Iraq Emergency Social Stabilization and Resilience Project

Abstract*

The development objective of the Emergency Social Stabilization Project for Iraq is to: (i) increase livelihood opportunities in liberated areas; (ii) increase access to psychosocial services in liberated areas; and (iii) strengthen the systems to expand the provision of social safety nets. This project has three components. First component, Cash for Work (CfW), Social Support, and Livelihood Opportunities is to increase access to short‐term employment...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to: (i) increase livelihood opportunities in liberated areas; (ii) increase access to psychosocial services in liberated areas; and (iii) strengthen the systems to expand the provision of social safety nets.

Key Details

Project Details

  • P165114

  • Closed

  • Haleem Al-Kazali , Khalid Moheyddeen

  • Ministry of Finance

  • Iraq

  • February 16, 2018

  • (as of board presentation)

    April 5, 2018

  • July 11, 2018

  • US$ 200.00 million

  • Ministry of Labor and Social Affairs (MOLSA)

  • Middle East and North Africa

  • 2018

  • US$ 200.00 million

  • B

  • January 29, 2024

  • April 30, 2021

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 200.00
IDA Commitment N/A
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 200.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 1, 2023 IBRD-88480 Loan Repay 138,892.70
May 1, 2024 IBRD-88480 Int Charges 506.92
May 1, 2024 IBRD-88480 Int Charges 80,794.94
May 1, 2024 IBRD-88480 Loan Repay 138,892.70
Apr 5, 2018 IBRD-88480 Loan Commitment 200,000,000.00
May 1, 2022 IBRD-88480 Int Charges 10,920.12
May 1, 2022 IBRD-88480 Int Charges -532.34
May 1, 2022 IBRD-88480 Int Charges 532.34
Nov 28, 2022 IBRD-88480 Int Charges 41,048.47
May 1, 2023 IBRD-88480 Int Charges 2,361.11
May 1, 2023 IBRD-88480 Int Charges 69,428.55
May 1, 2023 IBRD-88480 Loan Repay 138,892.70
Nov 14, 2019 IBRD-88480 Loan Disb 7,312,524.50
Jun 26, 2019 IBRD-88480 Loan Disb 10,000,000.00
May 1, 2019 IBRD-88480 Int Charges 247,325.34
May 1, 2019 IBRD-88480 Int Charges 8,522.07
Nov 1, 2018 IBRD-88480 Int Charges 172,215.77
Nov 1, 2018 IBRD-88480 Int Charges 4,849.59
Jul 11, 2018 IBRD-88480 Loan Disb 500,000.00
Jul 11, 2018 IBRD-88480 Fee Charges 500,000.00
Nov 1, 2019 IBRD-88480 Int Charges 242,657.55
Nov 1, 2019 IBRD-88480 Int Charges 122,336.66
Nov 13, 2019 IBRD-88480 Loan Disb 6,687,475.50
May 1, 2020 IBRD-88480 Int Charges 219,577.34
May 1, 2020 IBRD-88480 Int Charges 298,668.22
Nov 1, 2020 IBRD-88480 Int Charges 220,573.78
Nov 1, 2020 IBRD-88480 Int Charges 174,058.90
Mar 15, 2021 IBRD-88480 Loan Cancel 119,500,000.00
May 1, 2021 IBRD-88480 Int Charges 178,902.40
May 1, 2021 IBRD-88480 Int Charges 103,471.68
Aug 3, 2021 IBRD-88480 Loan Disb -9,950,538.00
Nov 1, 2021 IBRD-88480 Int Charges 38,469.17
Nov 1, 2021 IBRD-88480 Int Charges 45,375.39
Nov 1, 2021 IBRD-88480 Int Charges 59,982.87
Aug 3, 2021 IBRD-88480 Loan Disb -5,875,812.00
Aug 6, 2021 IBRD-88480 Loan Disb -5,895,796.00
Oct 31, 2021 IBRD-88480 Loan Cancel 77,722,144.00
Nov 1, 2023 IBRD-88480 Int Charges 80,319.18
Nov 1, 2023 IBRD-88480 Int Charges 1,194.45

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2021-03-18
Project Management Unsatisfactory 2021-03-18
Financial Management Unsatisfactory 2021-03-18
Monitoring and Evaluation Unsatisfactory 2021-03-18
Procurement Unsatisfactory 2021-03-18
Overall Implementation Progress (IP) Unsatisfactory 2021-03-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries receiving livelihood support, of which womenValue0.000.005000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries of social safety net programsValue0.000.001200000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries of social safety net programs - FemaleValue0.000.00600000.00
    DateApril 30, 2018April 30, 2018April 30, 2021
    Comment
  • Beneficiary households receiving Cash for Work supportValue0.000.00150000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries receiving direct counselingValue0.000.00150000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Share of beneficiaries included in the social registry from the poorest and second poorest quintilesValue0.000.0080.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries of conditional cash transfers receiving payments in a timely mannerValue0.000.0070.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiary households receiving Cash for Work support, of which female headed householdsValue0.000.0075000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries receiving direct counseling, of which womenValue0.000.0050000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Average share of cash for work resources transferred as wagesValue0.000.0070.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries receiving direct counseling, of which returneesValue0.000.0020000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries receiving livelihood supportValue0.000.0012000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Beneficiaries receiving direct counseling, of which children (5-15 years)Value0.000.0050000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Person work days generated by the projectValue0.000.0010000000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Share of grievances resolved in accordance with service standardsValue0.000.0075.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Share of sampled beneficiaries expressing satisfaction with the cash for work programValue0.000.0080.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Person work days generated by the project, of which womenValue0.000.003000000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Sub-projects supported by the projectValue0.000.00600.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Social Service Counselors trainedValue0.000.003000.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Integrated Mental Health, Psychosocial Services and GBV Centers establishedValue0.000.005.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Average of social worker home visits required to register conditional cash transfer beneficiariesValue0.000.002.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Time to process conditional cash transfer payments, from registration to enrollmentValue0.000.001.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment
  • Share of beneficiaires of microfinance from the lowest and second lowest income quintilesValue0.000.0020.00
    DateApril 30, 2018March 1, 2021April 30, 2021
    Comment