Financier | Commitments |
---|---|
IDA Grant | 5.00 |
P164321
Closed
Cornelius Fleischhaker
Democratic Republic of São Tomé and Príncipe
May 16, 2019
(as of board presentation)
December 18, 2019
December 20, 2019
US$ 6.00 million
Ministry of Planning, Finance, and Blue Economy
2020
US$ 5.00 million
N/A
April 19, 2023
December 31, 2020
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 5.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 5.00 |
IBRD + IDA Commitment | 5.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 6.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 18, 2019 | IDA-D5450 | Loan Commitment | 5,000,000.00 |
Dec 31, 2019 | IDA-D5450 | Loan Disb | 5,116,471.00 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-15-2022 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-12-2022 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | N/a |