P163939
Closed
Ahsan Tehsin , Armando Guzman Escobar, Rocio Schmunis
REPUBLIC OF MALDIVES
December 22, 2017
(as of board presentation)
July 1, 2019
November 7, 2019
US$ 10.00 million
Ministry of Finance
2020
US$ 10.00 million
N/A
N/A
September 30, 2022
BANK APPROVED
September 26, 2023
Financier | Commitments |
---|---|
IDA Credit | 5.00 |
IDA Grant | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 10.00 |
IBRD + IDA Commitment | 10.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 10.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2024 | IDA-64540 | Int Charges | 31.77 |
Aug 15, 2020 | IDA-64540 | Int Charges | 14,991.81 |
Feb 15, 2024 | IDA-64540 | Int Charges | 18,322.35 |
Feb 15, 2024 | IDA-64540 | Int Charges | 18,322.35 |
Jul 1, 2019 | IDA-64540 | Loan Commitment | 5,000,000.00 |
Jul 1, 2019 | IDA-D4930 | Loan Commitment | 5,000,000.00 |
Aug 15, 2024 | IDA-64540 | Int Charges | 18,032.64 |
Aug 15, 2024 | IDA-64540 | Int Charges | 18,032.64 |
Aug 15, 2024 | IDA-64540 | Int Charges | 249.34 |
Aug 15, 2024 | IDA-64540 | Int Charges | 249.34 |
Feb 15, 2023 | IDA-64540 | Int Charges | 159.08 |
Feb 15, 2023 | IDA-64540 | Int Charges | 159.08 |
Feb 15, 2023 | IDA-64540 | Int Charges | 18,305.90 |
Feb 15, 2023 | IDA-64540 | Int Charges | 18,305.90 |
Aug 15, 2023 | IDA-64540 | Int Charges | 90.83 |
Aug 15, 2023 | IDA-64540 | Int Charges | 90.83 |
Aug 15, 2023 | IDA-64540 | Int Charges | 18,486.36 |
Aug 15, 2023 | IDA-64540 | Int Charges | 18,486.36 |
Aug 15, 2022 | IDA-64540 | Int Charges | 56.25 |
Aug 15, 2022 | IDA-64540 | Int Charges | 56.25 |
Aug 15, 2022 | IDA-64540 | Int Charges | 18,320.41 |
Aug 15, 2022 | IDA-64540 | Int Charges | 18,320.41 |
Feb 15, 2022 | IDA-64540 | Int Charges | 261.63 |
Feb 15, 2022 | IDA-64540 | Int Charges | 261.63 |
Feb 15, 2022 | IDA-64540 | Int Charges | 19,115.34 |
Feb 15, 2022 | IDA-64540 | Int Charges | 19,115.34 |
Aug 15, 2021 | IDA-64540 | Int Charges | 38.53 |
Aug 15, 2021 | IDA-64540 | Int Charges | 38.53 |
Aug 15, 2021 | IDA-64540 | Int Charges | 19,707.36 |
Aug 15, 2021 | IDA-64540 | Int Charges | 19,707.36 |
Aug 15, 2020 | IDA-64540 | Int Charges | 14,991.81 |
Feb 15, 2021 | IDA-64540 | Int Charges | 336.92 |
Feb 15, 2021 | IDA-64540 | Int Charges | 336.92 |
Feb 15, 2021 | IDA-64540 | Int Charges | 19,951.32 |
Feb 15, 2021 | IDA-64540 | Int Charges | 19,951.32 |
Mar 24, 2020 | IDA-64540 | Loan Disb | 5,012,094.00 |
Mar 24, 2020 | IDA-D4930 | Loan Disb | 5,012,094.00 |
Feb 15, 2024 | IDA-64540 | Int Charges | 31.77 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2022-10-05 |
Overall Implementation Progress (IP) | Satisfactory | 2022-10-05 |
Progress towards achievement of PDO | Satisfactory | 2022-10-05 |
Monitoring and Evaluation | Satisfactory | 2022-10-05 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-02-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 03-12-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Health workers trained on the HEOP's gender-specific activities in crisis situations. | Value | 0.00 | 100.00 | 100.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
The Nat. Disaster Managment Plan is drafted | Value | No | Yes | Yes |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
Water service coverage | Value | 51.00 | 71.00 | 80.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
Simulations exercises on the activation and use of the HEOC are carried out | Value | 0.00 | 4.00 | 3.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
The Building Code has been enforced through the issuance of compliance documents | Value | 0.00 | 11.00 | 10.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
Sewerage service coverage | Value | 67.00 | 81.00 | 90.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
The Nat. Disaster Managment Authoirty (NDMA) reports on NEOP readiness | Value | 0.00 | 3.00 | 3.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |
EWS is supported with expanded meteorologial observation network with automated weather station (AWS) | Value | 36.00 | 22.00 | 50.00 |
Date | September 30, 2019 | September 30, 2022 | September 30, 2022 | |
Comment |