Skip to Main Navigation

Additional Financing for Social Protection System Project

Development Objective

The proposed Project Development Objectives are to support the Government’s effort to: (i) increase access of PROSPERA beneficiaries to social and productive programs, and (ii) develop instruments for an integrated social protection system.

Key Details

Project Details

  • P164152

  • Closed

  • Aylin Isik-Dikmelik

  • SEDESOL,Ministry of Finance,PROSPERA

  • Mexico

  • September 29, 2017

  • (as of board presentation)

    January 29, 2018

  • N/A

  • US$ 300.00 million

  • C

  • Not Applicable

  • June 30, 2021

  • Yes

  • BANK APPROVED

  • P147212

  • September 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • # of PROSPERA beneficiaries that participate in social programsValue465842.001115894.001174811.00
    DateJune 30, 2014December 31, 2016June 30, 2021
    Comment
  • # of PROSPERA beneficiaries that participate in productive programsValue14370.0015949.00236000.00
    DateJune 30, 2014December 31, 2016June 30, 2021
    Comment
  • # of instruments for an integrated social information system implementedValue0.003.008.00
    DateJune 30, 2014July 7, 2017June 30, 2021
    Comment
  • Direct project beneficiariesValue25000000.0028032582.0025000000.00
    DateJune 30, 2014December 31, 2016June 30, 2021
    Comment
  • Female beneficiariesValue52.8053.3052.80
    DateJune 30, 2014December 31, 2016June 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • % of PROSPERA beneficiaries in Q1 and Q2Value68.5068.5071.00
    DateDecember 31, 2010January 29, 2016June 30, 2021
    Comment
  • % of PROSPERA’ students that transition to upper secondaryValue65.0073.9473.00
    DateDecember 31, 2013December 31, 2016June 30, 2021
    Comment
  • Pilots of the PROSPERA coordination modelsValueNoneA number of pilots implemented using internal resoFollow up to the scale-up
    DateDecember 31, 2013July 7, 2017May 16, 2019
    Comment
  • Curriculum for PROSPERA personnel capacity building updatedValueNoneCurriculum content updatedEvaluation of the new curriculum
    DateDecember 31, 2013July 7, 2017June 30, 2021
    Comment
  • % of PROSPERA beneficiaries that are aware of complementary social and productive programsValue0.0047.4080.60
    DateDecember 31, 2013December 31, 2016June 30, 2021
    Comment
  • % beneficiaries of CNCH programs that are registered in the Unique Registry of BeneficiariesValue0.00100.0080.00
    DateDecember 31, 2013July 7, 2017May 16, 2019
    Comment
  • Development of the integrated Social Information SystemValueNoneSocial programs catalogue, Social Registry and UniSocial Registry, Unique Registry of beneficiaries,
    DateDecember 31, 2013July 7, 2017May 16, 2019
    Comment
  • Development of the Regional Social Development StrategyValueNoneNoneProcess evaluation of the RSDS designed and implem
    DateDecember 31, 2013July 7, 2017May 16, 2019
    Comment
  • Curriculum for SEDESOL Personnel capacity building on the RSD StrategyValueNoneNoneEvaluation of the curriculum
    DateDecember 31, 2013July 7, 2017May 16, 2019
    Comment
  • Number of certified bilingual promoters (promotores bilingues)Value136.000.00160.00
    DateJuly 4, 2017June 30, 2021
    Comment
  • % of citizen's demands received that are resolved within the time period established in the ProtocolValue0.000.0090.00
    DateJuly 4, 2017June 30, 2021
    Comment
  • % of municipalities that report the executed FISMDF in the integrated information system (MIDS-SFU)Value63.000.0080.00
    DateJuly 4, 2017June 30, 2021
    Comment
  • % of municipal FAIS liaison (enlaces) that completed capacity building activitiesValue30.000.0070.00
    DateJuly 4, 2017June 30, 2021
    Comment
  • Development of a planning systemValueNo system in placeConsolidated system
    DateJuly 4, 2017June 30, 2021
    Comment
  • % of female PROSPERA beneficiaries that participate in social programsValue0.000.0055.00
    DateNovember 9, 2017June 30, 2021
    Comment
  • % of female PROSPERA beneficiaries that participate in productive programsValue0.000.0050.00
    DateNovember 9, 2017June 30, 2021
    Comment
  • Number of services provided by the Integrated Social Information SystemValue0.000.009.00
    DateDecember 30, 2016June 30, 2021
    Comment