Abstract*

The objective of the Commercial Agriculture Development Project for Guinea is to increase the number of farmers and rural households benefiting from commercial agriculture value-chains in program's areas. There are five components to the project, the first component being improving market access in targeted areas. The first component being improving market access in targeted areas. This component includes three subcomponents: rehabilitation of rural...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Program Development Objective (PrDO) is to increase the number of farmers and rural households benefiting from commercial agriculture value-chains in Program's areas.

Key Details

Project Details

  • P164184

  • Active

  • Jeanne Coulibaly Y epse Oyolola , Jeremy Strauss, Mariama Altine Mahamane

  • Republic of Guinea

  • Guinea

  • March 31, 2020

  • (as of board presentation)

    September 22, 2020

  • June 18, 2021

  • US$ 100.00 million

  • A

  • November 14, 2024

  • January 31, 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 50.00
Borrower/Recipient 2.00
Local Govts. (Prov., District, City) of Borrowing Country 5.00
IDA Grant 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 107.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 16, 2024 IDA-D7130 Loan Disb 280,822.72
Jun 28, 2024 IDA-67710 Loan Disb 3,222,258.00
Jun 28, 2024 IDA-D7130 Loan Disb 267,749.75
Jun 28, 2024 IDA-D7130 Loan Disb 238,862.11
Jun 28, 2024 IDA-D7130 Loan Disb 2,030,266.00
Jun 28, 2024 IDA-D7130 Loan Disb 253,651.62
May 7, 2024 IDA-D7130 Loan Disb 213,606.81
Feb 23, 2024 IDA-D7130 Loan Disb 265,406.03
Aug 9, 2024 IDA-D7130 Loan Disb 766,628.75
Aug 8, 2024 IDA-D7130 Loan Disb 709,174.75
Jan 29, 2024 IDA-D7130 Loan Disb 286,191.20
Sep 22, 2020 IDA-67710 Loan Commitment 50,000,000.00
Sep 22, 2020 IDA-D7130 Loan Commitment 50,000,000.00
Jan 29, 2024 IDA-D7130 Loan Disb 355,029.34
Sep 28, 2023 IDA-D7130 Loan Disb 703,949.50
Dec 4, 2023 IDA-D7130 Loan Disb 423,658.60
Nov 7, 2023 IDA-D7130 Loan Disb 121,010.86
Oct 25, 2023 IDA-D7130 Loan Disb 112,749.52
Dec 29, 2023 IDA-D7130 Loan Disb 294,092.97
Dec 8, 2023 IDA-D7130 Loan Disb 1,107,361.90
Nov 16, 2023 IDA-D7130 Loan Disb 583,225.40
Jun 8, 2023 IDA-D7130 Loan Disb 1,000,000.00
Jun 26, 2023 IDA-D7130 Loan Disb 312,111.06
Jul 27, 2023 IDA-D7130 Loan Disb 61,849.45
Jun 27, 2023 IDA-D7130 Loan Disb 4,000,000.00
Sep 18, 2023 IDA-D7130 Loan Disb 108,007.23
Jun 1, 2023 IDA-D7130 Loan Disb 164,262.90
Jan 12, 2023 IDA-D7130 Loan Disb 278,806.03
Dec 20, 2022 IDA-D7130 Loan Disb 502,400.00
Mar 30, 2023 IDA-D7130 Loan Disb 128,860.34
Nov 21, 2022 IDA-D7130 Loan Disb 834,637.25
Aug 25, 2021 IDA-D7130 Loan Disb 1,659,792.40
Jun 18, 2021 IDA-D7130 Loan Disb 851,520.60
Mar 28, 2024 IDA-D7130 Loan Disb 319,334.12
Feb 26, 2024 IDA-D7130 Loan Disb 3,452,910.00
Jul 12, 2024 IDA-67710 Loan Disb 7,605,000.00
May 20, 2024 IDA-D7130 Loan Disb 68,231.31

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-31
Procurement Moderately Satisfactory 2024-10-31
Project Management Moderately Satisfactory 2024-10-31
Progress towards achievement of PDO Moderately Satisfactory 2024-10-31
Procurement Moderately Satisfactory 2024-10-31
Monitoring and Evaluation Moderately Satisfactory 2024-10-31
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-31
Monitoring and Evaluation Moderately Satisfactory 2024-10-31
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-31
Financial Management Moderately Unsatisfactory 2024-10-31
Financial Management Moderately Unsatisfactory 2024-10-31
Project Management Moderately Satisfactory 2024-10-31

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of jobs created along the agricultural value-chainsValue0.00450.0024000.00
    DateDecember 31, 2020December 4, 2023January 31, 2029
    Comment
  • of which womenValue0.00100.0012000.00
    DateMarch 2, 2020December 4, 2023January 31, 2029
    Comment
  • Number of farmers or rural households provided with commercial opportunities in agricultural value-chainsValue0.004268.00145000.00
    DateMarch 2, 2020December 4, 2023January 31, 2029
    Comment
  • of which womenValue0.001533.0072000.00
    DateMarch 2, 2020December 4, 2023January 31, 2029
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Firms benefiting from private sector initiativesValue0.003.0055.00
    DateMarch 2, 2020December 4, 2023January 31, 2026
    Comment
  • Roads rehablitatedValue0.000.00800.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Number of reforms and policies prepared under the ProjectValue0.000.002.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Amount of private investments in commercial agriculture mobilized through Program's support (US$)Value0.000.00120000000.00
    DateMarch 2, 2020December 4, 2023January 31, 2028
    Comment
  • Number of market and logistics infrastructures built or rehabilitated under the project and operated efficientlyValue0.000.005.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Number of operationnal interprofessionnal value-chain associationsValue0.002.002.00
    DateNovember 25, 2019December 4, 2024January 31, 2026
    Comment
  • Number of private investments supported by the DFF with climate-resilient investmentsValue0.003.00300.00
    DateApril 1, 2020December 4, 2023January 31, 2026
    Comment
  • Number of beneficiaries of market infrastructuresValue0.000.005000.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Number of accredited laboratories for microbiological and chemical analyses created or upgraded with project supportValue0.000.002.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Satisfactory rate of beneficiaries from the Project's assets and servicesValue0.000.0080.00
    DateNovember 25, 2019December 4, 2023January 31, 2026
    Comment
  • Farmers reached with agricultural assets or servicesValue0.004268.007000.00
    DateMarch 2, 2020December 4, 2023January 31, 2026
    Comment
  • of which womenValue0.000.000.00
    Date
    Comment
  • Increase in volume of agri-food products commercialized by project supported beneficiariesValue0.000.00130000.00
    DateMarch 2, 2020December 4, 2023January 31, 2028
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.00800.00
    Date
    Comment
  • Number of women trained on business capacitiesValue0.00100.00600.00
    DateDecember 4, 2019December 4, 2023January 31, 2026
    Comment
  • of which volumes exportedValue0.000.0032000.00
    DateMarch 2, 2020December 4, 2023January 31, 2028
    Comment
  • Number of new agribusinesses led by womenValue0.000.00180.00
    DateDecember 4, 2019December 4, 2023January 31, 2026
    Comment