National knowledge exchange workshop with all stakeholders conducted | Value | 0.00 | 3.00 | 5.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with training and workshop delivered on planning and budgeting, project management, and procurement | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Synthesis report of national urban development strategy completed | Value | No | No | Yes | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with spatial development framework developed | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with spatial area framework developed | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with priority area development plans reflecting inclusive urban design principles with a specific focus on enhancing women'ssafety in public spaces and universal accessibility | Value | 0.00 | 0.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Number of public consultations held on priority area development planning with published reports on feedback from the consultations | Value | 0.00 | 0.00 | 5.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Cities with capacity building on integrated planning delivered and spatially-informed capital investment plans developed | Value | 0.00 | 40.00 | 60.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment | 
| Number of selected major projects that are informed by the output of priority area development plans | Value | 0.00 | 0.00 | 3.00 | 
| Date | January 31, 2019 | November 22, 2023 | December 31, 2024 | |
| Comment |