Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 56.00 |
BioCarbon Technical Assistance Trust Fund | 10.00 |
Borrowing Agency | 119.00 |
P164661
Active
Katharina Siegmann , Rosa Martinez
United Mexican States
November 23, 2017
(as of board presentation)
January 29, 2018
May 17, 2018
US$ 185.00 million
CONAFOR
2018
US$ 66.00 million
B
March 21, 2024
March 28, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 56.00 |
BioCarbon Technical Assistance Trust Fund | 10.00 |
Borrowing Agency | 119.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 56.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 56.00 |
Lending Instrument | |
---|---|
Grant Amount | 10.00 |
Total Project Cost** | 185.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2019 | IBRD-88250 | Int Charges | 13,249.27 |
Mar 15, 2019 | IBRD-88250 | Int Charges | 60,176.02 |
Mar 15, 2019 | IBRD-88250 | Int Charges | 125,653.19 |
Dec 18, 2020 | IBRD-88250 | Loan Disb | 6,821,910.50 |
Mar 15, 2024 | IBRD-88250 | Int Charges | 28,660.29 |
Mar 15, 2024 | IBRD-88250 | Int Charges | 1,843,349.50 |
Jan 29, 2018 | IBRD-88250 | Loan Commitment | 56,000,000.00 |
Mar 15, 2021 | IBRD-88250 | Int Charges | 36,715.40 |
Mar 15, 2021 | IBRD-88250 | Int Charges | 142,982.73 |
Sep 15, 2020 | IBRD-88250 | Loan Disb | 2,452,109.80 |
Sep 15, 2020 | IBRD-88250 | Int Charges | 45,799.77 |
Sep 15, 2020 | IBRD-88250 | Int Charges | 151,954.20 |
Jun 12, 2020 | IBRD-88250 | Loan Disb | 1,538,768.10 |
Mar 23, 2020 | IBRD-88250 | Loan Disb | 6,836,194.50 |
Mar 15, 2020 | IBRD-88250 | Int Charges | 54,627.55 |
Mar 15, 2020 | IBRD-88250 | Int Charges | 174,149.20 |
Sep 15, 2019 | IBRD-88250 | Int Charges | 58,404.24 |
Sep 15, 2019 | IBRD-88250 | Int Charges | 171,774.84 |
Mar 15, 2022 | IBRD-88250 | Int Charges | 745.98 |
Mar 15, 2022 | IBRD-88250 | Int Charges | 21,914.18 |
Mar 15, 2022 | IBRD-88250 | Int Charges | 188,827.80 |
Mar 15, 2022 | IBRD-88250 | Int Charges | 240.94 |
Apr 26, 2022 | IBRD-88250 | Loan Disb | 2,658,416.50 |
Sep 15, 2021 | IBRD-88250 | Int Charges | 29,839.27 |
Sep 15, 2021 | IBRD-88250 | Int Charges | 165,872.62 |
Sep 3, 2021 | IBRD-88250 | Loan Disb | 2,931,439.50 |
May 17, 2021 | IBRD-88250 | Loan Disb | 3,432,369.00 |
Apr 14, 2023 | IBRD-88250 | Loan Disb | 654,220.60 |
Feb 3, 2023 | IBRD-88250 | Loan Disb | 2,559,148.50 |
Mar 30, 2023 | IBRD-88250 | Loan Disb | 327,906.44 |
Dec 7, 2022 | IBRD-88250 | Loan Disb | 2,016,848.10 |
Sep 26, 2022 | IBRD-88250 | Loan Disb | 4,193,659.00 |
Sep 15, 2022 | IBRD-88250 | Int Charges | 16,657.89 |
Sep 15, 2022 | IBRD-88250 | Int Charges | 425,582.78 |
Dec 21, 2021 | IBRD-88250 | Loan Disb | 4,492,040.00 |
Dec 21, 2022 | IBRD-88250 | Loan Disb | 2,532,868.50 |
Jun 26, 2023 | IBRD-88250 | Loan Disb | 326,220.06 |
Sep 15, 2023 | IBRD-88250 | Int Charges | 35,538.82 |
Sep 15, 2023 | IBRD-88250 | Int Charges | 1,653,844.90 |
Sep 15, 2023 | IBRD-88250 | Int Charges | 701.14 |
Sep 15, 2023 | IBRD-88250 | Int Charges | 398.26 |
Mar 15, 2023 | IBRD-88250 | Int Charges | 49,486.32 |
Mar 15, 2023 | IBRD-88250 | Int Charges | 7,238.81 |
Mar 15, 2023 | IBRD-88250 | Int Charges | 1,283,136.60 |
Sep 23, 2019 | IBRD-88250 | Loan Disb | 2,198,142.80 |
May 17, 2018 | IBRD-88250 | Loan Disb | 140,000.00 |
May 17, 2018 | IBRD-88250 | Fee Charges | 140,000.00 |
Sep 15, 2018 | IBRD-88250 | Int Charges | 1,510.49 |
Sep 15, 2018 | IBRD-88250 | Int Charges | 35,244.84 |
Aug 10, 2018 | IBRD-88250 | Loan Disb | 4,470,929.50 |
Nov 14, 2018 | IBRD-88250 | Loan Disb | 4,262,188.50 |
May 13, 2019 | IBRD-88250 | Loan Disb | 1,154,619.50 |
Mar 15, 2019 | IBRD-88250 | Int Charges | 1,102.42 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2024-12-26 |
Progress towards achievement of PDO | Satisfactory | 2024-12-26 |
Procurement | Satisfactory | 2024-12-26 |
Financial Management | Satisfactory | 2024-12-26 |
Monitoring and Evaluation | Satisfactory | 2024-12-26 |
Overall Implementation Progress (IP) | Satisfactory | 2024-12-26 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Area of forest landscape managed according to defined criteria | Value | 0.00 | 2936443.00 | 2498509.00 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |
Share of target beneficiaries that increase their Index of forest entrepreneurship by at least one range | Value | 0.00 | 85.00 | 70.00 |
Date | July 2, 2018 | December 31, 2022 | September 30, 2024 | |
Comment |
Share of target beneficiaries with rating “Satisfied" or above on project interventions | Value | 0.00 | 82.00 | 70.00 |
Date | July 2, 2018 | December 31, 2022 | September 30, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area under sustainable landscape management practices | Value | 0.00 | 1431774.00 | 992576.00 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |
Emissions Reduction Program prepared and submitted to the BioCarbon Fund | Value | No | Yes | Yes |
Date | July 2, 2018 | March 31, 2023 | July 30, 2021 | |
Comment |
Forest area brought under management plans | Value | 0.00 | 533968.00 | 598808.00 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |
Knowledge products prepared on entrepreneurship and forest management | Value | 0.00 | 30.00 | 35.00 |
Date | July 2, 2018 | June 30, 2023 | September 30, 2024 | |
Comment |
Number of beneficiaries implementing sustainable forest management schemes | Value | 0.00 | 172668.00 | 191008.00 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |
Inter-institutional coordination mechanisms in place to improve landscape level governance | Value | 0.00 | 5.00 | 5.00 |
Date | July 2, 2018 | June 30, 2023 | September 30, 2024 | |
Comment |
Share of target territory that meets the criteria of innovative landscape level management schemes | Value | 0.00 | 87.00 | 72.00 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |
Net greenhouse gas emissions | Value | 0.00 | 3068687.00 | -2940691.52 |
Date | July 2, 2018 | March 31, 2023 | March 31, 2023 | |
Comment |