Tanzania Roads to Inclusion and Socioeconomic Opportunities (RISE) Project

Abstract*

The RISE project will address some of the urgent challenges in the rural road subsector in Tanzania. The RISE project is proposed as a combination of mutually reinforcing investments and institutional strengthening activities. It is expected that the RISE will set the foundation for the management of rural roads in Tanzania in the medium term from the policy, planning and implementation capacity perspectives and create a model for a national program...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve rural road access and provide employment opportunities for population in selected rural areas and build capacity in the sustainable management of rural roads incorporating community engagement approaches.

Key Details

Project Details

  • P164920

  • Active

  • Sofia Guerrero Gamez , Gladness Rwejumura

  • United Republic of Tanzania

  • Tanzania

  • March 24, 2020

  • (as of board presentation)

    May 27, 2021

  • December 18, 2019

  • US$ 350.00 million

  • Tanzania National Roads Agency (TANROADS),Tanzania Rural and Urban Roads Agency (TARURA)

  • Eastern and Southern Africa

  • 2021

  • US$ 300.00 million

  • N/A

  • April 14, 2024

  • June 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 300.00
Borrower/Recipient 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 300.00
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 350.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 27, 2021 IDA-68670 Loan Commitment 300,000,000.00
May 16, 2023 IDA-68670 Loan Disb 8,496,213.00
Sep 1, 2023 IDA-68670 Int Charges 69.80
Sep 1, 2023 IDA-68670 Int Charges 55,912.38
Sep 1, 2023 IDA-68670 Int Charges 55,912.38
Jun 26, 2024 IDA-68670 Loan Disb 11,153,000.00
Jun 4, 2024 IDA-68670 Loan Disb 9,436,347.00
Aug 9, 2024 IDA-68670 Loan Disb 862,165.00
Aug 27, 2024 IDA-68670 Loan Disb 9,412,541.00
Mar 1, 2024 IDA-68670 Int Charges 68,878.34
Mar 1, 2024 IDA-68670 Int Charges 68,878.34
Mar 5, 2024 IDA-68670 Loan Disb 9,533,870.00
May 29, 2024 IDA-68670 Loan Disb 3,982,055.00
Mar 1, 2024 IDA-68670 Int Charges 2.10
Mar 1, 2024 IDA-68670 Int Charges 2.10
Mar 25, 2022 IDA-68670 Loan Disb 4,407,852.00
Sep 1, 2022 IDA-68670 Int Charges 13,520.78
Sep 1, 2022 IDA-68670 Int Charges 13,520.78
Dec 27, 2022 IDA-68670 Loan Disb 5,500,000.00
Dec 2, 2022 IDA-68670 Loan Disb 238,452.06
Mar 1, 2023 IDA-68670 Int Charges 290.58
Mar 1, 2023 IDA-68670 Int Charges 290.58
Jan 18, 2023 IDA-68670 Loan Disb 18,087.86
Mar 1, 2023 IDA-68670 Int Charges 23,433.27
Mar 1, 2023 IDA-68670 Int Charges 23,433.27
Sep 1, 2023 IDA-68670 Int Charges 69.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2024-08-05
Overall Implementation Progress (IP) Moderately Satisfactory 2024-08-05
Procurement Moderately Satisfactory 2024-08-05
Project Management Moderately Satisfactory 2024-08-05
Progress towards achievement of PDO Moderately Satisfactory 2024-08-05
Monitoring and Evaluation Moderately Satisfactory 2024-08-05

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of rural population within 5km access to good condition roadsValue48.0048.0058.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • “People-centered” design approach for rural road developmentValueNoNoYes
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Civil works jobs created (person-year)Value0.00171.0035000.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Share of district rural roads in good and fair condition in the Project areaValue45.0045.0048.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Share of regional rural roads in good and fair condition in the project area.Value68.0068.0070.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Kilometers of rural roads improved with climate resilient approachesValue0.000.00535.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Number of people employed under CBRM contracts (person-year)Value0.000.0019000.00
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • National Rural Roads PlanValueNoNoYes
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Emergency Management Protocol operationalized by TARURA and TANROADSValueNoYesYes
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • Approval of TARURA Business Modernization PlanValueNoNoYes
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • Kilometers of regional roads improved with climate resilient approachesValue0.000.00135.00
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • Percentage of people employed under CBRM contracts that are womenValue0.000.0012.50
    Date
    Comment
  • Approval of TARURA's Gender PolicyValueNoNoYes
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • Kilometers of rural district roads improved with climate resilient approachesValue0.000.00400.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Percentage of people employed in CBRM that are trained on life skillsValue0.000.00100.00
    Date
    Comment
  • Kilometres of rural district roads that received routine maintenance with community based approachesValue0.000.0023000.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Kilometers of roads that received bottleneck improvements (cumulative)Value0.000.004500.00
    DateMarch 15, 2021March 18, 2024April 28, 2027
    Comment
  • Construction workers on project site who have signed the code of conduct (CoC) and attended the CoC trainingValue0.00171.00100.00
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • Road Safety Data Collection System for rural district roadsValueNoNoYes
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment
  • System to receive and log grievances related to design, construction and operations of development projects, including GBV, within the stipulated services standardsValueNoYesYes
    DateJanuary 6, 2020March 18, 2024April 28, 2027
    Comment