Financier | Commitments |
---|---|
IDA Grant | 40.00 |
IDA Credit | 40.00 |
P164563
Closed
Sabine Beddies
Cabinet du Premier Ministre
May 29, 2018
(as of board presentation)
September 12, 2018
March 26, 2019
US$ 80.00 million
Executive Secretariat for the SDS Sahel Niger (SE/SDS Sahel-Niger)
2019
US$ 80.00 million
B
March 27, 2024
September 30, 2023
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 40.00 |
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 80.00 |
IBRD + IDA Commitment | 80.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 80.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 9, 2020 | IDA-D3690 | Loan Disb | 95,841.18 |
Jan 14, 2020 | IDA-D3690 | Loan Disb | 145,561.69 |
May 13, 2022 | IDA-63080 | Loan Disb | 1,572,070.40 |
Mar 30, 2022 | IDA-63080 | Loan Disb | 1,696,681.40 |
Oct 20, 2021 | IDA-D3690 | Loan Disb | 884,162.80 |
Nov 8, 2021 | IDA-D3690 | Loan Disb | 1,140,175.90 |
Oct 12, 2021 | IDA-D3690 | Loan Disb | 3,178,190.50 |
Apr 20, 2022 | IDA-63080 | Loan Disb | 897,658.90 |
Apr 20, 2022 | IDA-63080 | Loan Disb | 1,511,722.10 |
Jun 10, 2022 | IDA-63080 | Loan Disb | 401,867.78 |
Dec 14, 2021 | IDA-D3690 | Loan Disb | 1,146,931.00 |
May 27, 2022 | IDA-63080 | Loan Disb | 1,139,272.00 |
Jun 30, 2022 | IDA-63080 | Loan Disb | 1,584,542.90 |
May 6, 2021 | IDA-D3690 | Loan Disb | 937,530.44 |
Jun 25, 2021 | IDA-D3690 | Loan Disb | 860,279.40 |
Sep 21, 2021 | IDA-D3690 | Loan Disb | 1,195,955.50 |
Sep 21, 2021 | IDA-D3690 | Loan Disb | 916,484.70 |
Aug 18, 2021 | IDA-D3690 | Loan Disb | 1,639,686.60 |
Nov 17, 2021 | IDA-D3690 | Loan Disb | 1,490,644.10 |
Oct 29, 2021 | IDA-D3690 | Loan Disb | 2,355,316.50 |
Nov 19, 2020 | IDA-D3690 | Loan Disb | 907,466.06 |
Jun 16, 2021 | IDA-D3690 | Loan Disb | 2,361,515.50 |
Apr 13, 2021 | IDA-D3690 | Loan Disb | 499,784.90 |
Jul 21, 2021 | IDA-D3690 | Loan Disb | 1,058,934.50 |
May 25, 2021 | IDA-D3690 | Loan Disb | 1,261,623.20 |
Sep 21, 2020 | IDA-D3690 | Loan Disb | 127,172.87 |
Dec 30, 2020 | IDA-D3690 | Loan Disb | 242,140.38 |
Dec 3, 2020 | IDA-D3690 | Loan Disb | 2,668,527.80 |
Dec 3, 2020 | IDA-D3690 | Loan Disb | 159,378.44 |
Dec 9, 2020 | IDA-D3690 | Loan Disb | 307,491.90 |
Feb 16, 2021 | IDA-D3690 | Loan Disb | 386,837.00 |
Apr 29, 2020 | IDA-D3690 | Loan Disb | 102,377.94 |
Jun 12, 2020 | IDA-D3690 | Loan Disb | 639,477.30 |
May 19, 2020 | IDA-D3690 | Loan Disb | 96,042.95 |
Jun 23, 2020 | IDA-D3690 | Loan Disb | 368,460.38 |
Aug 19, 2020 | IDA-D3690 | Loan Disb | 236,665.16 |
Mar 26, 2019 | IDA-D3690 | Loan Disb | 700,163.80 |
Feb 25, 2022 | IDA-D3690 | Loan Disb | 459,771.10 |
Dec 30, 2022 | IDA-63080 | Loan Disb | 1,434,202.40 |
Apr 27, 2022 | IDA-63080 | Loan Disb | 980,553.94 |
Feb 15, 2022 | IDA-D3690 | Loan Disb | 988,813.20 |
Jun 6, 2019 | IDA-D3690 | Loan Disb | 1,717,799.90 |
Jun 6, 2019 | IDA-D3690 | Loan Disb | 1,717,799.90 |
Nov 6, 2019 | IDA-D3690 | Loan Disb | 111,671.21 |
Aug 26, 2019 | IDA-D3690 | Loan Disb | 562,156.40 |
Sep 18, 2019 | IDA-D3690 | Loan Disb | 324,300.10 |
Nov 22, 2019 | IDA-D3690 | Loan Disb | 146,418.77 |
Mar 4, 2020 | IDA-D3690 | Loan Disb | 110,547.62 |
Dec 31, 2019 | IDA-D3690 | Loan Disb | 91,336.39 |
Sep 12, 2018 | IDA-D3690 | Loan Commitment | 40,000,000.00 |
Sep 12, 2018 | IDA-63080 | Loan Commitment | 40,000,000.00 |
Jun 10, 2024 | IDA-63080 | Loan Disb | -1,284,852.80 |
Apr 30, 2024 | IDA-63080 | Int Charges | 2,403.08 |
Apr 30, 2024 | IDA-63080 | Int Charges | 2,403.08 |
Apr 30, 2024 | IDA-63080 | Int Charges | 106,439.91 |
Apr 30, 2024 | IDA-63080 | Int Charges | 106,439.91 |
Apr 30, 2024 | IDA-63080 | Int Charges | 121,432.10 |
Apr 30, 2024 | IDA-63080 | Int Charges | 121,432.10 |
Jun 26, 2023 | IDA-63080 | Loan Disb | 989,739.75 |
Jun 14, 2023 | IDA-63080 | Loan Disb | 1,543,913.60 |
Apr 14, 2023 | IDA-63080 | Loan Disb | 820,142.70 |
Apr 14, 2023 | IDA-63080 | Loan Disb | 606,083.25 |
Jan 13, 2023 | IDA-63080 | Loan Disb | 1,441,249.00 |
May 9, 2023 | IDA-63080 | Loan Disb | 2,339,811.80 |
Feb 15, 2023 | IDA-63080 | Int Charges | 1,529.93 |
Feb 15, 2023 | IDA-63080 | Int Charges | 1,529.93 |
Feb 15, 2023 | IDA-63080 | Int Charges | 58,052.95 |
Feb 15, 2023 | IDA-63080 | Int Charges | 58,052.95 |
Feb 9, 2023 | IDA-63080 | Loan Disb | 791,450.00 |
Dec 12, 2022 | IDA-63080 | Loan Disb | 4,026,940.80 |
Apr 14, 2023 | IDA-63080 | Loan Disb | 2,376,162.80 |
Dec 30, 2021 | IDA-D3690 | Loan Disb | 5,249,256.50 |
Dec 1, 2022 | IDA-63080 | Loan Disb | 1,454,798.60 |
Oct 18, 2022 | IDA-63080 | Loan Disb | 611,233.70 |
Sep 16, 2022 | IDA-63080 | Loan Disb | 1,077,883.50 |
Nov 14, 2022 | IDA-63080 | Loan Disb | 1,414,328.80 |
Aug 19, 2022 | IDA-63080 | Loan Disb | 1,444,413.50 |
Jan 26, 2022 | IDA-D3690 | Loan Disb | 561,009.60 |
Aug 15, 2022 | IDA-63080 | Int Charges | 17,170.81 |
Aug 15, 2022 | IDA-63080 | Int Charges | 17,170.81 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2023-09-30 |
Project Management | Satisfactory | 2023-09-30 |
Progress towards achievement of PDO | Satisfactory | 2023-09-30 |
Financial Management | Satisfactory | 2023-09-30 |
Monitoring and Evaluation | Satisfactory | 2023-09-30 |
Overall Implementation Progress (IP) | Satisfactory | 2023-09-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-27-2024 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-18-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries with improved access to community infrastructure | Value | 0.00 | 869940.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Beneficiaries with improved access to community infrastructure (Refugees) | Value | 0.00 | 244856.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Beneficiaries with improved access to community infrastructure (Women) | Value | 0.00 | 297305.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Beneficiaries with improved access to economic opportunities | Value | 0.00 | 77874.00 | 83500.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Beneficiaries with improved access to economic opportunities (Refugees) | Value | 0.00 | 31047.00 | 23500.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Beneficiaries with improved access to economic opportunities (Women) | Value | 0.00 | 34254.00 | 41750.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of municipal annual investment plans incorporating risk management aspects, including needs of refugees and host communities | Value | 0.00 | 15.00 | 0.00 |
Date | May 30, 2018 | September 1, 2023 | ||
Comment |
Number of direct beneficiaries | Value | 0.00 | 1126037.00 | 0.00 |
Date | August 31, 2018 | September 15, 2023 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Investments with functional O&M arrangements one year after completion | Value | 0.00 | 100.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Percentage of grievances registered, related to delivery of project benefits, are addressed | Value | 0.00 | 99.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Operationalization of MIS for enhanced data collection on forced displacement | Value | 0.00 | 0.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Number of beneficiaries provided with cash grants for agricultural production and other income-generating activities | Value | 0.00 | 77874.00 | 83500.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of beneficiaries employed through labor-intensive works | Value | 0.00 | 16070.00 | 15000.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of meetings of the Technical Committee of the Humanitarian-Development Nexus at inter-ministerial level | Value | 0.00 | 2.00 | 3.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of beneficiaries provided with cash grants for agricultural production and other income-generating activities (Refugees) | Value | 0.00 | 31047.00 | 23500.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of municipal councils consulting their refugee and local populations annually in developing their annual investment plans | Value | 0.00 | 15.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Number of beneficiaries provided with cash grants for agricultural production and other income-generating activities (Women) | Value | 0.00 | 34254.00 | 41750.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of beneficiaries employed through labor-intensive works (Refugees) | Value | 0.00 | 2331.00 | 3000.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of beneficiaries employed through labor-intensive works (Women) | Value | 0.00 | 2076.00 | 2300.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2021 | |
Comment |
Number of newly built or rehabilitated water distribution points | Value | 0.00 | 62.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Number of newly built or rehabilitated classrooms | Value | 0.00 | 148.00 | 148.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Share of beneficiaries interviewed that feel project investments reflected their needs | Value | 0.00 | 83.00 | 0.00 |
Date | March 29, 2022 | September 15, 2023 | ||
Comment |
Number of newly built or rehabilitated health facilities | Value | 0.00 | 20.00 | 0.00 |
Date | May 30, 2018 | September 15, 2023 | ||
Comment |
Number of cash grant recipients trained under the project | Value | 0.00 | 81310.00 | 83500.00 |
Date | April 1, 2021 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of newly built or rehabilitated other infrastructure | Value | 0.00 | 99.00 | 85.00 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of cash grant recipients trained under the project (Refugees) | Value | 0.00 | 2219100.00 | 0.00 |
Date | ||||
Comment |
Number of newly built or rehabilitated kilometer of rural roads | Value | 0.00 | 66.50 | 66.50 |
Date | May 30, 2018 | September 15, 2023 | June 1, 2022 | |
Comment |
Number of cash grant recipients trained under the project (Women) | Value | 0.00 | 4751.00 | 0.00 |
Date | ||||
Comment |