Chad Rural Mobility and Connectivity Project

Abstract*

The development objective of the Rural Mobility and Connectivity Project for Chad is to improve and sustain access by rural populations to markets and basic social services in the project area. The project comprises of four components. The first component, rural roads rehabilitation and maintenance works consists of following sub-components: (i) rural roads rehabilitation works; (ii) community-based rural roads maintenance; (iii) studies and financing...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve and sustain access by rural populations to markets and basic social services in the Project Area.

Key Details

Project Details

  • P164747

  • Active

  • Ndeye Ba

  • Republic of Chad

  • Chad

  • July 26, 2018

  • (as of board presentation)

    December 19, 2018

  • June 13, 2019

  • US$ 30.00 million

  • Ministère des Infrastructures, du Transport, et du Désenclavement

  • Western and Central Africa

  • 2019

  • US$ 30.00 million

  • B

  • April 2, 2024

  • June 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 30.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 30.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 2, 2023 IDA-D4170 Loan Disb 84,670.98
Dec 8, 2022 IDA-D4170 Loan Disb 170,170.33
Jul 14, 2023 IDA-D4170 Loan Disb 611,713.94
Jun 29, 2023 IDA-D4170 Loan Disb 221,228.70
Nov 15, 2019 IDA-D4170 Loan Disb 215,870.60
Jun 13, 2019 IDA-D4170 Loan Disb 247,786.58
Mar 31, 2020 IDA-D4170 Loan Disb 159,386.34
Mar 31, 2020 IDA-D4170 Loan Disb 78,769.65
Mar 13, 2020 IDA-D4170 Loan Disb 100,041.32
Sep 11, 2019 IDA-D4170 Loan Disb 883,540.90
May 7, 2020 IDA-D4170 Loan Disb 51,971.88
Jul 27, 2020 IDA-D4170 Loan Disb 67,515.25
Aug 3, 2020 IDA-D4170 Loan Disb 186,348.69
Jun 1, 2020 IDA-D4170 Loan Disb 594,950.25
Jun 11, 2020 IDA-D4170 Loan Disb 184,276.31
Jul 1, 2020 IDA-D4170 Loan Disb 15,000,000.00
Oct 8, 2020 IDA-D4170 Loan Disb 49,374.76
Oct 16, 2020 IDA-D4170 Loan Disb 121,985.87
Oct 14, 2020 IDA-D4170 Loan Disb 140,438.22
Jan 29, 2021 IDA-D4170 Loan Disb 92,884.59
Mar 18, 2021 IDA-D4170 Loan Disb 148,372.00
Feb 5, 2021 IDA-D4170 Loan Disb 90,442.63
Feb 5, 2021 IDA-D4170 Loan Disb 34,391.21
Mar 1, 2021 IDA-D4170 Loan Disb 432,764.25
Jun 28, 2023 IDA-D4170 Loan Disb 836,886.25
Oct 6, 2023 IDA-D4170 Loan Disb 56,324.29
Nov 29, 2023 IDA-D4170 Loan Disb 840,390.20
Oct 11, 2023 IDA-D4170 Loan Disb 169,292.08
Jan 16, 2024 IDA-D4170 Loan Disb 642,490.40
Jan 29, 2024 IDA-D4170 Loan Disb 79,941.21
May 24, 2024 IDA-D4170 Loan Disb 169,834.61
Sep 28, 2023 IDA-D4170 Loan Disb 120,623.28
Sep 28, 2023 IDA-D4170 Loan Disb 132,566.81
Apr 26, 2024 IDA-D4170 Loan Disb 325,732.56
Apr 16, 2021 IDA-D4170 Loan Disb 641,876.70
Apr 16, 2021 IDA-D4170 Loan Disb 380,066.53
Nov 29, 2021 IDA-D4170 Loan Disb 71,173.41
Nov 29, 2021 IDA-D4170 Loan Disb 77,414.12
Dec 19, 2018 IDA-D4170 Loan Commitment 30,000,000.00
Dec 15, 2020 IDA-D7580 Loan Commitment 15,000,000.00
Aug 3, 2023 IDA-D4170 Loan Disb 254,392.75
Sep 6, 2023 IDA-D4170 Loan Disb -818,191.70
Sep 19, 2023 IDA-D4170 Loan Disb 99,420.19
Jun 28, 2023 IDA-D4170 Loan Disb 659,302.56
Jul 20, 2021 IDA-D4170 Loan Disb 287,888.22
Apr 21, 2021 IDA-D4170 Loan Disb -126,218.80
Apr 21, 2021 IDA-D4170 Loan Disb 123,894.33
Dec 23, 2021 IDA-D4170 Loan Disb 144,607.08
Mar 7, 2023 IDA-D4170 Loan Disb 21,344.11
Mar 3, 2023 IDA-D4170 Loan Disb 170,205.44
Oct 21, 2021 IDA-D4170 Loan Disb 212,156.45
Nov 29, 2021 IDA-D4170 Loan Disb 117,269.41
Aug 31, 2021 IDA-D4170 Loan Disb 121,106.44
Sep 13, 2021 IDA-D4170 Loan Disb 102,957.25
Sep 8, 2021 IDA-D4170 Loan Disb 40,027.91
Sep 8, 2021 IDA-D4170 Loan Disb 28,713.08
Sep 8, 2021 IDA-D4170 Loan Disb 51,921.31
May 27, 2022 IDA-D4170 Loan Disb 84,004.20
May 3, 2022 IDA-D4170 Loan Disb 201,527.72
May 3, 2022 IDA-D4170 Loan Disb 85,331.08
Jan 24, 2022 IDA-D4170 Loan Disb 204,518.34
Aug 17, 2022 IDA-D4170 Loan Disb 114,313.01
Aug 17, 2022 IDA-D4170 Loan Disb 179,592.05
Aug 17, 2022 IDA-D4170 Loan Disb 82,758.81
Dec 8, 2021 IDA-D4170 Loan Disb 208,529.10
Dec 1, 2022 IDA-D4170 Loan Disb 33,291.44
Dec 1, 2022 IDA-D4170 Loan Disb 67,190.52
Jul 15, 2024 IDA-D7580 Loan Disb 218,519.75
Jun 24, 2024 IDA-D7580 Loan Disb 843,591.25
Jun 25, 2024 IDA-D7580 Loan Disb 490,596.90

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-28
Procurement Moderately Satisfactory 2024-10-28
Project Management Moderately Satisfactory 2024-10-28
Financial Management Moderately Satisfactory 2024-10-28
Monitoring and Evaluation Moderately Satisfactory 2024-10-28
Overall Safeguards Rating Moderately Satisfactory 2024-10-28
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with access to an all season roadValue12582.0069007.00159156.00
    DateOctober 1, 2018April 2, 2024June 30, 2025
    Comment
  • Proportion of improved roads under routine maintenanceValue0.000.00100.00
    DateDecember 1, 2018April 2, 2024June 30, 2025
    Comment
  • Travel time along the improved roadsValue165.0090.0060.00
    DateNovember 1, 2018April 2, 2024January 30, 2025
    Comment
  • Travel time along Moissala-Bedaya (75 kms)Value264.0095.0090.00
    DateDecember 18, 2018April 2, 2024June 30, 2025
    Comment
  • Travel time along Moïssala - Démbo - Maya - Frontière RCA (50.5 kms)Value170.00170.0060.00
    DateOctober 16, 2019April 2, 2024June 30, 2025
    Comment
  • Travel time along Banda - Moussafoyo – Miavélé (41.5 kms)Value115.00115.0051.00
    DateOctober 16, 2019April 2, 2024June 30, 2025
    Comment
  • Travel time along Danamadji – Moussafoyo (22 kms)Value78.0078.0029.00
    DateOctober 16, 2019April 2, 2024June 30, 2025
    Comment
  • Travel time along Danamadji - Sakogongo – Boro (22 kms)Value0.000.0027.00
    DateOctober 16, 2019April 2, 2024June 30, 2025
    Comment
  • Number of schools and health centers reached by an improved roadValue0.0023.0076.00
    DateNovember 1, 2018April 2, 2024June 30, 2025
    Comment
  • Number of markets reached by an improved roadValue3.0023.0080.00
    DateDecember 24, 2018April 2, 2024June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Roads rehablitatedValue0.0075.00211.00
    DateNovember 1, 2018April 2, 2024June 25, 2025
    Comment
  • Percentage of rural roads inventoriedValue10.0050.00100.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • People benefiting from food kitsValue0.00433460.00433460.00
    DateApril 30, 2020April 2, 2024June 30, 2025
    Comment
  • Road users trained and sensitized in road safetyValue0.00737.002300.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • Roads rehabilitated - ruralValue0.000.000.00
    Date
    Comment
  • Proportion of villages that have implemented physical road safety measuresValue0.0028.00100.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • Roads rehabilitated - non-ruralValue0.000.000.00
    Date
    Comment
  • Percentage of construction costs allocated to climate change adaptation measuresValue0.0013.005.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • Small common facilities provided and built for womenValue0.000.0050.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • Percentage of women employed in the rehabilitation works and routine road maintenanceValue0.002.0020.00
    DateJuly 26, 2018April 2, 2024June 30, 2025
    Comment
  • Number of people reached by a GBV awareness campaignValue0.001000.005000.00
    DateNovember 1, 2019April 2, 2024June 30, 2025
    Comment
  • Number of Intermediate Means of Transport providedValue0.000.00200.00
    DateNovember 1, 2018April 2, 2024June 30, 2025
    Comment
  • Number of Intermediate Means of Transport provided to womenValue0.000.0060.00
    DateOctober 1, 2020April 2, 2024June 30, 2025
    Comment
  • Percentage of beneficiaries satisfied with road improvement (disaggregated by gender and age)Value0.0075.0075.00
    DateNovember 1, 2019April 2, 2024June 30, 2025
    Comment
  • Percentage of grievances addressed through the grievance redress mechanisms within two (2) months of their registrationValue0.00100.00100.00
    DateNovember 1, 2019April 2, 2024June 30, 2025
    Comment
  • Percentage of workers that have signed a code of conductValue0.00100.00100.00
    DateSeptember 2, 2019April 2, 2024June 30, 2025
    Comment
  • Bridge between Bedaya and Moissala at PK 1+750 is constructed with climate resilience and road safety standardsValueNoNoYes
    DateJune 23, 2023April 2, 2024June 30, 2025
    Comment