P164190
Closed
Federica Ranghieri , Naif Abu-Lohom, Abdulhakim Al-Aghbari
United Nations Office for Project Services (UNOPS)
Yemen, Republic of
December 6, 2017
(as of board presentation)
November 2, 2017
November 15, 2017
US$ 150.00 million
United Nations Office for Project Services (UNOPS)
2018
US$ 150.00 million
B
July 12, 2023
June 30, 2021
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 2, 2017 | IDA-D2450 | Loan Commitment | 150,000,000.00 |
Sep 4, 2022 | IDA-D2450 | Loan Cancel | 771.41 |
May 10, 2021 | IDA-D2450 | Loan Disb | 124,719.26 |
Dec 10, 2019 | IDA-D2450 | Loan Disb | 26,351,936.00 |
Jan 17, 2018 | IDA-D2450 | Loan Disb | 35,415,044.00 |
Apr 5, 2019 | IDA-D2450 | Loan Disb | 69,244,200.00 |
Dec 26, 2018 | IDA-D2450 | Loan Disb | 17,284,796.00 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2021-01-18 |
Monitoring and Evaluation | Satisfactory | 2021-01-18 |
Overall Implementation Progress (IP) | Satisfactory | 2021-01-18 |
Procurement | Satisfactory | 2021-01-18 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-01-18 |
Financial Management | Moderately Satisfactory | 2021-01-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-14-2021 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | High | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries with restored access to critical urban services | Value | 0.00 | 3050000.00 | 3000000.00 |
Date | August 1, 2017 | June 30, 2021 | November 3, 2020 | |
Comment |
Of which female beneficiaries | Value | 0.00 | 0.00 | 49.50 |
Date | August 1, 2017 | February 20, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Person-days of temporary employment created under the Project | Value | 0.00 | 1600000.00 | 1000000.00 |
Date | August 1, 2017 | June 30, 2021 | ||
Comment |
Tertiary municipal services activities implemented | Value | 0.00 | 146.00 | 130.00 |
Date | August 1, 2017 | June 30, 2021 | November 3, 2020 | |
Comment |
People provided access to rehabilitated water and sanitation services | Value | 0.00 | 1200000.00 | 1200000.00 |
Date | August 1, 2017 | June 30, 2021 | April 20, 2020 | |
Comment |
Roads rehablitated | Value | 0.00 | 266.00 | 240.00 |
Date | August 1, 2017 | June 30, 2021 | November 3, 2020 | |
Comment |
Energy generation supported through the Project | Value | 0.00 | 106572.00 | 40000.00 |
Date | August 1, 2017 | June 30, 2021 | ||
Comment |
Energy Saved in Megawatt Hour (MWh) | Value | 0.00 | 5000.00 | 0.00 |
Date | ||||
Comment |
CO2 Emissions Avoided through the Project | Value | 0.00 | 10000.00 | 0.00 |
Date | ||||
Comment |
Cities in which beneficiary consultation informed activity prioritization | Value | 0.00 | 10.00 | 8.00 |
Date | August 1, 2017 | June 30, 2021 | ||
Comment |
Activities informed by women's participation in beneficiary consultations | Value | 0.00 | 0.00 | 30.00 |
Date | August 1, 2017 | February 20, 2018 | ||
Comment |
Percentage of project financing executed by local contractors or suppliers | Value | 0.00 | 99.00 | 99.00 |
Date | August 1, 2017 | June 30, 2021 | April 20, 2020 | |
Comment |