Financier | Commitments |
---|---|
IDA Credit | 16.50 |
P164555
Active
Paul Prettitore , Caleb Johnson
Republic of Kosovo
August 15, 2018
(as of board presentation)
December 18, 2018
September 2, 2020
US$ 16.50 million
Ministry of Environment, Spatial Planning and Infrastructure,Kosovo Cadastral Agency
2019
US$ 16.50 million
B
March 15, 2024
August 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 16.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 16.50 |
IBRD + IDA Commitment | 16.50 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 16.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 18, 2018 | IDA-63540 | Loan Commitment | 16,500,000.00 |
Nov 15, 2021 | IDA-63540 | Int Charges | 409.83 |
May 15, 2022 | IDA-63540 | Int Charges | 764.22 |
May 15, 2022 | IDA-63540 | Int Charges | 611.36 |
Nov 15, 2022 | IDA-63540 | Int Charges | 860.20 |
Nov 15, 2022 | IDA-63540 | Int Charges | 860.20 |
Nov 15, 2022 | IDA-63540 | Int Charges | 688.15 |
Dec 28, 2021 | IDA-63540 | Loan Disb | 114,479.18 |
Feb 1, 2023 | IDA-63540 | Loan Disb | 379,857.25 |
May 15, 2023 | IDA-63540 | Int Charges | 1,720.83 |
May 15, 2023 | IDA-63540 | Int Charges | 1,720.83 |
May 15, 2023 | IDA-63540 | Int Charges | 1,376.64 |
Nov 15, 2023 | IDA-63540 | Int Charges | 2,318.65 |
Nov 15, 2023 | IDA-63540 | Int Charges | 2,318.65 |
Nov 15, 2023 | IDA-63540 | Int Charges | 1,854.89 |
May 15, 2024 | IDA-63540 | Loan Repay | 260,774.25 |
May 15, 2024 | IDA-63540 | Int Charges | 3,763.14 |
May 15, 2024 | IDA-63540 | Int Charges | 3,763.14 |
May 15, 2024 | IDA-63540 | Int Charges | 3,010.48 |
Feb 2, 2024 | IDA-63540 | Loan Disb | 680,928.94 |
Aug 7, 2024 | IDA-63540 | Loan Disb | 1,224,504.40 |
May 15, 2021 | IDA-63540 | Int Charges | 412.51 |
May 15, 2021 | IDA-63540 | Int Charges | 412.51 |
May 15, 2021 | IDA-63540 | Int Charges | 330.00 |
Dec 28, 2020 | IDA-63540 | Loan Disb | 145,478.73 |
Nov 15, 2021 | IDA-63540 | Int Charges | 512.29 |
Nov 15, 2021 | IDA-63540 | Int Charges | 512.29 |
May 15, 2022 | IDA-63540 | Int Charges | 764.22 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-14 |
Procurement | Moderately Satisfactory | 2024-10-14 |
Project Management | Moderately Satisfactory | 2024-10-14 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-10-14 |
Financial Management | Satisfactory | 2024-10-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-14 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of properties updated and registered in the digital cadastre register (after cadastre reconstruction) | Value | 0.00 | 0.00 | 300000.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of e-services implemented | Value | 0.00 | 3.00 | 3.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Target land area in priority cadastral zones with user or ownership rights recorded as a result of the Project | Value | 30.00 | 30.00 | 60.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of datasets available through the Geoportal | Value | 10.00 | 14.00 | 30.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
KCA strategy and business plan developed | Value | No | Yes | Yes |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of priority cadastral zones reconstructed as a result of the Project | Value | 174.00 | 174.00 | 302.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of external systems with which KCLIS-SOA is interoperable | Value | 0.00 | 10.00 | 4.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
User satisfaction with KCA and MCO services | Value | 0.00 | 51.00 | 70.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of cities for which inventory of utility data has been completed | Value | 0.00 | 0.00 | 3.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of annual hits on the NSDI Geoportal | Value | 3000.00 | 1500.00 | 4500.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of KCA/MCO and KPCVA staff receiving training | Value | 0.00 | 229.00 | 300.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of MCOs with building footprints captured for the building register | Value | 0.00 | 0.00 | 12.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of MCOs with digital archive completed | Value | 0.00 | 0.00 | 3.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Percentage of properties updated, validated, and registered in the name of women | Value | 16.80 | 19.66 | 20.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Address data (buildings entrances, internal addressing, floors and residential units) updated throughout Kosovo | Value | 0.00 | 0.00 | 10.00 |
Date | June 30, 2023 | December 7, 2023 | August 31, 2025 | |
Comment |
Percentage of cadastral zones undergoing CR with local participation on CR Commission | Value | 0.00 | 0.00 | 90.00 |
Date | April 1, 2019 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of tables with addresses of entry numbers placed in pending Municipalities | Value | 0.00 | 0.00 | 280000.00 |
Date | March 6, 2023 | December 7, 2023 | August 31, 2025 | |
Comment |
Number of tables with addresses of entry numbers placed in the Northern Municipalities | Value | 0.00 | 0.00 | 800.00 |
Date | March 6, 2023 | December 7, 2023 | August 31, 2025 | |
Comment |