Water Security and Resilience for the Valley of Mexico (PROSEGHIR)

Abstract*

The development objective of Water Security and Resilience for the Valley of Mexico Project are to improve the reliability of the Cutzamala System and strengthen the management of groundwater resources in the Valley of Mexico. This project has three components. 1) The first component, Improving Energy Efficiency and Resilience of the Cutzamala System, has the following sub-components: (i) Designing, Modernizing and Implementing Infrastructure Information...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project are to improve the reliability of the Cutzamala System and strengthen the management of groundwater resources in the Valley of Mexico

Key Details

Project Details

  • P164389

  • Closed

  • Jean-Martin Brault , Hector Serrano

  • United Mexican States

  • Mexico

  • November 1, 2017

  • (as of board presentation)

    February 27, 2020

  • June 1, 2022

  • US$ 120.00 million

  • B

  • December 20, 2023

  • December 31, 2024

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 120.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 120.00
IDA Commitment N/A
IBRD + IDA Commitment 120.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 120.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2024 IBRD-90490 Int Charges 9,571.75
Apr 12, 2023 IBRD-90490 Loan Disb 9,834,483.00
Mar 15, 2023 IBRD-90490 Int Charges 340.96
Sep 15, 2023 IBRD-90490 Int Charges 8,602.52
Mar 15, 2023 IBRD-90490 Int Charges 7,418.13
Sep 15, 2022 IBRD-90490 Int Charges 114,028.77
Sep 15, 2022 IBRD-90490 Int Charges 1,879.56
Sep 15, 2022 IBRD-90490 Loan Disb -300,000.00
Sep 15, 2022 IBRD-90490 Loan Disb 300,000.00
Jun 1, 2022 IBRD-90490 Loan Disb 300,000.00
Jun 1, 2022 IBRD-90490 Fee Charges 300,000.00
Sep 15, 2023 IBRD-90490 Loan Disb -9,834,483.00
Sep 15, 2023 IBRD-90490 Loan Disb 9,834,483.00
Sep 15, 2023 IBRD-90490 Int Charges 114.59
Sep 15, 2023 IBRD-90490 Int Charges 140,346.72
Sep 15, 2023 IBRD-90490 Int Charges 240,572.23
Mar 15, 2024 IBRD-90490 Int Charges 313,777.50
Mar 15, 2024 IBRD-90490 Int Charges 136,803.52
Mar 15, 2024 IBRD-90490 Int Charges 4,710.99
Mar 15, 2024 IBRD-90490 Int Charges 153.92
Feb 27, 2020 IBRD-90490 Loan Commitment 120,000,000.00
Mar 15, 2023 IBRD-90490 Int Charges 148,395.19

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Unsatisfactory 2025-01-02
Financial Management Moderately Satisfactory 2025-01-02
Monitoring and Evaluation Moderately Satisfactory 2025-01-02
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-01-02
Progress towards achievement of PDO Moderately Unsatisfactory 2025-01-02
Procurement Moderately Unsatisfactory 2025-01-02

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved reliability of the Cutzamala System for the delivery of water to the VMMA and the TMAValue82.0082.0090.00
    DateMarch 30, 2018December 18, 2023December 31, 2025
    Comment
  • Annual reporting on groundwater information (quantity and quality) being used for decision makingValueNoNoYes
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • SCADA system in place and using data from monitoring network.ValueNoNoYes
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Water balance updated for the Valley of MexicoValueNoNoYes
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Grievances resolved related to delivery of project benefits addressedValue0.000.0095.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Dam operation and maintenance and emergency plan prepared and adopted by CONAGUAValue0.000.008.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Aquifer model improved to include monthly variabilityValueNoNoYes
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Number of CONAGUA employees (female) who have completed trainingValue0.000.00300.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Dams rehabilitated under the Project.Value0.000.004.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Percentage of women expressing satisfaction with the technical and leadership trainingValue0.000.0080.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Engineering analysis and design of the pressurized transmission lineValueNoNoYes
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment
  • Improved dam safety in key Cutzamala damsValue0.000.001.00
    DateMarch 30, 2020December 18, 2023December 31, 2025
    Comment