Financier | Commitments |
---|---|
Philippines - Multi-donor Trust Fund Program for Mindanao | 3.20 |
P164019
Closed
Maria Padua
Community and Family Services International
December 8, 2017
(as of board presentation)
April 4, 2018
April 10, 2018
US$ 3.20 million
Community Family and Services International
2018
US$ 3.20 million
B
March 7, 2024
December 31, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Philippines - Multi-donor Trust Fund Program for Mindanao | 3.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.20 |
Total Project Cost** | 3.20 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-09-25 |
Overall | Moderable | 2020-09-25 |
Overall Implementation Progress (IP) | Satisfactory | 2020-09-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-17-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries in targeted communities in conflict-affected areas in Mindanao reporting improved access to socio-economic infrastructure in terms of time, distance and cost | Value | 0.00 | 50.00 | 53.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Number of people in targeted communities in conflict-affected areas in Mindanao with improved literacy | Value | 0.00 | 2513.00 | 2512.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Direct project beneficiaries, of which women | Value | 0.00 | 50.00 | 76.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Direct project beneficiaries, of which women | Value | 0.00 | 1300.00 | 1359.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of community volunteers that benefited from capacity-building assistance by the Project | Value | 0.00 | 1151.00 | 1151.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Number of BDA, camp JTFCT and CPST members provided with capacity-building assistance | Value | 0.00 | 101.00 | 103.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Number of community-wide meetings that achieved at least 60% participation of households in targeted communities | Value | 0.00 | 34.00 | 40.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Number of reflection sessions conducted for targeted communities | Value | 0.00 | 90.00 | 122.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Number of socio-economic infrastructure subprojects completed | Value | 0.00 | 44.00 | 42.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |
Capacity building activities for camp JTFCT and JTFCT Coordinators | Value | 0.00 | 16.00 | 16.00 |
Date | July 15, 2019 | December 31, 2020 | December 31, 2020 | |
Comment |
Capacity building activities for BDA (CMO and CPST) | Value | 0.00 | 16.00 | 16.00 |
Date | July 15, 2019 | December 31, 2020 | December 31, 2020 | |
Comment |
Capacity building activities for Peoples' Organizations | Value | 0.00 | 24.00 | 24.00 |
Date | July 15, 2019 | December 31, 2020 | December 31, 2020 | |
Comment |
Community volunteers, of which women | Value | 0.00 | 863.00 | 469.00 |
Date | April 2, 2018 | December 31, 2020 | December 31, 2020 | |
Comment |