Skip to Main Navigation

Building Statistical Capacities in the Ministry of Education

Development Objective

The objective of the Project is to strengthen the capacity of MINEDUC to collect, manage, analyze and use high-quality statistical information to design, implement and evaluate evidence-based interventions to address key sector challenges.

Key Details

Project Details

  • P165120

  • Closed

  • Enrique Alasino Massetti , Monica Yanez Pagans

  • Government of Guatemala

  • Guatemala

  • November 2, 2017

  • (as of board presentation)

    February 23, 2018

  • July 13, 2018

  • US$ 0.35 million

  • Department of Education Planning (DIPLAN), Ministry of Education

  • Latin America and Caribbean

  • 2018

  • US$ 0.35 million

  • C

  • May 21, 2022

  • March 31, 2020

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Trust Fund for Statistical Capacity Building 0.35

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.35
Total Project Cost** 0.35

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2019-09-26
Progress towards achievement of PDO Moderately Satisfactory 2019-09-26
Overall Moderable 2019-09-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-29-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • The plan includes a section on how to improve information management for indigenous populations.ValueNoYesYes
    DateFebruary 15, 2018August 15, 2019March 31, 2020
    Comment
  • An action plan to strengthen the statistical management in MINEDUC is prepared based on the diagnostic carried out.ValueNoYesYes
    DateFebruary 15, 2018August 15, 2019March 31, 2020
    Comment
  • EWS is strengthened with new predictors and evidence-based interventions incorporated into the design.ValueNoYesNo
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • New modules are collected and analyzed; including statistics disaggregated by gender and ethnicity.ValueNoYesYes
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of MINEDUC staff trained under the Project on how to collect, manage, analyze and/or use data related to indigenous peoples’challenges and concerns.Value0.0030.0038.00
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • MINEDUC's software for statistical management is updated and fully functional.ValueNoYesYes
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • Number of MINEDUC's staff trained under the project on how to collect, manage, analyze and/or use high-quality statistical information.Value0.0040.0038.00
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • MINEDUC formally adopts a "Good Practices in Statistical Information Management Manual"ValueNoYesNo
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • At least two evidence-based interventions to support the EWS designedValueNoYesYes
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment
  • New modules for data collection are developed and incorporated into SIRE, showing disaggregated data by gender and ethnicity.ValueNoYesYes
    DateFebruary 15, 2018December 31, 2019March 31, 2020
    Comment