| Financier | Commitments |
|---|---|
| Borrower/Recipient | 2.00 |
| IDA Credit | 30.00 |
| IDA Grant | 30.00 |
| Local Beneficiaries | 2.50 |
P164052
Active
Soulemane Fofana , Kalilou Sylla
Ministry of Finance
May 15, 2018
(as of board presentation)
July 5, 2018
October 22, 2018
US$ 64.50 million
Ministry of Agriculture
2019
US$ 60.00 million
B
Not Applicable
December 31, 2025
TBD
Bank Approved
November 14, 2024
| Financier | Commitments |
|---|---|
| Borrower/Recipient | 2.00 |
| IDA Credit | 30.00 |
| IDA Grant | 30.00 |
| Local Beneficiaries | 2.50 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | N/A |
| IDA Commitment | 60.00 |
| IBRD + IDA Commitment | 60.00 |
| Lending Instrument | |
|---|---|
| Grant Amount | N/A |
| Total Project Cost** | 64.50 |
| Name | Review | Date |
|---|---|---|
| Counterpart Funding | Satisfactory | 2025-08-11 |
| Financial Management | Moderately Satisfactory | 2025-08-11 |
| Monitoring and Evaluation | Satisfactory | 2025-08-11 |
| Overall Implementation Progress (IP) | Satisfactory | 2025-08-11 |
| Procurement | Moderately Satisfactory | 2025-08-11 |
| Progress towards achievement of PDO | Satisfactory | 2025-08-11 |
| Project Management | Satisfactory | 2025-08-11 |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Yield increase of major crops in the project areas | Value | 0.00 | 0.00 | 20.00 |
| Date | April 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Beneficiary statisfaction rate with services provided by the project | Value | 0.00 | 90.00 | 90.00 |
| Date | April 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Direct beneficiary households of the project | Value | 0.00 | 162528.00 | 171000.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Female head of household direct beneficiaries of the project | Value | 0.00 | 59291.00 | 53000.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Proportion of cash transfer beneficiary households with food consumption score above 35 | Value | 46.00 | 47.00 | 70.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Yield increase in Maize | Value | 2.50 | 2.57 | 3.00 |
| Date | April 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Yield increase in Millet | Value | 1.00 | 1.20 | 1.20 |
| Date | April 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Yield increase of Sorghum | Value | 1.20 | 0.96 | 1.44 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Agricultural policies affecting dryland enforced as a result of the project policy notes | Value | 0.00 | 3.00 | 7.00 |
| Date | April 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Area directly protected or recovered as result from investment of productive community infrastructure made by the project | Value | 0.00 | 999.75 | 3000.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Direct cash transfer recipients | Value | 0.00 | 0.00 | 7700.00 |
| Date | April 30, 2018 | September 30, 2023 | ||
| Comment |
| Farmers adopting improved agricultural technology | Value | 0.00 | 10956.00 | 10000.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Farmers adopting improved agricultural technology - Female | Value | 0.00 | 0.00 | 2500.00 |
| Date | September 30, 2018 | January 23, 2019 | September 30, 2023 | |
| Comment |
| Grants for PIPs | Value | 0.00 | 0.00 | 600.00 |
| Date | September 30, 2018 | September 30, 2023 | ||
| Comment |
| Households with access to cash transfers, productive transfers and grants (gender disagreg) | Value | 0.00 | 12223.00 | 17000.00 |
| Date | September 30, 2018 | September 30, 2023 | December 31, 2025 | |
| Comment |
| Number of households receiving emergency support from the Project | Value | 0.00 | 116600.00 | 151000.00 |
| Date | December 31, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |
| Productive cash transfer recipients | Value | 0.00 | 0.00 | 4900.00 |
| Date | September 30, 2018 | September 30, 2023 | ||
| Comment |
| Productive infrastructure completed and used by beneficiary community as a result of the project. | Value | 0.00 | 87.00 | 250.00 |
| Date | September 30, 2018 | September 29, 2023 | December 31, 2025 | |
| Comment |